1650 W FLORENCE AVE 90047

Certificate Information: 1650 W FLORENCE AVE 90047

Application / Permit
18010-10000-05189
Plan Check / Job No.
B18LA22895
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 5-story, 128-unit, TOC Tier 3, apartment building. 4-levels of Type VA over 1 level of Type 1A abv grade open parking garage
Permit Issued
Issued on 3/19/2020
Issuing Office
Metro
Current Status
CofO Issued on 3/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2018 APPLICANT
Assigned to Plan Check Engineer 11/30/2018 HERNAN ARREOLA
Corrections Issued 12/10/2018 HERNAN ARREOLA
Quality Review Completed 12/17/2018 BILL STUTSMAN
Building Plans Picked Up 12/18/2018 APPLICANT
Applicant returned to address corrections 4/30/2019 HERNAN ARREOLA
Applicant returned to address corrections 5/22/2019 HERNAN ARREOLA
Plan Check Approved 2/11/2020 BILL STUTSMAN
Issued 3/19/2020 LADBS
Permit Closed-Status Void 12/28/2021 JAMES POWERS
Re-Activate Permit 12/30/2021 JAMES POWERS
CofO in Progress 3/10/2022 JAMES POWERS
CofO Issued 3/10/2022 TED RIES
Permit Finaled 3/10/2022 TED RIES

Permit Application Clearance Information

Address approval Cleared 2/12/2019 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 3/5/2019 JEANIE LAM
Sewer availability Cleared 3/5/2019 JEANIE LAM
ZA Case Cleared 5/6/2019 JOE LUCKEY
Trees in Parkway Cleared 5/7/2019 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 5/8/2019 GILBERT URREA
Highway dedication Cleared 5/13/2019 ZIXUAN CHEN
Construction near power lines Cleared 5/24/2019 RIDWAN HARDY
Construction within easement Cleared 5/24/2019 RIDWAN HARDY
Green Code Cleared 5/30/2019 HERNAN ARREOLA
Density Bonus 12.22.A.31 Cleared 12/16/2019 DORIS KWOK
Low Impact Development Cleared 1/3/2020 MITESH PATEL
DAS Clearance Cleared 1/7/2020 HERNAN ARREOLA
Miscellaneous Cleared 1/7/2020 JOE LUCKEY
Miscellaneous Cleared 1/7/2020 JOE LUCKEY
Project located in CRA area Cleared 1/8/2020 GISELLE CORELLA
Fire Marshall Fire Life Safety Cleared 1/22/2020 VIDAL GARCIA
Miscellaneous Cleared 1/28/2020 JOE LUCKEY
Opn space landscape/Water mgmt Cleared 1/28/2020 JOE LUCKEY
Roof/Waste drainage to street Cleared 2/6/2020 MINA GRAIS
Building over 3-story or 36-ft Cleared 2/10/2020 CALOSHA APPROVED

Contact Information

Architect Kaliski,, John Ethan; Lic. No.: C17945 3780 WILSHIRE BLVD SUITE 300      LOS ANGELES, CA 90010
Contractor Mohrsaz Mike; Lic. No.: 910443-B 4448 AZALIA DRIVE      TARZANA, CA 91356
Engineer Javadi-Koma,, Shahram; Lic. No.: C69497 6701 ETON AVE APT 115      CANOGA PARK, CA 91303
Engineer Walter,, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 6/9/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/10/2020 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 6/23/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 6/24/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/25/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 7/6/2020 Partial Approval JAMES POWERS
Reinforced Masonry Frame 7/9/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/13/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 7/14/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/15/2020 Partial Approval JAMES POWERS
Reinforced Masonry Frame 7/15/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/17/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/17/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/22/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/24/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/24/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/27/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/27/2020 Partial Approval JAMES POWERS
Masonry Wall/Backfill 8/3/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/4/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 9/2/2020 Partial Approval NICK DANERI
Deputy Reinf. Concrete 9/8/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/13/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 10/26/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 10/29/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 11/4/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/5/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/6/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 11/6/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/25/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/8/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 12/22/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 1/6/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 1/7/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/7/2021 Partial Approval JAMES POWERS
Green Building Rough 1/7/2021 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 1/7/2021 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/1/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/9/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/11/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 2/22/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 2/25/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/25/2021 Partial Approval JAMES POWERS
Green Building Rough 3/1/2021 Approved JAMES POWERS
Verify Sprinkler Sign Off 3/1/2021 Not Ready for Inspection JAMES POWERS
Wood Frame 3/1/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 3/8/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/8/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 3/18/2021 Conditional Approval LANNY MERRICK
Deputy Wood Construction 3/22/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/24/2021 Partial Approval JAMES POWERS
Insulation 3/24/2021 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 4/8/2021 Not Ready for Inspection JAMES POWERS
Wood Frame 4/8/2021 Partial Approval JAMES POWERS
Insulation 4/16/2021 Partial Approval JAMES POWERS
Insulation 4/22/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 4/27/2021 Not Ready for Inspection JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 4/28/2021 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/3/2021 Not Ready for Inspection JAMES POWERS
Insulation 5/3/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 5/10/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 5/13/2021 Partial Approval JAMES POWERS
Drywall Nailing 5/13/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/13/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/14/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 5/20/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/20/2021 Partial Approval JAMES POWERS
Drywall Nailing 5/24/2021 Partial Approval JAMES POWERS
Insulation 5/24/2021 Partial Approval JAMES POWERS
Drywall Nailing 6/1/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 6/1/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 6/3/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 6/22/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 7/15/2021 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 7/15/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 8/18/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/18/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 9/14/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 9/14/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 9/27/2021 Partial Approval JAMES POWERS
Drywall Nailing 10/12/2021 Not Ready for Inspection JAMES POWERS
Excavation/Setback/Form/Re-Bar 10/28/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 11/4/2021 Partial Approval JAMES POWERS
Masonry Wall/Backfill 11/4/2021 Partial Approval JAMES POWERS
Reinforced Masonry Frame 11/8/2021 Partial Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 11/12/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 11/16/2021 Partial Approval TED RIES
Deputy Drilled-In Anchors 11/22/2021 Approved TED RIES
Reinforced Concrete Frame 11/30/2021 Partial Approval JAMES POWERS
Drywall Nailing 12/13/2021 Partial Approval JAMES POWERS
Final 12/13/2021 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 12/13/2021 Approved JAMES POWERS
Green Building Final 12/13/2021 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 12/13/2021 SGSOV Not Ready JAMES POWERS
Smoke Detectors 12/13/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 12/13/2021 Not Ready for Inspection JAMES POWERS
Wood Frame 12/13/2021 Partial Approval JAMES POWERS
Drywall Nailing 12/21/2021 Partial Approval JAMES POWERS
Final 12/21/2021 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 12/21/2021 SGSOV Not Ready JAMES POWERS
Smoke Detectors 12/21/2021 Approved JAMES POWERS
Verify Sprinkler Sign Off 12/21/2021 Not Ready for Inspection JAMES POWERS
Wood Frame 12/21/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 12/22/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/28/2021 Partial Approval JAMES POWERS
Drywall Nailing 12/28/2021 Partial Approval JAMES POWERS
Final 12/28/2021 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 12/28/2021 Partial Approval JAMES POWERS
SGSOV-Seismic Gas S/O Valve 12/28/2021 SGSOV Not Ready JAMES POWERS
Verify Sprinkler Sign Off 12/28/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 1/5/2022 Partial Approval JAMES POWERS
Drywall Nailing 1/20/2022 Approved JAMES POWERS
Final 1/20/2022 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 1/20/2022 SGSOV Approved JAMES POWERS
Verify Sprinkler Sign Off 1/20/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 1/20/2022 Partial Approval JAMES POWERS
Final 2/3/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 2/3/2022 Approved JAMES POWERS
Wood Frame 2/3/2022 Approved JAMES POWERS
Final 2/9/2022 Not Ready for Inspection JAMES POWERS
Final 3/10/2022 OK to Issue CofO JAMES POWERS