6570 S NORMANDIE AVE 90044

Certificate Information: 6570 S NORMANDIE AVE 90044

Application / Permit
18010-10000-05186
Plan Check / Job No.
B18LA22878
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 5-story, 93-unit, apartment building. 4-story Type VA over 1-story 1A. TOC Tier-1 and additional incentives. 100% privately funded, no tax credit, no public housing.
Permit Issued
Issued on 5/10/2021
Issuing Office
Metro
Current Status
CofO Issued on 8/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2018 APPLICANT
Assigned to Plan Check Engineer 11/29/2018 EUGENE BARBEAU
Corrections Issued 12/3/2018 EUGENE BARBEAU
Quality Review Completed 12/5/2018 SIAVOSH POURSABAHIAN
Building Plans Picked Up 12/17/2018 APPLICANT
Applicant returned to address corrections 3/3/2020 EUGENE BARBEAU
Plan Check Approved 3/3/2021 EUGENE BARBEAU
Issued 5/10/2021 APPLICANT
TCO Issued (Expire Date: 05-05-2024) 11/7/2023 ERNESTO CORRAL
TCO Issued (Expire Date: 11-12-2024) 5/16/2024 ERNESTO CORRAL
CofO in Progress 8/16/2024 JAMES POWERS
CofO Issued 8/20/2024 ERNESTO CORRAL
Permit Finaled 8/20/2024 ERNESTO CORRAL

Permit Application Clearance Information

Trees in Parkway Cleared 12/21/2019 JOHN KIM
Address approval Cleared 12/27/2019 THOMAS LANG
Permit Cleared 12/27/2019 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 1/16/2020 ELAINE LEI
Sewer availability Cleared 2/11/2020 JEANETTE VONG
Highway dedication Cleared 6/23/2020 ELAINE LEI
Miscellaneous Cleared 7/8/2020 TERRI OSBORNE
Miscellaneous Cleared 7/8/2020 TERRI OSBORNE
Site Plan review Cleared 7/8/2020 TERRI OSBORNE
Green Code Cleared 7/9/2020 EUGENE BARBEAU
Density Bonus 12.22.A.31 Cleared 7/21/2020 RICHARD TRUONG
Fire Marshall Fire Life Safety Cleared 10/7/2020 OSCAR SALGADO JR
Hydrant and Access approval Cleared 10/13/2020 MATTHEW CRAIG
DAS Clearance Cleared 10/21/2020 ELIZABETH TOMS
Construction near power lines Cleared 11/23/2020 RIDWAN HARDY
Construction within easement Cleared 11/23/2020 RIDWAN HARDY
Low Impact Development Cleared 11/23/2020 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 12/3/2020 ROSA SILVA
Frnt yard landscape/Water mgmt Cleared 2/4/2021 TERRI OSBORNE
Miscellaneous Cleared 2/4/2021 TERRI OSBORNE
Miscellaneous Cleared 2/4/2021 TERRI OSBORNE
Miscellaneous Cleared 2/4/2021 TERRI OSBORNE
Opn space landscape/Water mgmt Cleared 2/4/2021 TERRI OSBORNE
Redevelopment Project Area Cleared 2/8/2021 DAVID URITA
Building over 3-story or 36-ft Cleared 2/19/2021 CALOSHA APPROVED

Contact Information

Architect Kaliski,, John Ethan; Lic. No.: C17945 3780 WILSHIRE BLVD SUITE 300      LOS ANGELES, CA 90010
Contractor Mohrsaz Mike; Lic. No.: 910443-B 5080 AVENIDA HACIENDA      TARZANA, CA 91356
Engineer Koma,, Shahram Javadi; Lic. No.: C69497 23241 VENTURA BLVD 300      WOODLAND HILLS, CA 91364
Engineer Walter,, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401
Engineer White,, William Michael; Lic. No.: C62111 19619 MATHILDE LN      SAUGUS, CA 91350
Landscape Architect Mc, Eowen, Susan E; Lic. No.: LA2180 19197 GOLDEN VALLEY RD 924      SANTA CLARITA, CA 91387

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 8/30/2021 Partial Approval JAMES POWERS
Green Building Rough 8/30/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 8/30/2021 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 8/30/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 8/31/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 8/31/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/1/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/10/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/13/2021 Partial Approval JAMES POWERS
Green Building Rough 9/13/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 9/13/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 9/13/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 9/14/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/14/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/21/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/22/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/23/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/23/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/24/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/27/2021 Partial Approval JAMES POWERS
Reinforced Masonry Frame 9/30/2021 Partial Approval JONATHAN QUACH
Deputy Reinf. Masonry 10/1/2021 Conditional Approval LEOPOLDO MENDOZA
Green Building Rough 10/4/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 10/4/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 10/4/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 10/5/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/6/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/7/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/8/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/13/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/13/2021 Partial Approval JAMES POWERS
Reinforced Masonry Frame 10/13/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/14/2021 Partial Approval JAMES POWERS
Green Building Rough 10/14/2021 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 10/14/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 10/14/2021 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 10/15/2021 Not Ready for Inspection JAMES POWERS
Masonry Wall/Backfill 10/20/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Masonry 10/21/2021 Conditional Approval JONATHAN QUACH
Deputy Reinf. Masonry 10/27/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/28/2021 Partial Approval JAMES POWERS
Reinforced Masonry Frame 10/28/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/29/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/13/2022 Approved TED RIES
Footing/Foundation/Slab 1/13/2022 Partial Approval TED RIES
Deputy Reinf. Concrete 1/14/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/11/2022 Partial Approval JAMES POWERS
Green Building Rough 2/11/2022 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 2/11/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 2/11/2022 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 2/16/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/24/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/24/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 2/25/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/25/2022 Partial Approval JAMES POWERS
Green Building Rough 3/7/2022 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 3/7/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 3/7/2022 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 3/8/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/9/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/10/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 6/7/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/8/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 6/28/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 6/28/2022 Partial Approval JAMES POWERS
Insulation 7/5/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 7/6/2022 Conditional Approval ERNESTO CORRAL
Deputy Wood Construction 7/15/2022 Conditional Approval TED RIES
Floor/Roof Diaphrgm/Shear Wall 7/15/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 7/19/2022 Partial Approval JAMES POWERS
Insulation 7/19/2022 Partial Approval JAMES POWERS
Green Building Rough 7/25/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 7/25/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 7/25/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 7/26/2022 Conditional Approval ERNESTO CORRAL
Insulation 7/28/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 8/10/2022 Conditional Approval ERNESTO CORRAL
Green Building Rough 8/11/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 8/11/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 8/11/2022 Partial Approval JAMES POWERS
Insulation 8/17/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 8/22/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/22/2022 Partial Approval JAMES POWERS
Green Building Rough 8/22/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 8/22/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 8/22/2022 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/24/2022 Partial Approval JAMES POWERS
Insulation 8/31/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 9/1/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/1/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 9/9/2022 Conditional Approval MICHAEL ROSENBERG
Insulation 9/12/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 9/12/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 9/16/2022 Conditional Approval MICHAEL ROSENBERG
Insulation 9/20/2022 Partial Approval JAMES POWERS
Green Building Rough 9/21/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 9/21/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 9/21/2022 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 9/26/2022 Partial Approval JAMES POWERS
Drywall Nailing 9/26/2022 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/29/2022 Approved DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 10/3/2022 Partial Approval JAMES POWERS
Green Building Rough 10/3/2022 Approved JAMES POWERS
Verify Sprinkler Sign Off 10/3/2022 Not Ready for Inspection JAMES POWERS
Insulation 10/13/2022 Partial Approval RUSSELL BONVOULOIR
Verify Sprinkler Sign Off 10/13/2022 Partial Inspection RUSSELL BONVOULOIR
Wood Frame 10/13/2022 Partial Inspection RUSSELL BONVOULOIR
Light Gage Steel Frame 10/26/2022 Partial Approval JAMES POWERS
Drywall Nailing 11/4/2022 Partial Approval GREGORY POMISH
Light Gage Steel Frame 11/14/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 11/21/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 12/8/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 12/14/2022 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 12/19/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 12/29/2022 Partial Approval JAMES POWERS
Drywall Nailing 1/6/2023 Partial Approval JAMES POWERS
Interior/Exterior Lathing 1/13/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 1/24/2023 Partial Approval JAMES POWERS
Drywall Nailing 3/13/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/30/2023 Partial Approval JAMES POWERS
Reinforced Masonry Frame 5/12/2023 Partial Approval LARRY ARNICK
Masonry Wall/Backfill 5/17/2023 Partial Approval JAMES POWERS
Masonry Wall/Backfill 5/19/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 5/19/2023 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 5/25/2023 Partial Approval JAMES POWERS
Reinforced Masonry Frame 5/31/2023 Partial Approval TED RIES
Reinforced Concrete Frame 6/5/2023 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 6/5/2023 Not Ready for Inspection JAMES POWERS
Insulation 6/20/2023 Partial Approval JAMES POWERS
Drywall Nailing 6/27/2023 Partial Approval JAMES POWERS
Light Gage Steel Frame 7/10/2023 Partial Approval JAMES POWERS
Drywall Nailing 7/17/2023 Partial Approval LARRY ARNICK
Final 10/19/2023 OK for TCO JAMES POWERS
Footing/Foundation/Slab 10/19/2023 Approved JAMES POWERS
Green Building Final 10/19/2023 Approved JAMES POWERS
Reinforced Concrete Frame 10/19/2023 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 10/19/2023 SGSOV Approved JAMES POWERS
Smoke Detectors 10/19/2023 Approved JAMES POWERS
Verify Sprinkler Sign Off 10/19/2023 Approved JAMES POWERS
Wood Frame 10/19/2023 Approved JAMES POWERS
Final 11/6/2023 OK for TCO JAMES POWERS
Special/Order Compliance 4/9/2024 Approved JAMES POWERS
Deputy Drilled-In Anchors 8/16/2024 Partial Approval JAMES POWERS
Final 8/16/2024 OK to Issue CofO JAMES POWERS
Special/Order Compliance 8/16/2024 Approved JAMES POWERS