2909 S BUCKINGHAM ROAD 90016

Certificate Information: 2909 S BUCKINGHAM ROAD 90016

Application / Permit
18010-10000-05113
Plan Check / Job No.
B18LA22422
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY ACCESSORY DWELLING UNIT WITH ROOF DECK PER AB 494 & SB 229
Permit Issued
Issued on 2/8/2021
Issuing Office
Current Status
Issued on 2/8/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/19/2018 APPLICANT
Assigned to Plan Check Engineer 11/20/2018 PRANITA SHAH
Corrections Issued 11/30/2018 PRANITA SHAH
Quality Review Completed 12/10/2018 HERNAN ARREOLA
Green Plans Picked Up 12/21/2018 APPLICANT
Building Plans Picked Up 1/10/2019 APPLICANT
Applicant returned to address corrections 9/25/2019 PRANITA SHAH
Plan Check Approved 10/8/2019 PRANITA SHAH
Issued 2/8/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/13/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 9/13/2019 ERIK BEASLEY
Hydrant and Access approval Cleared 9/13/2019 JEREMY CARTER
Sewer availability Cleared 9/13/2019 ERIK BEASLEY
Construction near power lines Cleared 9/14/2019 RIDWAN HARDY
Low Impact Development Cleared 10/4/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 10/4/2019 EMIL KYUPELYAN
Green Code Cleared 10/7/2019 PRANITA SHAH

Contact Information

Contractor Gonzales Jose Eduardo Inc; Lic. No.: 1055061-B 2907 BUCKINGHAM RD      LOS ANGELES, CA 90016
Engineer Moser,, Bradley Charles; Lic. No.: C68803 116 OAKSIDE LN      BUELLTON, CA 93427

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/5/2021 Approved STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 3/22/2021 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 5/7/2021 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 5/21/2021 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 7/12/2021 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Rough 7/12/2021 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 7/12/2021 Approved STUART CHAPMAN
Green Building Rough 7/12/2021 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 7/12/2021 Corrections Issued STUART CHAPMAN
PLUMBING-Rough 7/12/2021 Corrections Issued STUART CHAPMAN
Verify Sprinkler Sign Off 7/12/2021 Approved STUART CHAPMAN
Wood Frame 7/12/2021 Corrections Issued STUART CHAPMAN
Deck 7/20/2021 Partial Inspection ROBERT VORHIS
Interior/Exterior Lathing 7/20/2021 Partial Inspection ROBERT VORHIS
ELECTRICAL-Rough 8/5/2021 Approved RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 8/5/2021 Approved RUBEN SALAS
Green Building Rough 8/5/2021 Approved RUBEN SALAS
HVAC-Rough 8/5/2021 Approved RUBEN SALAS
Interior/Exterior Lathing 8/5/2021 Not Ready for Inspection RUBEN SALAS
PLUMBING-Rough 8/5/2021 Approved RUBEN SALAS
Rough-Elec/Plmb/HVAC 8/5/2021 Approved RUBEN SALAS
Wood Frame 8/5/2021 Approved RUBEN SALAS
BUILDING-Rough-Frame 8/17/2021 Approved STUART CHAPMAN
ELECTRICAL-Rough 8/17/2021 Approved STUART CHAPMAN
HVAC-Rough 8/17/2021 Approved STUART CHAPMAN
Insulation 8/17/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/17/2021 Approved STUART CHAPMAN
PLUMBING-Rough 8/17/2021 Approved STUART CHAPMAN
Shower Pan 8/17/2021 Approved STUART CHAPMAN
Wood Frame 8/17/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 9/17/2021 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 9/17/2021 Approved STUART CHAPMAN
Rough-Elec/Plmb/HVAC 9/17/2021 Approved STUART CHAPMAN
Sewer 9/17/2021 Approved STUART CHAPMAN
Underground Mechanical 9/17/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 9/22/2021 Not Ready for Inspection STUART CHAPMAN
Drywall Nailing 10/13/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 10/13/2021 Approved STUART CHAPMAN
ELECTRICAL-Final 6/10/2025 No Access for Inspection JUSTIN HAWLEY
Final 6/10/2025 No Access for Inspection JUSTIN HAWLEY
Footing/Foundation/Slab 6/10/2025 No Access for Inspection JUSTIN HAWLEY
Green Building Final 6/10/2025 No Access for Inspection JUSTIN HAWLEY
HVAC-Final 6/10/2025 No Access for Inspection JUSTIN HAWLEY
PLUMBING-Final 6/10/2025 No Access for Inspection JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 6/10/2025 SGSOV Not Ready JUSTIN HAWLEY
Service/Power Release 6/10/2025 No Access for Inspection JUSTIN HAWLEY
Sewer 6/10/2025 No Access for Inspection JUSTIN HAWLEY
Smoke Detectors 6/10/2025 No Access for Inspection JUSTIN HAWLEY
ELECTRICAL-Final 8/25/2025 Not Ready for Inspection JUSTIN HAWLEY
Final 8/25/2025 Corrections Issued JUSTIN HAWLEY
Footing/Foundation/Slab 8/25/2025 Approved JUSTIN HAWLEY
Green Building Final 8/25/2025 Not Ready for Inspection JUSTIN HAWLEY
HVAC-Final 8/25/2025 Not Ready for Inspection JUSTIN HAWLEY
PLUMBING-Final 8/25/2025 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 8/25/2025 SGSOV Approved JUSTIN HAWLEY
Service/Power Release 8/25/2025 Not Ready for Inspection JUSTIN HAWLEY
Smoke Detectors 8/25/2025 Approved JUSTIN HAWLEY