21050 W KITTRIDGE ST 91303

Certificate Information: 21050 W KITTRIDGE ST 91303

Application / Permit
18010-10000-04971
Plan Check / Job No.
B18LA21991
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 7-story, 395-unit, Apartment building. 5 stories of TYPE IIIA over 2-story TYPE IA podium (FOUNDATION ONLY EARLY START FOR APARTMENT FOUNDATION ONLY)
Permit Issued
Issued on 6/21/2019
Issuing Office
Metro
Current Status
CofO Issued on 5/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/19/2018 APPLICANT
Assigned to Plan Check Engineer 11/3/2018 HERNAN ARREOLA
Corrections Issued 11/13/2018 HERNAN ARREOLA
Quality Review Completed 11/29/2018 BILL STUTSMAN
Building Plans Picked Up 12/5/2018 APPLICANT
Applicant returned to address corrections 2/19/2019 HERNAN ARREOLA
Plan Check Approved 6/21/2019 HERNAN ARREOLA
Issued 6/21/2019 LADBS
TCO Issued (Expire Date: 05-11-2021) 11/12/2020 JEFFREY DURAN
TCO Issued (Expire Date: 09-22-2021) 3/26/2021 JEFFREY DURAN
CofO in Progress 4/30/2021 JEFFREY DURAN
Permit Finaled 5/20/2021 RICKEY JACKSON
CofO Issued 5/20/2021 RICKEY JACKSON
Permit Finaled 5/20/2021 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 12/6/2018 HOWARD COOPER
Hydrant and Access approval Cleared 4/26/2019 GEORGE SUCHAND
Low Impact Development Cleared 4/26/2019 MITESH PATEL
Eng Process Fee Ord 176,300 Cleared 5/8/2019 ELENA LOPEZ
Sewer availability Cleared 6/7/2019 ELENA LOPEZ
Fire Marshall Fire Life Safety Cleared 6/10/2019 VIDAL GARCIA
DAS Clearance Cleared 6/13/2019 HERNAN ARREOLA
Trees in Parkway Cleared 6/13/2019 JOHN KIM
Building over 3-story or 36-ft Cleared 6/14/2019 CALOSHA APPROVED
Green Code Cleared 6/14/2019 DONALD CRICHLOW
Driveway location Cleared 6/18/2019 DURRE SHAMSI
Highway dedication Cleared 6/18/2019 JOHN LIN
Permit Cleared 6/18/2019 JOHN LIN
Roof/Waste drainage to street Cleared 6/18/2019 MARKOS PEREZ-BRAN
Frnt yard landscape/Water mgmt Cleared 6/21/2019 DIANA JIMENEZ
Opn space landscape/Water mgmt Cleared 6/21/2019 DIANA JIMENEZ
Prkng lot landscape/Water mgmt Cleared 6/21/2019 DIANA JIMENEZ
Site Plan review Cleared 6/21/2019 DIANA JIMENEZ
Specific Plan Cleared 6/21/2019 DIANA JIMENEZ
ZI Cleared 6/21/2019 DIANA JIMENEZ

Contact Information

Architect Olsen,, Eric H; Lic. No.: C27721 3802 OSTROM AVE      LONG BEACH, CA 90808
Contractor Hanover R S Construction Llc; Lic. No.: 970389-B 5847 SAN FELIPE SUITE 3600      HOUSTON, TX 77057
Engineer Kim,, Carl Chong-Soo; Lic. No.: GE2620 10246 FALL CT      TRUCKEE, CA 96161
Engineer Maingot,, Martin Rex; Lic. No.: S5623 4722 CASTLEWOOD STREET      SUGAR LAND, TX 77479

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/26/2019 Approved JEFFREY DURAN
Footing/Foundation/Slab 7/9/2019 Partial Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 7/11/2019 Conditional Approval JAMES STEPHENS
Excavation/Setback/Form/Re-Bar 7/12/2019 Conditional Approval JAMES STEPHENS
Special/Order Compliance 7/12/2019 Partial Inspection JAMES STEPHENS
Deputy Reinf. Concrete 7/23/2019 Conditional Approval JAMES STEPHENS
Footing/Foundation/Slab 7/24/2019 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 7/25/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/26/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/29/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/30/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/31/2019 Approved JEFFREY DURAN
Footing/Foundation/Slab 7/31/2019 Partial Inspection JEFFREY DURAN
Deputy Reinf. Concrete 8/1/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 8/1/2019 Partial Inspection JEFFREY DURAN
Deputy Reinf. Concrete 8/2/2019 Conditional Approval JEFFREY DURAN
Green Building Rough 8/2/2019 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 8/2/2019 Not Ready for Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 8/2/2019 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 8/5/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/6/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/7/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 8/7/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/8/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/9/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 8/9/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/12/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 8/12/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/13/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/14/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/15/2019 Conditional Approval ROBERT COLE
Excavation/Setback/Form/Re-Bar 8/15/2019 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Concrete 8/16/2019 Conditional Approval DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 8/16/2019 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 8/19/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 8/19/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/20/2019 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 8/20/2019 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 8/21/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 8/21/2019 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 8/22/2019 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 8/22/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/23/2019 Approved JEFFREY DURAN
Deputy Pre-Stress Concrete 8/26/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/26/2019 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 8/27/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 8/27/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 8/27/2019 Partial Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 8/28/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 8/28/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 8/28/2019 Partial Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 8/29/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 8/29/2019 Approved JEFFREY DURAN
Deputy Pre-Stress Concrete 8/30/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 8/30/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 8/30/2019 Partial Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 9/4/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 9/4/2019 Partial Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 9/5/2019 Conditional Approval DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 9/5/2019 Partial Approval DANNY RODRIGUEZ
Deputy Pre-Stress Concrete 9/6/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 9/6/2019 Partial Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 9/9/2019 Conditional Approval JAMES STEPHENS
Deputy Pre-Stress Concrete 9/10/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 9/10/2019 Partial Inspection JEFFREY DURAN
Deputy Pre-Stress Concrete 9/11/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 9/11/2019 Partial Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 9/12/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 9/12/2019 Partial Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 9/13/2019 Conditional Approval RICKEY JACKSON
Deputy Reinf. Concrete 9/13/2019 Conditional Approval RICKEY JACKSON
Deputy Reinf. Concrete 9/16/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 9/16/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/18/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 9/20/2019 Not Ready for Inspection JEFFREY DURAN
Green Building Rough 9/20/2019 Not Ready for Inspection JEFFREY DURAN
Reinforced Masonry Frame 9/20/2019 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 9/20/2019 Not Ready for Inspection JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 9/24/2019 Partial Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 9/25/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 9/25/2019 Approved JEFFREY DURAN
Deputy Reinf. Masonry 9/25/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 9/25/2019 Partial Inspection JEFFREY DURAN
Deputy Pre-Stress Concrete 9/26/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 9/26/2019 Approved JEFFREY DURAN
Deputy Reinf. Masonry 9/26/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 9/26/2019 Partial Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 9/27/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/27/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/27/2019 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 9/30/2019 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 9/30/2019 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 9/30/2019 Conditional Approval ROBERT COLE
Deputy Pre-Stress Concrete 10/1/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 10/1/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 10/1/2019 Conditional Approval JEFFREY DURAN
Reinforced Concrete Frame 10/1/2019 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 10/2/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 10/2/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 10/2/2019 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 10/3/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 10/3/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 10/3/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 10/3/2019 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 10/4/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 10/4/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 10/4/2019 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 10/7/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 10/7/2019 Approved JEFFREY DURAN
Deputy Reinf. Masonry 10/7/2019 Approved JEFFREY DURAN
Deputy Pre-Stress Concrete 10/8/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 10/8/2019 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 10/9/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 10/9/2019 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 10/10/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 10/10/2019 Approved JEFFREY DURAN
Deputy Pre-Stress Concrete 10/11/2019 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 10/11/2019 Conditional Approval ROBERT COLE
Green Building Rough 10/11/2019 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 10/11/2019 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 10/11/2019 Not Ready for Inspection ROBERT COLE
Deputy Pre-Stress Concrete 10/15/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 10/15/2019 Approved JEFFREY DURAN
Deputy Pre-Stress Concrete 10/17/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 10/17/2019 Approved JEFFREY DURAN
Deputy Reinf. Masonry 10/17/2019 Approved JEFFREY DURAN
Deputy Pre-Stress Concrete 10/18/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 10/18/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 10/18/2019 Conditional Approval JEFFREY DURAN
Structural Steel Frame 10/18/2019 Partial Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 10/21/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 10/21/2019 Approved JEFFREY DURAN
Deputy Reinf. Masonry 10/21/2019 Approved JEFFREY DURAN
Deputy Pre-Stress Concrete 10/22/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 10/22/2019 Approved JEFFREY DURAN
Deputy Reinf. Masonry 10/22/2019 Approved JEFFREY DURAN
Drywall Nailing 10/22/2019 Partial Inspection JEFFREY DURAN
Green Building Rough 10/22/2019 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 10/22/2019 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 10/22/2019 Not Ready for Inspection JEFFREY DURAN
Deputy Pre-Stress Concrete 10/23/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 10/23/2019 Approved JEFFREY DURAN
Deputy Reinf. Masonry 10/23/2019 Approved JEFFREY DURAN
Drywall Nailing 10/23/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 10/24/2019 Approved JEFFREY DURAN
Drywall Nailing 10/24/2019 Partial Approval JEFFREY DURAN
Green Building Rough 10/25/2019 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 10/25/2019 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 10/25/2019 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 10/29/2019 Partial Inspection JEFFREY DURAN
Green Building Rough 11/1/2019 Not Ready for Inspection JAMES STEPHENS
Reinforced Concrete Frame 11/1/2019 Partial Approval JAMES STEPHENS
Verify Sprinkler Sign Off 11/1/2019 Not Ready for Inspection JAMES STEPHENS
Drywall Nailing 11/8/2019 Partial Approval JEFFREY DURAN
Green Building Rough 11/15/2019 Not Ready for Inspection JEFFREY DURAN
Reinforced Masonry Frame 11/15/2019 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 11/15/2019 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 11/18/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 11/18/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 11/19/2019 Conditional Approval RICKEY JACKSON
Deputy Reinf. Masonry 11/19/2019 Conditional Approval RICKEY JACKSON
Deputy Reinf. Concrete 11/20/2019 Approved JEFFREY DURAN
Deputy Reinf. Masonry 11/20/2019 Approved JEFFREY DURAN
Green Building Rough 11/20/2019 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 11/20/2019 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 11/20/2019 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 11/21/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 11/21/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 11/22/2019 Approved JEFFREY DURAN
Deputy Reinf. Masonry 11/22/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 11/22/2019 Partial Approval JEFFREY DURAN
Green Building Rough 11/25/2019 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 11/25/2019 Partial Approval ROBERT COLE
Verify Sprinkler Sign Off 11/25/2019 Not Ready for Inspection ROBERT COLE
Wood Frame 11/25/2019 Partial Approval ROBERT COLE
Footing/Foundation/Slab 11/27/2019 Partial Approval HAMID PISHEHVAR
Wood Frame 12/4/2019 Not Ready for Inspection JEFF BYTHEWAY
Drywall Nailing 12/5/2019 Not Ready for Inspection JEFFREY DURAN
Wood Frame 12/5/2019 Not Ready for Inspection JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 12/7/2019 Off-Hour Fees Due
Floor/Roof Diaphrgm/Shear Wall 12/7/2019 Partial Approval JEFFREY DURAN
Wood Frame 12/9/2019 Partial Approval JEFFREY DURAN
Drywall Nailing 12/10/2019 Not Ready for Inspection JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 12/11/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/13/2019 Approved JEFFREY DURAN
Green Building Rough 12/13/2019 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 12/13/2019 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 12/13/2019 Not Ready for Inspection JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/16/2019 Partial Inspection MILLARD ARDOIN
Excavation/Setback/Form/Re-Bar 12/17/2019 Partial Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/18/2019 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 12/18/2019 Partial Approval JEFFREY DURAN
Deputy Wood Construction 12/24/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 12/26/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 12/27/2019 Conditional Approval JEFFREY DURAN
Wood Frame 1/2/2020 Not Ready for Inspection JEFFREY DURAN
Deputy Pre-Stress Concrete 1/9/2020 Conditional Approval JEFFREY DURAN
Green Building Rough 1/9/2020 Partial Approval JEFFREY DURAN
Reinforced Concrete Frame 1/9/2020 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 1/9/2020 Not Ready for Inspection JEFFREY DURAN
Deputy Pre-Stress Concrete 1/10/2020 Conditional Approval JEFFREY DURAN
Wood Frame 1/13/2020 Partial Approval JEFFREY DURAN
Structural Steel Frame 1/14/2020 Partial Approval JEFFREY DURAN
Wood Frame 1/22/2020 Partial Approval JEFFREY DURAN
Light Gage Steel Frame 1/27/2020 Partial Inspection JEFFREY DURAN
Drywall Nailing 1/29/2020 Partial Approval JEFFREY DURAN
Wood Frame 1/29/2020 Conditional Approval JEFFREY DURAN
Green Building Rough 1/30/2020 Partial Inspection JEFFREY DURAN
Reinforced Concrete Frame 1/30/2020 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 1/30/2020 Partial Inspection JEFFREY DURAN
Deputy Reinf. Concrete 1/31/2020 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 1/31/2020 Partial Approval JEFFREY DURAN
Drywall Nailing 2/3/2020 Not Ready for Inspection JEFFREY DURAN
Green Building Rough 2/3/2020 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 2/3/2020 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 2/3/2020 Not Ready for Inspection JEFFREY DURAN
Wood Frame 2/3/2020 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 2/4/2020 Partial Approval JEFFREY DURAN
Wood Frame 2/4/2020 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 2/5/2020 Partial Approval JEFFREY DURAN
Green Building Rough 2/5/2020 Not Ready for Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 2/5/2020 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 2/7/2020 Partial Approval JEFFREY DURAN
Drywall Nailing 2/11/2020 Partial Approval JEFFREY DURAN
Green Building Rough 2/11/2020 Not Ready for Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 2/11/2020 Not Ready for Inspection JEFFREY DURAN
Wood Frame 2/12/2020 Partial Approval JEFFREY DURAN
Footing/Foundation/Slab 2/18/2020 Partial Approval JEFFREY DURAN
Wood Frame 2/18/2020 Partial Approval JEFFREY DURAN
Green Building Rough 2/19/2020 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 2/19/2020 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 2/19/2020 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 2/21/2020 Not Ready for Inspection JEFFREY DURAN
Wood Frame 2/21/2020 Partial Approval JEFFREY DURAN
Drywall Nailing 2/24/2020 Partial Approval JEFFREY DURAN
Insulation 2/24/2020 Partial Approval JEFFREY DURAN
Drywall Nailing 2/25/2020 Partial Approval JEFFREY DURAN
Insulation 2/25/2020 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 2/27/2020 Partial Approval JEFFREY DURAN
Drywall Nailing 2/28/2020 Partial Approval JEFFREY DURAN
Wood Frame 2/28/2020 Not Ready for Inspection JEFFREY DURAN
Wall Anchors 3/2/2020 Partial Approval JEFFREY DURAN
Drywall Nailing 3/4/2020 Not Ready for Inspection JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 3/4/2020 Partial Approval JEFFREY DURAN
Drywall Nailing 3/6/2020 Partial Approval JEFFREY DURAN
Wood Frame 3/6/2020 Partial Approval JEFFREY DURAN
Drywall Nailing 3/10/2020 Partial Approval JEFFREY DURAN
Light Gage Steel Frame 3/10/2020 Not Ready for Inspection JEFFREY DURAN
Wood Frame 3/10/2020 Not Ready for Inspection JEFFREY DURAN
Green Building Rough 3/13/2020 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 3/13/2020 Partial Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 3/13/2020 Not Ready for Inspection JEFFREY DURAN
Wood Frame 3/20/2020 Partial Approval JEFFREY DURAN
Wood Frame 3/23/2020 Partial Approval JEFFREY DURAN
Wood Frame 3/24/2020 Conditional Approval JEFFREY DURAN
Drywall Nailing 3/25/2020 Not Ready for Inspection JEFFREY DURAN
Wood Frame 3/25/2020 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 3/26/2020 Conditional Approval JEFFREY DURAN
Drywall Nailing 3/26/2020 Partial Approval JEFFREY DURAN
Green Building Rough 3/27/2020 Not Ready for Inspection JEFFREY DURAN
Insulation 3/27/2020 Partial Approval JEFFREY DURAN
Reinforced Masonry Frame 3/27/2020 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 3/27/2020 Not Ready for Inspection JEFFREY DURAN
Wood Frame 3/27/2020 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 3/31/2020 Partial Approval JEFFREY DURAN
Wood Frame 3/31/2020 Partial Approval JEFFREY DURAN
Insulation 4/1/2020 Partial Approval JEFFREY DURAN
Special/Order Compliance 4/1/2020 Conditional Approval JEFFREY DURAN
Wood Frame 4/1/2020 Partial Approval JEFFREY DURAN
Insulation 4/2/2020 Partial Approval JEFFREY DURAN
Wood Frame 4/2/2020 Partial Approval JEFFREY DURAN
Insulation 4/6/2020 Partial Approval JEFFREY DURAN
Wood Frame 4/6/2020 Not Ready for Inspection JEFFREY DURAN
Insulation 4/7/2020 Partial Approval DANIEL VARNUM
Wood Frame 4/7/2020 Partial Approval DANIEL VARNUM
Insulation 4/8/2020 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 4/8/2020 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 4/9/2020 Partial Approval ROBERT COLE
Insulation 4/9/2020 Not Ready for Inspection ROBERT COLE
Wood Frame 4/9/2020 Not Ready for Inspection ROBERT COLE
Insulation 4/10/2020 Partial Inspection JEFFREY FULTON
Wood Frame 4/10/2020 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 4/13/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 4/14/2020 Not Ready for Inspection JEFFREY FULTON
Insulation 4/14/2020 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 4/15/2020 Partial Approval ROBERT COLE
Insulation 4/16/2020 Partial Approval DANIEL VARNUM
Wood Frame 4/16/2020 Partial Approval DANIEL VARNUM
Insulation 4/20/2020 Not Ready for Inspection ROBERT COLE
Wood Frame 4/20/2020 Partial Approval ROBERT COLE
Drywall Nailing 4/21/2020 Partial Approval DANIEL VARNUM
Insulation 4/21/2020 Partial Approval DANIEL VARNUM
Drywall Nailing 4/22/2020 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 4/22/2020 Partial Approval DANIEL VARNUM
Drywall Nailing 4/23/2020 Partial Approval ROBERT DAVIS
Insulation 4/23/2020 Partial Approval ROBERT DAVIS
Drywall Nailing 4/24/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 4/28/2020 Partial Inspection JEFFREY FULTON
Insulation 4/28/2020 Partial Inspection JEFFREY FULTON
Wood Frame 4/28/2020 Not Ready for Inspection JEFFREY FULTON
Wood Frame 4/29/2020 Approved HAMID PISHEHVAR
Drywall Nailing 4/30/2020 Partial Inspection JEFFREY FULTON
Wood Frame 4/30/2020 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 5/1/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 5/5/2020 Partial Inspection JEFFREY FULTON
Wood Frame 5/5/2020 Not Ready for Inspection JEFFREY FULTON
Insulation 5/6/2020 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 5/6/2020 Partial Inspection JEFFREY FULTON
Wood Frame 5/7/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 5/8/2020 Partial Inspection JEFFREY FULTON
Wood Frame 5/8/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 5/12/2020 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 5/12/2020 Conditional Approval DANIEL VARNUM
Insulation 5/12/2020 Partial Inspection DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 5/13/2020 Partial Inspection JEFFREY FULTON
Insulation 5/13/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 5/14/2020 Partial Inspection JEFFREY FULTON
Wood Frame 5/14/2020 Partial Inspection JEFFREY FULTON
Insulation 5/15/2020 Partial Inspection JEFFREY FULTON
Wood Frame 5/15/2020 Corrections Issued JEFFREY FULTON
Insulation 5/18/2020 Partial Approval DANIEL VARNUM
Wood Frame 5/18/2020 Partial Approval DANIEL VARNUM
Wood Frame 5/19/2020 Partial Approval ROBERT DAVIS
Drywall Nailing 5/20/2020 Partial Approval ROBERT DAVIS
Wood Frame 5/20/2020 Partial Approval ROBERT DAVIS
Insulation 5/21/2020 Partial Approval JEFFREY DURAN
Wood Frame 5/21/2020 Not Ready for Inspection JEFFREY DURAN
Insulation 5/22/2020 Not Ready for Inspection JEFFREY DURAN
Wood Frame 5/22/2020 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 5/26/2020 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 5/26/2020 Partial Inspection JEFFREY FULTON
Insulation 5/26/2020 Not Ready for Inspection JEFFREY FULTON
Interior/Exterior Lathing 5/26/2020 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 5/27/2020 Not Ready for Inspection JEFFREY FULTON
Interior/Exterior Lathing 5/27/2020 Partial Inspection JEFFREY FULTON
Wood Frame 5/27/2020 Not Ready for Inspection JEFFREY FULTON
Interior/Exterior Lathing 5/28/2020 Partial Inspection JEFFREY FULTON
Wood Frame 5/28/2020 Not Ready for Inspection JEFFREY FULTON
Insulation 5/29/2020 Partial Inspection JEFFREY FULTON
Wood Frame 5/29/2020 Partial Inspection JEFFREY FULTON
Insulation 6/2/2020 Partial Inspection JEFFREY FULTON
Wood Frame 6/2/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 6/3/2020 Partial Inspection JEFFREY FULTON
Insulation 6/3/2020 Partial Inspection JEFFREY FULTON
Insulation 6/4/2020 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 6/4/2020 Partial Inspection JEFFREY FULTON
Insulation 6/5/2020 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 6/5/2020 Partial Inspection JEFFREY FULTON
Insulation 6/9/2020 Approved HAMID PISHEHVAR
Wood Frame 6/9/2020 Approved HAMID PISHEHVAR
Insulation 6/10/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 6/11/2020 Not Ready for Inspection JEFFREY FULTON
Insulation 6/11/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 6/12/2020 Partial Inspection JEFFREY FULTON
Insulation 6/12/2020 Not Ready for Inspection JEFFREY FULTON
Insulation 6/16/2020 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 6/16/2020 Partial Inspection JEFFREY FULTON
Wood Frame 6/16/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 6/17/2020 Partial Inspection JEFFREY FULTON
Wood Frame 6/17/2020 Partial Inspection JEFFREY FULTON
Wood Frame 6/18/2020 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 6/19/2020 Partial Inspection JEFFREY FULTON
Wood Frame 6/19/2020 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 6/20/2020 Off-Hour Fees Due
Floor/Roof Diaphrgm/Shear Wall 6/20/2020 Partial Approval JEFFREY DURAN
Insulation 6/20/2020 Not Ready for Inspection JEFFREY DURAN
Insulation 6/20/2020 Off-Hour Fees Due
Light Gage Steel Frame 6/20/2020 Not Ready for Inspection JEFFREY DURAN
Light Gage Steel Frame 6/20/2020 Off-Hour Fees Due
Insulation 6/22/2020 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 6/22/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 6/23/2020 Partial Inspection JEFFREY FULTON
Insulation 6/23/2020 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 6/23/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 6/24/2020 Partial Approval DANIEL VARNUM
Insulation 6/24/2020 Partial Approval DANIEL VARNUM
Light Gage Steel Frame 6/24/2020 Partial Approval DANIEL VARNUM
Wood Frame 6/24/2020 Partial Approval DANIEL VARNUM
Drywall Nailing 6/26/2020 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 6/26/2020 Not Ready for Inspection JEFFREY FULTON
Insulation 6/27/2020 Partial Approval JEFFREY DURAN
Interior/Exterior Lathing 6/27/2020 Conditional Approval JEFFREY DURAN
Interior/Exterior Lathing 6/29/2020 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 6/29/2020 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 6/30/2020 Off-Hour Fees Due
Insulation 6/30/2020 Off-Hour Fees Due
Interior/Exterior Lathing 6/30/2020 Off-Hour Fees Due
Light Gage Steel Frame 6/30/2020 Off-Hour Fees Due
Light Gage Steel Frame 6/30/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 7/1/2020 Partial Inspection JEFFREY FULTON
Wood Frame 7/2/2020 Partial Inspection JEFFREY FULTON
Insulation 7/6/2020 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 7/6/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 7/7/2020 Partial Inspection JEFFREY FULTON
Wood Frame 7/7/2020 Partial Inspection JEFFREY FULTON
Wood Frame 7/8/2020 Not Ready for Inspection HAMID PISHEHVAR
Drywall Nailing 7/9/2020 Partial Inspection JEFFREY FULTON
Insulation 7/10/2020 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 7/14/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 7/15/2020 Partial Inspection ANDREW DORSO
Drywall Nailing 7/16/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 7/17/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 7/20/2020 Approved JEFFREY FULTON
Wood Frame 7/20/2020 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 7/21/2020 Not Ready for Inspection JEFFREY FULTON
Insulation 7/22/2020 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 7/22/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 7/23/2020 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 7/23/2020 Not Ready for Inspection JEFFREY FULTON
Insulation 7/24/2020 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 7/24/2020 Partial Inspection JEFFREY FULTON
Insulation 7/27/2020 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 7/27/2020 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 7/30/2020 Partial Approval ROBERT DAVIS
Insulation 7/30/2020 Partial Approval ROBERT DAVIS
Drywall Nailing 7/31/2020 Partial Inspection JEFFREY FULTON
Wood Frame 7/31/2020 Not Ready for Inspection JEFFREY FULTON
Insulation 8/3/2020 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 8/3/2020 Partial Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 8/4/2020 Partial Inspection JEFFREY FULTON
Wood Frame 8/5/2020 Partial Approval DANIEL VARNUM
Drywall Nailing 8/6/2020 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 8/6/2020 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 8/7/2020 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 8/7/2020 Not Ready for Inspection JEFFREY FULTON
Insulation 8/10/2020 Not Ready for Inspection JEFFREY FULTON
Interior/Exterior Lathing 8/10/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 8/13/2020 Partial Approval ROBERT DAVIS
Insulation 8/13/2020 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 8/13/2020 Partial Approval ROBERT DAVIS
Wood Frame 8/13/2020 Partial Approval ROBERT DAVIS
Drywall Nailing 8/18/2020 Approved HAMID PISHEHVAR
Interior/Exterior Lathing 8/19/2020 Partial Inspection JEFFREY FULTON
Insulation 8/20/2020 Partial Inspection JEFFREY FULTON
Insulation 8/21/2020 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 8/26/2020 Partial Approval DANIEL VARNUM
Insulation 8/26/2020 Partial Approval DANIEL VARNUM
Wood Frame 8/26/2020 Partial Approval DANIEL VARNUM
Drywall Nailing 8/27/2020 Partial Inspection JEFFREY FULTON
Insulation 8/29/2020 Partial Approval DANIEL VARNUM
Wood Frame 8/29/2020 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 9/1/2020 Conditional Approval DANIEL VARNUM
Insulation 9/3/2020 Not Ready for Inspection JEFFREY FULTON
Insulation 9/3/2020 Partial Approval ROBERT DAVIS
Interior/Exterior Lathing 9/3/2020 Not Ready for Inspection JEFFREY FULTON
Interior/Exterior Lathing 9/3/2020 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 9/3/2020 Not Ready for Inspection JEFFREY FULTON
Wood Frame 9/3/2020 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 9/4/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 9/8/2020 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 9/10/2020 Partial Inspection JEFFREY FULTON
Insulation 9/15/2020 Approved HAMID PISHEHVAR
Insulation 9/15/2020 No Access for Inspection JEFFREY FULTON
Light Gage Steel Frame 9/15/2020 Approved HAMID PISHEHVAR
Light Gage Steel Frame 9/15/2020 No Access for Inspection JEFFREY FULTON
Insulation 9/16/2020 Approved HAMID PISHEHVAR
Light Gage Steel Frame 9/16/2020 Approved HAMID PISHEHVAR
Insulation 9/17/2020 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 9/17/2020 Partial Inspection JEFFREY FULTON
Insulation 9/18/2020 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 9/18/2020 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 9/21/2020 Not Ready for Inspection JEFFREY FULTON
Final 9/21/2020 Partial Inspection JEFFREY FULTON
Green Building Final 9/21/2020 Not Ready for Inspection JEFFREY FULTON
Green Building Rough 9/21/2020 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 9/21/2020 Not Ready for Inspection JEFFREY FULTON
Reinforced Masonry Frame 9/21/2020 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 9/21/2020 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 9/21/2020 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 9/21/2020 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 9/22/2020 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 9/23/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 9/24/2020 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 9/28/2020 Conditional Approval JEFFREY FULTON
Insulation 9/28/2020 Approved HAMID PISHEHVAR
Drywall Nailing 9/29/2020 Partial Inspection JEFFREY FULTON
Insulation 9/29/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 10/1/2020 Partial Inspection JEFFREY FULTON
Insulation 10/3/2020 Partial Approval DANNY RODRIGUEZ
Light Gage Steel Frame 10/3/2020 Partial Approval DANNY RODRIGUEZ
Wood Frame 10/5/2020 Partial Inspection JEFFREY FULTON
Insulation 10/6/2020 Partial Approval ROBERT DAVIS
Interior/Exterior Lathing 10/6/2020 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 10/6/2020 Partial Approval ROBERT DAVIS
Drywall Nailing 10/7/2020 Partial Inspection JEFFREY FULTON
Wood Frame 10/7/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 10/8/2020 Partial Inspection JEFFREY FULTON
Wood Frame 10/8/2020 Partial Inspection JEFFREY FULTON
Insulation 10/10/2020 Partial Approval PAUL DAVIDSON
Light Gage Steel Frame 10/10/2020 Partial Approval PAUL DAVIDSON
Drywall Nailing 10/13/2020 Partial Inspection JEFFREY FULTON
Insulation 10/13/2020 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 10/13/2020 Not Ready for Inspection JEFFREY FULTON
Insulation 10/14/2020 Partial Inspection JEFFREY FULTON
Wood Frame 10/14/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 10/15/2020 No Access for Inspection JEFFREY FULTON
Insulation 10/15/2020 No Access for Inspection JEFFREY FULTON
Drywall Nailing 10/16/2020 Partial Inspection JEFFREY FULTON
Insulation 10/16/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 10/17/2020 Partial Approval JEFFREY DURAN
Insulation 10/17/2020 Partial Approval JEFFREY DURAN
Drywall Nailing 10/19/2020 Partial Inspection JEFFREY FULTON
Insulation 10/19/2020 Partial Inspection JEFFREY FULTON
Final 10/20/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 10/22/2020 Approved HAMID PISHEHVAR
Insulation 10/22/2020 Approved HAMID PISHEHVAR
Final 10/27/2020 Partial Inspection JEFFREY FULTON
Green Building Final 10/27/2020 Not Ready for Inspection JEFFREY FULTON
Green Building Rough 10/27/2020 Approved JEFFREY FULTON
Reinforced Concrete Frame 10/27/2020 Not Ready for Inspection JEFFREY FULTON
Reinforced Masonry Frame 10/27/2020 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 10/27/2020 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 10/27/2020 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 10/27/2020 Partial Inspection JEFFREY FULTON
Final 10/28/2020 Partial Inspection JEFFREY FULTON
Final 10/29/2020 Not Ready for Inspection JEFFREY FULTON
Special/Order Compliance 10/30/2020 Partial Inspection JEFFREY FULTON
Special/Order Compliance 11/2/2020 Partial Approval HAMID PISHEHVAR
Final 11/4/2020 Partial Inspection JEFFREY FULTON
Special/Order Compliance 11/5/2020 Partial Approval HAMID PISHEHVAR
Special/Order Compliance 11/6/2020 Approved HAMID PISHEHVAR
Final 11/9/2020 Partial Inspection JEFFREY FULTON
Special/Order Compliance 11/10/2020 Not Ready for Inspection HAMID PISHEHVAR
Special/Order Compliance 11/12/2020 Approved HAMID PISHEHVAR
Light Gage Steel Frame 11/16/2020 Partial Approval HAMID PISHEHVAR
Drywall Nailing 11/23/2020 Partial Approval JOHN KITCKO
Drywall Nailing 11/24/2020 Partial Approval ALAN NOVAK
Drywall Nailing 12/1/2020 Partial Approval HAMID PISHEHVAR
Drywall Nailing 12/2/2020 Not Ready for Inspection RICKEY JACKSON
Drywall Nailing 12/4/2020 Approved HAMID PISHEHVAR
Light Gage Steel Frame 12/7/2020 Approved HAMID PISHEHVAR
Drywall Nailing 12/17/2020 Approved HAMID PISHEHVAR
Drywall Nailing 12/23/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/8/2021 Partial Inspection JEFFREY FULTON
Drywall Nailing 1/22/2021 Approved HAMID PISHEHVAR
Special/Order Compliance 1/22/2021 Partial Approval HAMID PISHEHVAR
Special/Order Compliance 2/24/2021 Partial Inspection ROBERT DAVIS
Special/Order Compliance 3/15/2021 Partial Approval HAMID PISHEHVAR
Special/Order Compliance 3/16/2021 Approved HAMID PISHEHVAR
Special/Order Compliance 3/18/2021 Partial Inspection JEFFREY FULTON
Special/Order Compliance 3/22/2021 Approved HAMID PISHEHVAR
Special/Order Compliance 3/24/2021 Approved HAMID PISHEHVAR
Special/Order Compliance 3/25/2021 Partial Approval HAMID PISHEHVAR
Green Building Final 3/26/2021 Approved JEFFREY DURAN
Reinforced Concrete Frame 3/26/2021 Approved JEFFREY DURAN
Reinforced Masonry Frame 3/26/2021 Approved JEFFREY DURAN
SGSOV-Seismic Gas S/O Valve 3/26/2021 SGSOV Approved JEFFREY DURAN
Smoke Detectors 3/26/2021 Approved JEFFREY DURAN
Verify Sprinkler Sign Off 3/26/2021 Approved JEFFREY DURAN
Final 3/30/2021 Partial Inspection JEFFREY FULTON
Final 4/30/2021 OK to Issue CofO JEFFREY DURAN
Footing/Foundation/Slab 5/6/2021 No Access for Inspection JEFFREY DURAN