2712 W LYTELLE PL 90065

Certificate Information: 2712 W LYTELLE PL 90065

Application / Permit
18010-10000-04968
Plan Check / Job No.
B18LA21976
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY S.F.D. W/BASEMENT AND ATTACHED GARAGE.
Permit Issued
Issued on 11/24/2020
Issuing Office
Current Status
CofO Issued on 4/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/12/2018 APPLICANT
Assigned to Plan Check Engineer 11/15/2018 YAQUB MIRZA
Corrections Issued 11/21/2018 YAQUB MIRZA
Green Plans Picked Up 11/21/2018 APPLICANT
Building Plans Picked Up 12/11/2018 APPLICANT
Quality Review Completed 12/31/2018 HERNAN ARREOLA
Plan Check Approved 7/16/2019 YAQUB MIRZA
Issued 11/24/2020 APPLICANT
CofO in Progress 3/31/2023 CRAIG VAUGHAN
CofO in Progress 3/31/2023 CRAIG VAUGHAN
Permit Finaled 4/6/2023 DEROLD HAUFF
CofO Issued 4/6/2023 DEROLD HAUFF
Permit Finaled 4/6/2023 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 12/11/2018 NAZILA NOORIFAR
BHO/Hillside ordinance Cleared 12/11/2018 NAZILA NOORIFAR
BHO/Hillside ordinance Cleared 12/11/2018 NAZILA NOORIFAR
Eng Process Fee Ord 176,300 Cleared 2/1/2019 JEANETTE VONG
Hydrant and Access approval Cleared 2/1/2019 GEORGE SUCHAND
Sewer availability Cleared 2/1/2019 JEANETTE VONG
Green Code Cleared 2/6/2019 YAQUB MIRZA
Trees in Parkway Cleared 2/7/2019 ADRIAN SANCHEZ
Low Impact Development Cleared 3/8/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 3/8/2019 ELAINE LEI
Disturb/Remove Protected Trees Cleared 3/29/2019 JOHN KIM
Excavation more than 5-ft deep Cleared 6/28/2019 CALOSHA APPROVED
GPI Written Notices Cleared 6/28/2019 YAQUB MIRZA
Grading Pre-Inspection Cleared 6/28/2019 YAQUB MIRZA

Contact Information

Contractor Owner-Builder       ,
Engineer Khaliq,, Shehzad; Lic. No.: S4390 3456 GOLDEN POPPY WAY      YORBA LINDA, CA 92886

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 1/14/2021 No Access for Inspection CRAIG VAUGHAN
Special/Order Compliance 2/19/2021 Partial Inspection CRAIG VAUGHAN
Piling/Pier/Caisson 5/6/2021 Corrections Issued HAMIK HARTOUNIAN
Piling/Pier/Caisson 5/24/2021 No Access for Inspection CRAIG VAUGHAN
Piling/Pier/Caisson 6/4/2021 No Access for Inspection HAMIK HARTOUNIAN
Piling/Pier/Caisson 7/19/2021 Not Ready for Inspection CRAIG VAUGHAN
Deputy Methane Barrier 9/30/2021 No Access for Inspection CRAIG VAUGHAN
Deputy Methane Barrier 10/1/2021 No Access for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 10/29/2021 Corrections Issued KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 11/3/2021 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 12/9/2021 Partial Approval CRAIG VAUGHAN
Reinforced Concrete Frame 12/22/2021 Corrections Issued OSVALDO PARAMO
Reinforced Concrete Frame 12/29/2021 Not Ready for Inspection CRAIG VAUGHAN
Reinforced Concrete Frame 1/5/2022 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 2/3/2022 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 2/14/2022 Not Ready for Inspection CRAIG VAUGHAN
Sewer 2/14/2022 Approved CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 3/9/2022 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 3/9/2022 Partial Approval CRAIG VAUGHAN
Reinforced Concrete Frame 4/1/2022 Partial Approval CRAIG VAUGHAN
Reinforced Concrete Frame 4/14/2022 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 4/18/2022 Approved CRAIG VAUGHAN
Deputy Wood Construction 5/18/2022 Conditional Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 5/19/2022 Partial Approval CRAIG VAUGHAN
Wood Frame 5/19/2022 Not Ready for Inspection CRAIG VAUGHAN
Deputy Wood Construction 6/3/2022 Conditional Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 6/7/2022 Partial Approval CRAIG VAUGHAN
Green Building Rough 6/7/2022 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 6/7/2022 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 7/7/2022 Partial Inspection HAMIK HARTOUNIAN
Rough-Elec/Plmb/HVAC 7/12/2022 Not Ready for Inspection CRAIG VAUGHAN
Shower Pan 7/12/2022 Not Ready for Inspection CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 7/20/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Shower Pan 7/20/2022 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 8/4/2022 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 8/4/2022 Partial Approval CRAIG VAUGHAN
Green Building Rough 8/4/2022 Approved CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 8/4/2022 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 8/4/2022 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 8/11/2022 Approved OSVALDO PARAMO
PLUMBING-Rough 8/11/2022 Corrections Issued OSVALDO PARAMO
Gas Test 8/18/2022 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 8/18/2022 Partial Approval CRAIG VAUGHAN
Wood Frame 8/22/2022 Approved CRAIG VAUGHAN
Insulation 8/25/2022 Approved CRAIG VAUGHAN
Drywall Nailing 9/2/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 9/20/2022 Approved CRAIG VAUGHAN
Sewer 12/7/2022 Approved HAMIK HARTOUNIAN
Service/Power Release 1/24/2023 Corrections Issued CRAIG VAUGHAN
Service/Power Release 1/30/2023 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/8/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Final 2/8/2023 Partial Approval CRAIG VAUGHAN
Final 2/8/2023 Corrections Issued CRAIG VAUGHAN
Green Building Final 2/8/2023 Approved CRAIG VAUGHAN
HVAC-Final 2/8/2023 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Final 2/8/2023 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 2/8/2023 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 2/8/2023 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 2/8/2023 Approved CRAIG VAUGHAN
Final 2/15/2023 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 2/15/2023 Approved CRAIG VAUGHAN
HVAC-Final 2/15/2023 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 2/15/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 2/15/2023 SGSOV Approved CRAIG VAUGHAN
Final 3/22/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 3/22/2023 SGSOV Approved ALIZAH MAYAGOITIA
Final 3/30/2023 OK to Issue CofO CRAIG VAUGHAN