614 E 28TH ST 90011
Certificate Information: 614 E 28TH ST 90011
- Application / Permit
- 18010-10000-04798
- Plan Check / Job No.
- B18LA21243
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2 - STORY ACCESSORY DWELLING UNIT PER AB494 AND SB229.
- Permit Issued
- Issued on 1/27/2020
- Issuing Office
- Metro
- Current Status
- Issued on 1/27/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/3/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2018 | ANA AVELAR |
| Green Plans Picked Up | 11/9/2018 | APPLICANT |
| Corrections Issued | 11/14/2018 | ANA AVELAR |
| Quality Review Completed | 11/30/2018 | KESETE HAREGOT |
| Building Plans Picked Up | 12/3/2018 | APPLICANT |
| Applicant returned to address corrections | 10/8/2019 | JOHNNY WU |
| Applicant returned to address corrections | 1/24/2020 | JOHNNY WU |
| Plan Check Approved | 1/24/2020 | JOHNNY WU |
| Issued | 1/27/2020 | LADBS |
Permit Application Clearance Information
| Address approval | Cleared | 5/30/2019 | ZIXUAN CHEN |
| Eng Process Fee Ord 176,300 | Cleared | 5/30/2019 | ZIXUAN CHEN |
| Hydrant and Access approval | Cleared | 5/30/2019 | GEORGE SUCHAND |
| Sewer availability | Cleared | 5/30/2019 | ZIXUAN CHEN |
| Highway dedication | Cleared | 12/4/2019 | CELINA MORENO |
| ZI | Cleared | 12/4/2019 | JOE LUCKEY |
| Low Impact Development | Cleared | 12/16/2019 | MARTIN FRAGOSO |
| Green Code | Cleared | 1/8/2020 | ANA AVELAR |
| Roof/Waste drainage to street | Cleared | 1/24/2020 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVENUE LONG BEACH, CA 90813 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/14/2020 | Partial Approval | ROBERT MCDOWELL |
| Sewer | 8/14/2020 | Approved | ROBERT MCDOWELL |
| Excavation/Setback/Form/Re-Bar | 8/28/2020 | Corrections Issued | COREY HUPP |
| Footing/Foundation/Slab | 10/14/2020 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Wood Frame | 4/19/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 5/10/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 5/11/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Green Building Rough | 5/11/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 5/11/2022 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 8/22/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 9/2/2022 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 9/2/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 9/2/2022 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 9/7/2022 | Approved | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 9/16/2022 | Approved | RYAN SALAZAR |
| Green Building Rough | 9/16/2022 | Approved | RYAN SALAZAR |
| Insulation | 9/16/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/16/2022 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 11/8/2022 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 11/8/2022 | Approved | LILIANA PORTILLO |