New 4-story 25-unit affordable housing apartment building with 2 units set aside for Extremely low income per 12.22A31. VA over subterranean basement garage I-A. TOC affordable housing project.
Permit Issued
Issued on 5/2/2022
Issuing Office
Metro
Current Status
Issued on 5/2/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/9/2018 APPLICANT
Assigned to Plan Check Engineer 10/27/2018 HERNAN ARREOLA
Corrections Issued 11/5/2018 HERNAN ARREOLA
Quality Review Completed 11/14/2018 BILL STUTSMAN
Building Plans Picked Up 12/31/2018 APPLICANT
Disabled Access Plans Picked Up 12/31/2018 APPLICANT
Plan Check Approved 4/29/2022 HERNAN ARREOLA
Issued 5/2/2022 APPLICANT
TCO Issued (Expire Date: 05-06-2026) 11/7/2025 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 1/29/2019 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/29/2019 JEANIE LAM
Highway dedication Cleared 1/29/2019 JEANIE LAM
Sewer availability Cleared 1/29/2019 JEANIE LAM
Permit Cleared 3/3/2021 JEANIE LAM
Building over 3-story or 36-ft Cleared 3/16/2021 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 3/16/2021 CALOSHA APPROVED
Hydrant and Access approval Cleared 5/12/2021 JOHN CONNEALLY
Density Bonus 12.22.A.31 Cleared 7/13/2021 MICHAEL ZIRBES
Work Adjacent to Public Way Cleared 11/16/2021 BOK GOH
Low Impact Development Cleared 1/12/2022 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 1/28/2022 AMAAN MALIK
Green Code Cleared 3/10/2022 AARON COSTA
Fire Marshall Fire Life Safety Cleared 3/15/2022 WILLIAM JOHNS
DAS Clearance Cleared 3/31/2022 EDDIE GARIN
Frnt yard landscape/Water mgmt Cleared 4/19/2022 DANIEL CORONADO
Miscellaneous Cleared 4/19/2022 DANIEL CORONADO
Miscellaneous Cleared 4/19/2022 DANIEL CORONADO
Opn space landscape/Water mgmt Cleared 4/19/2022 DANIEL CORONADO
Miscellaneous Cleared 4/21/2022 DANIEL CORONADO

Contact Information

Architect Maly,, Farzin; Lic. No.: C33731 7136 HASKELL AVENUE # 320      VAN NUYS, CA 91406
Contractor I D C S Corporation; Lic. No.: 995061-B 9854 NATIONAL BLVD #162      LOS ANGELES, CA 90034
Engineer Jahani,, Fereidoun; Lic. No.: C62875 3720 BLANCHE ST      PASADENA, CA 91107
Engineer Nguyen,, Tuan Minh; Lic. No.: S5883 5552 W 123RD PLACE      HAWTHORNE, CA 90250

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/5/2022 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 5/5/2022 Approved EDWIN GREGORYONA
METHANE-Subgrade 5/5/2022 Approved EDWIN GREGORYONA
Deputy Reinf. Concrete 5/9/2022 Partial Approval EDWIN GREGORYONA
Reinforced Masonry Frame 5/19/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 5/23/2022 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 5/23/2022 Partial Approval DAVID BURKHEAD
Deputy Shotcrete 5/24/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 6/30/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 6/30/2022 Partial Approval EDWIN GREGORYONA
Pre-Inspection 7/18/2022 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 7/18/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 7/20/2022 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 7/20/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 7/20/2022 Partial Approval EDWIN GREGORYONA
Reinforced Masonry Frame 7/20/2022 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 7/22/2022 Conditional Approval WINSTON DUNNING
Reinforced Masonry Frame 8/8/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/17/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 9/23/2022 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 10/3/2022 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 10/7/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 11/21/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/22/2022 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 11/23/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 11/30/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 12/28/2022 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 2/21/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 2/22/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/30/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 4/10/2023 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 4/18/2023 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Rough 4/18/2023 Approved EDWIN GREGORYONA
Verify Sprinkler Sign Off 4/18/2023 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 4/18/2023 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 5/25/2023 Partial Approval ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 5/25/2023 Partial Approval ALAN MORELOS
Insulation 7/5/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 8/14/2023 Corrections Issued EDWIN GREGORYONA
Green Building Rough 8/14/2023 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 8/14/2023 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 8/14/2023 Not Ready for Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 9/15/2023 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 1/5/2024 Approved EDWIN GREGORYONA
Interior/Exterior Lathing 1/9/2024 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 1/30/2024 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 2/6/2024 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 2/13/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 3/4/2024 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 3/27/2024 Partial Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 4/9/2024 Partial Approval EDWIN GREGORYONA
Green Building Rough 4/16/2024 Approved EDWIN GREGORYONA
Verify Sprinkler Sign Off 4/16/2024 Approved EDWIN GREGORYONA
Wood Frame 4/16/2024 Partial Approval EDWIN GREGORYONA
Pre-Inspection 4/29/2024 Partial Inspection EDWIN GREGORYONA
Wood Frame 5/24/2024 Partial Approval EDWIN GREGORYONA
Special/Order Compliance 5/29/2024 Approved EDWIN GREGORYONA
Drywall Nailing 5/30/2024 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 5/30/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 7/3/2024 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 7/3/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 8/16/2024 Partial Approval NICK DANERI
Reinforced Concrete Frame 8/20/2024 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 8/23/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 8/27/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 9/26/2024 Partial Approval LARRY ARNICK
Drywall Nailing 9/27/2024 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 10/3/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 10/18/2024 Partial Approval RAFAEL CORTES
Drywall Nailing 10/21/2024 Partial Approval EDWIN GREGORYONA
Insulation 12/16/2024 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 12/24/2024 Partial Approval MARTIN TAVITIAN
Insulation 2/20/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 2/25/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 3/21/2025 Approved EDWIN GREGORYONA
Drywall Nailing 4/7/2025 Not Ready for Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 4/10/2025 Partial Approval EDWIN GREGORYONA
Wood Frame 5/20/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 6/2/2025 Partial Approval EDWIN GREGORYONA
Final 9/30/2025 Partial Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 9/30/2025 Approved EDWIN GREGORYONA
Green Building Final 9/30/2025 Not Ready for Inspection EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 9/30/2025 SGSOV Not Ready EDWIN GREGORYONA
Smoke Detectors 9/30/2025 Approved EDWIN GREGORYONA
Wood Frame 9/30/2025 Approved EDWIN GREGORYONA
Final 3/31/2026 Conditional Approval MARTIN TAVITIAN
Green Building Final 3/31/2026 Approved MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 3/31/2026 SGSOV Approved MARTIN TAVITIAN
Special/Order Compliance 4/7/2026 Approved MARTIN TAVITIAN
Final 6/3/2026 Not Ready for Inspection MARTIN TAVITIAN