2555 S MANSFIELD AVE 90016

Certificate Information: 2555 S MANSFIELD AVE 90016

Application / Permit
18010-10000-04760
Plan Check / Job No.
B18LA20941
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
New 5-story 69-unit mixed used apartment building III-A over 1 story I-A with subterranean basement garage, Core and shell for retail and restaurant only. TOC 2 affordable housing project. "COMPLY WITH DEPARTMENT ORDER effective date 08/31/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 6/21/2021
Issuing Office
Metro
Current Status
CofO Issued on 5/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/10/2018 APPLICANT
Assigned to Plan Check Engineer 10/18/2018 LARRY LEE
Corrections Issued 11/6/2018 LARRY LEE
Quality Review Completed 11/15/2018 WING SUEN
Disabled Access Plans Picked Up 11/29/2018 APPLICANT
Green Plans Picked Up 11/29/2018 APPLICANT
Building Plans Picked Up 11/30/2018 APPLICANT
Applicant returned to address corrections 1/3/2019 LARRY LEE
Applicant returned to address corrections 1/30/2019 LARRY LEE
Applicant returned to address corrections 4/17/2019 LARRY LEE
Applicant returned to address corrections 10/15/2019 LARRY LEE
Applicant returned to address corrections 2/5/2020 LARRY LEE
Applicant returned to address corrections 8/7/2020 LARRY LEE
Applicant returned to address corrections 8/31/2020 LARRY LEE
Applicant returned to address corrections 10/8/2020 LARRY LEE
Plan Check Approved 10/14/2020 LARRY LEE
Issued 6/21/2021 APPLICANT
TCO Issued (Expire Date: 10-02-2024) 4/5/2024 RAFAEL ESPINOZA
CofO in Progress 4/19/2024 EDWIN GREGORYONA
CofO Issued 5/1/2024 ERNESTO CORRAL
Permit Finaled 5/1/2024 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/6/2019 JEANETTE VONG
Permit Cleared 3/6/2019 JEANETTE VONG
Building over 3-story or 36-ft Cleared 10/15/2019 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 10/15/2019 CALOSHA APPROVED
Green Code Cleared 10/15/2019 KHEDER ALRAZAA
Address approval Cleared 10/16/2019 ERIK BEASLEY
Miscellaneous Cleared 10/16/2019 ERIK BEASLEY
Project located in CRA area Cleared 10/24/2019 JIM URQUHART
Hydrant and Access approval Cleared 10/25/2019 JOHN CONNEALLY
Highway dedication Cleared 12/20/2019 JEANIE LAM
Low Impact Development Cleared 12/20/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 12/20/2019 JEANIE LAM
"D" conditions Cleared 2/5/2020 JOE LUCKEY
Density Bonus 12.22.A.31 Cleared 2/5/2020 MICHAEL ZIRBES
Fire Marshall Fire Life Safety Cleared 2/5/2020 VIDAL GARCIA
Miscellaneous Cleared 2/5/2020 JOE LUCKEY
Opn space landscape/Water mgmt Cleared 2/5/2020 JOE LUCKEY
Site Plan review Cleared 2/5/2020 JOE LUCKEY
Tract Map conditions Cleared 2/5/2020 JOE LUCKEY
ZA Case Cleared 2/5/2020 JOE LUCKEY
ZA Case Cleared 2/5/2020 JOE LUCKEY
ZA Case Cleared 2/5/2020 JOE LUCKEY
ZA Case Cleared 2/5/2020 JOE LUCKEY
ZI Cleared 2/5/2020 JOE LUCKEY
Trees in Parkway Cleared 3/6/2020 ADRIAN SANCHEZ
Community Plan Implem. Overlay Cleared 3/9/2020 JOE LUCKEY
DAS Clearance Cleared 6/9/2020 LARRY LEE
Food Service Establishment Cleared 8/12/2020 JASH PATEL
Sewer availability Cleared 8/13/2020 JAMES KHO
Specific Plan Cleared 8/26/2020 EDUARDO HERMOSO
Work Adjacent to Public Way Cleared 9/8/2020 BOK GOH
Community Plan Implem. Overlay Cleared 6/8/2021 MOHAMMAD HASAN
Community Plan Implem. Overlay Cleared 6/8/2021 THAN WIN
Miscellaneous Cleared 6/8/2021 JOE LUCKEY
Miscellaneous Cleared 6/8/2021 JOE LUCKEY
Miscellaneous Cleared 6/8/2021 JOE LUCKEY

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: S5421       ,

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 6/23/2021 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 6/24/2021 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 6/25/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 8/5/2021 Partial Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 8/26/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 9/15/2021 Partial Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 10/18/2021 Partial Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 10/28/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 10/28/2021 Partial Approval EDWIN GREGORYONA
Reinforced Concrete Frame 11/3/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 11/8/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 11/9/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 11/10/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 11/10/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 11/12/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 11/12/2021 Not Ready for Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 11/13/2021 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 11/13/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 11/15/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 11/22/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 12/2/2021 Partial Inspection DAVID BURKHEAD
Footing/Foundation/Slab 12/2/2021 Not Ready for Inspection DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 12/10/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 12/14/2021 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 12/14/2021 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 12/15/2021 Partial Approval EDWIN GREGORYONA
Special/Order Compliance 12/15/2021 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 12/17/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 12/17/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 12/20/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 12/21/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 12/22/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 12/22/2021 Partial Approval EDWIN GREGORYONA
Deputy Other (see comments) 12/27/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 12/27/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 12/28/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 12/28/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 12/29/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 12/29/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 12/30/2021 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 1/4/2022 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 1/4/2022 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 1/4/2022 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 1/5/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 1/6/2022 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 1/6/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 1/7/2022 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 1/7/2022 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 1/10/2022 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 1/18/2022 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 1/18/2022 Not Ready for Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 1/25/2022 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 1/25/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 1/27/2022 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 1/31/2022 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 1/31/2022 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 2/1/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 2/2/2022 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 2/2/2022 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 2/3/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 2/4/2022 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 2/4/2022 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 2/4/2022 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 2/7/2022 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 2/7/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Shotcrete 2/8/2022 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 2/8/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 2/9/2022 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 2/9/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 2/11/2022 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Masonry Frame 2/11/2022 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 2/11/2022 Not Ready for Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 2/25/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 2/28/2022 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 3/3/2022 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 3/10/2022 Partial Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 3/11/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 3/22/2022 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Masonry Frame 3/22/2022 Partial Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 3/22/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 4/5/2022 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 4/12/2022 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 4/14/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 4/27/2022 Not Ready for Inspection RUSSELL BONVOULOIR
Light Gage Steel Frame 4/27/2022 Not Ready for Inspection RUSSELL BONVOULOIR
Drywall Nailing 4/29/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 5/20/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 5/23/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 5/27/2022 Not Ready for Inspection DAVID BURKHEAD
Drywall Nailing 5/31/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 6/6/2022 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 6/7/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 6/13/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 6/15/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 6/21/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 6/28/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 6/29/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 7/7/2022 Partial Approval EDWIN GREGORYONA
Insulation 7/7/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 7/14/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 7/18/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 8/11/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 8/12/2022 Partial Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 8/15/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/17/2022 Partial Inspection GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 8/19/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 9/7/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 9/19/2022 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 10/11/2022 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 10/26/2022 Partial Approval EDWIN GREGORYONA
Wood Frame 10/31/2022 Partial Inspection EDWIN GREGORYONA
Interior/Exterior Lathing 11/2/2022 Partial Approval EDWIN GREGORYONA
Wood Frame 11/2/2022 Partial Approval EDWIN GREGORYONA
Wood Frame 11/4/2022 Partial Inspection EDWIN GREGORYONA
Interior/Exterior Lathing 11/8/2022 Not Ready for Inspection EDWIN GREGORYONA
Interior/Exterior Lathing 11/14/2022 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 11/16/2022 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 11/17/2022 Partial Approval EDWIN GREGORYONA
Wood Frame 11/18/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 11/28/2022 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 11/30/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 11/30/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 12/1/2022 Partial Approval EDWIN GREGORYONA
Wood Frame 12/12/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 12/15/2022 Partial Approval EDWIN GREGORYONA
Wood Frame 12/21/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 12/28/2022 Partial Approval EDWIN GREGORYONA
Drywall Nailing 1/5/2023 Partial Approval EDWIN GREGORYONA
Special/Order Compliance 1/12/2023 Approved EDWIN GREGORYONA
Drywall Nailing 1/31/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 2/17/2023 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 3/9/2023 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 3/9/2023 Not Ready for Inspection GREGORY POMISH
Insulation 4/6/2023 Approved EDWIN GREGORYONA
Special/Order Compliance 4/6/2023 Approved EDWIN GREGORYONA
Special/Order Compliance 7/14/2023 Approved EDWIN GREGORYONA
Green Building Final 8/30/2023 Partial Inspection EDWIN GREGORYONA
Green Building Rough 3/13/2024 Approved EDWIN GREGORYONA
Smoke Detectors 3/13/2024 Approved EDWIN GREGORYONA
Verify Sprinkler Sign Off 3/13/2024 Approved EDWIN GREGORYONA
Green Building Final 3/22/2024 Approved EDWIN GREGORYONA
Final 4/19/2024 OK to Issue CofO EDWIN GREGORYONA
Footing/Foundation/Slab 4/19/2024 Approved EDWIN GREGORYONA
Reinforced Concrete Frame 4/19/2024 Approved EDWIN GREGORYONA
Reinforced Masonry Frame 4/19/2024 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 4/19/2024 SGSOV Approved EDWIN GREGORYONA