462 N CRANE BLVD 90065

Certificate Information: 462 N CRANE BLVD 90065

Application / Permit
18010-10000-04703
Plan Check / Job No.
B18LA20660
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW TWO STORY SIGNLE-FAMILY DWELLING WITH ATTACED 2 CAR GARAGE.
Permit Issued
Issued on 3/16/2020
Issuing Office
Metro
Current Status
CofO Issued on 10/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/26/2018 APPLICANT
Assigned to Plan Check Engineer 11/1/2018 GARO TELMI
Green Plans Picked Up 11/13/2018 APPLICANT
Corrections Issued 11/19/2018 GARO TELMI
Quality Review Completed 11/20/2018 JOHN FRANCIA
Building Plans Picked Up 12/6/2018 APPLICANT
Applicant returned to address corrections 1/16/2019 GARO TELMI
Applicant returned to address corrections 3/13/2019 GARO TELMI
Applicant returned to address corrections 3/28/2019 GARO TELMI
Applicant returned to address corrections 1/14/2020 GARO TELMI
Plan Check Approved 1/28/2020 GARO TELMI
Issued 3/16/2020 LADBS
No Progress 10/11/2025 ALIZAH MAYAGOITIA
CofO in Progress 10/11/2025 ALIZAH MAYAGOITIA
CofO in Progress 10/14/2025 ALIZAH MAYAGOITIA
No Progress 10/14/2025 CHARLES BOGHOSKHAN
CofO in Progress 10/14/2025 CHARLES BOGHOSKHAN
Permit Finaled 10/29/2025 DEROLD HAUFF
CofO Issued 10/29/2025 DEROLD HAUFF
Permit Finaled 10/29/2025 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 1/9/2019 GARO TELMI
Address approval Cleared 1/31/2019 JEANETTE VONG
BHO/Hillside ordinance Cleared 1/31/2019 JEANETTE VONG
BHO/Hillside ordinance Cleared 1/31/2019 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 1/31/2019 JEANETTE VONG
Permit Cleared 1/31/2019 JEANETTE VONG
Trees in Parkway Cleared 1/31/2019 ADRIAN SANCHEZ
Disturb/Remove Protected Trees Cleared 3/4/2019 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 3/13/2019 JEANETTE VONG
GPI Written Notices Cleared 3/13/2019 TODD MALAND
Grading Pre-Inspection Cleared 3/13/2019 TODD MALAND
Miscellaneous Cleared 3/13/2019 ANNA VAN
Sewer availability Cleared 3/13/2019 JEANETTE VONG
Hydrant and Access approval Cleared 3/28/2019 GEORGE SUCHAND
Low Impact Development Cleared 5/7/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 5/7/2019 CELINA MORENO
Drainage to Storm Drain Cleared 5/10/2019 NGOC KIEM
Miscellaneous Cleared 1/15/2020 DENZEL HENDERSON
Specific Plan Cleared 1/15/2020 DENZEL HENDERSON

Contact Information

Contractor Owner-Builder       ,
Engineer Darvasan-Stanciu,, George; Lic. No.: L7884 825 E COLTON AVE      REDLANDS, CA 92374
Engineer Labib,, Youhanna T; Lic. No.: S4549 319 MAIN STREET      EL SEGUNDO, CA 90245
Engineer Lee,, Shyan-Chyun Tony; Lic. No.: C44045 17834 BAILEY DRIVE      TORRANCE, CA 90504

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/21/2021 Partial Inspection OSVALDO PARAMO
Piling/Pier/Caisson 10/21/2021 Partial Inspection OSVALDO PARAMO
Piling/Pier/Caisson 11/15/2021 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 1/19/2022 Partial Approval OSVALDO PARAMO
Piling/Pier/Caisson 1/19/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 3/7/2022 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 3/9/2022 Conditional Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 3/22/2022 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 3/23/2022 Conditional Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 3/23/2022 Partial Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 5/26/2022 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 6/1/2022 Conditional Approval OSVALDO PARAMO
Piling/Pier/Caisson 8/4/2022 Partial Approval OSVALDO PARAMO
Deputy Steel/Welding 8/25/2022 Conditional Approval OSVALDO PARAMO
Deputy Steel/Welding 8/26/2022 Conditional Approval OSVALDO PARAMO
Deputy Steel/Welding 8/30/2022 Conditional Approval OSVALDO PARAMO
Deputy Steel/Welding 8/31/2022 Conditional Approval OSVALDO PARAMO
Deputy Steel/Welding 9/1/2022 Conditional Approval OSVALDO PARAMO
Deputy Steel/Welding 9/2/2022 Conditional Approval OSVALDO PARAMO
Deputy Drilled-In Anchors 11/2/2022 Conditional Approval OSVALDO PARAMO
Structural Steel Frame 11/9/2022 Partial Approval OSVALDO PARAMO
Structural Steel Frame 11/17/2022 Approved OSVALDO PARAMO
Deputy Reinf. Concrete 11/21/2022 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 4/11/2023 Partial Inspection OSVALDO PARAMO
PLUMBING-Rough 6/16/2023 Approved OSVALDO PARAMO
ELECTRICAL-Rough 6/20/2023 Not Ready for Inspection OSVALDO PARAMO
HVAC-Rough 6/20/2023 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 6/21/2023 Approved OSVALDO PARAMO
Green Building Rough 6/21/2023 Approved OSVALDO PARAMO
Structural Steel Frame 6/21/2023 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 6/21/2023 Approved OSVALDO PARAMO
Insulation 7/25/2023 Approved BRENDAN MORELLI
Drywall Nailing 8/3/2023 Approved ALIZAH MAYAGOITIA
Shower Pan 9/7/2023 Approved JOSH MEISTER
Interior/Exterior Lathing 10/3/2023 Approved OSVALDO PARAMO
Sewer 1/30/2024 Approved OSVALDO PARAMO
Footing/Foundation/Slab 7/5/2024 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 7/9/2024 Partial Approval OSVALDO PARAMO
ELECTRICAL-Final 8/8/2024 Partial Approval OSVALDO PARAMO
HVAC-Final 8/8/2024 Approved OSVALDO PARAMO
Final 10/2/2024 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 10/2/2024 Approved OSVALDO PARAMO
Green Building Final 10/2/2024 Approved OSVALDO PARAMO
Reinforced Masonry Frame 10/2/2024 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 10/2/2024 SGSOV Approved OSVALDO PARAMO
Service/Power Release 10/2/2024 Not Ready for Inspection OSVALDO PARAMO
Smoke Detectors 10/2/2024 Approved OSVALDO PARAMO
Final 11/6/2024 Partial Approval ALIZAH MAYAGOITIA
Service/Power Release 11/6/2024 Approved ALIZAH MAYAGOITIA
Final 10/8/2025 Conditional Approval ALIZAH MAYAGOITIA
Final 10/14/2025 OK to Issue CofO ALIZAH MAYAGOITIA