2025 E NEW JERSEY ST 90033

Certificate Information: 2025 E NEW JERSEY ST 90033

Application / Permit
18010-10000-04650
Plan Check / Job No.
B18LA20371
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 3-STORY, TYPE VA, 15 UNIT APARTMENT BUILDING, AFFORDABLE TOC TIER 4 HOUSING PROJECT RESTRICTING 14 UNITS FOR 2 ELI, 1 VLI, & 11 LI HOUSEHOLDS.
Permit Issued
Issued on 1/21/2021
Issuing Office
Metro
Current Status
CofO Issued on 2/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/21/2018 APPLICANT
Disabled Access Plans Picked Up 10/17/2018 APPLICANT
Assigned to Plan Check Engineer 10/18/2018 KESETE HAREGOT
Corrections Issued 12/7/2018 KESETE HAREGOT
Quality Review Completed 12/7/2018 QUAN NGHIEM
Applicant returned to address corrections 9/5/2019 KESETE HAREGOT
Applicant returned to address corrections 3/2/2020 KESETE HAREGOT
Green Plans Picked Up 9/15/2020 APPLICANT
Plan Check Approved 9/28/2020 KESETE HAREGOT
Issued 1/21/2021 APPLICANT
Building Plans Picked Up 1/25/2021 APPLICANT
CofO in Progress 2/6/2024 RAFAEL ESPINOZA
CofO Issued 2/6/2024 ERNESTO CORRAL
Permit Finaled 2/6/2024 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 1/9/2019 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 1/9/2019 JEANETTE VONG
Highway dedication Cleared 1/9/2019 JEANETTE VONG
Permit Cleared 1/9/2019 JEANETTE VONG
"Q" conditions Cleared 5/19/2020 ANNA VIDAL
Clean Up Green Up Cleared 5/19/2020 ANNA VIDAL
Sewer availability Cleared 5/20/2020 JUAN ASHTON
Low Impact Development Cleared 6/17/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 6/17/2020 JUAN ASHTON
Frnt yard landscape/Water mgmt Cleared 6/22/2020 TERRI OSBORNE
Opn space landscape/Water mgmt Cleared 6/22/2020 TERRI OSBORNE
Green Code Cleared 6/30/2020 COLIN LOREDO
Hydrant and Access approval Cleared 7/16/2020 MATTHEW CRAIG
Density Bonus 12.22.A.31 Cleared 7/31/2020 MICHAEL ZIRBES
DAS Clearance Cleared 8/10/2020 SHINE LIN
Fire Marshall Fire Life Safety Cleared 8/11/2020 OSCAR SALGADO JR
Building over 3-story or 36-ft Cleared 9/14/2020 CALOSHA APPROVED
GPI Written Notices Cleared 9/28/2020 KESETE HAREGOT
Grading Pre-Inspection Cleared 9/28/2020 KESETE HAREGOT

Contact Information

Contractor Owner-Builder       ,
Engineer Afsharhasani,, Rouzbeh; Lic. No.: C87032 1133 CAMELBACK ST 9038      NEWPORT BEACH, CA 92658
Engineer Bozorgnia,, Behrouz; Lic. No.: C79581 1557 WESTWOOD BLVD 145      LOS ANGELES, CA 90024
Engineer Plouff,, Kacie Allison; Lic. No.: L9013 27821 FREMONT COURT 6      VALENCIA, CA 91355

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/6/2021 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 4/15/2021 Not Ready for Inspection RONALD PACHECO
Footing/Foundation/Slab 5/4/2021 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 5/7/2021 Partial Approval NICK DANERI
Footing/Foundation/Slab 5/18/2021 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 8/27/2021 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 8/30/2021 Conditional Approval RAFAEL ESPINOZA
Green Building Rough 8/30/2021 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Wood Construction 9/17/2021 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/21/2021 Partial Approval RAFAEL ESPINOZA
Green Building Rough 9/21/2021 Not Ready for Inspection RAFAEL ESPINOZA
Wood Frame 10/25/2021 Partial Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/7/2021 Partial Approval RAFAEL ESPINOZA
Insulation 8/4/2022 Not Ready for Inspection TED RIES
Insulation 8/10/2022 Corrections Issued RAFAEL ESPINOZA
Insulation 8/17/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 9/16/2022 Not Ready for Inspection RAFAEL ESPINOZA
Drywall Nailing 9/30/2022 Partial Approval RAFAEL ESPINOZA
Insulation 9/30/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 10/19/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 11/22/2022 Approved RAFAEL ESPINOZA
Green Building Rough 12/6/2022 Approved RAFAEL ESPINOZA
Interior/Exterior Lathing 12/6/2022 Not Ready for Inspection RAFAEL ESPINOZA
Interior/Exterior Lathing 12/9/2022 Approved RAFAEL ESPINOZA
Special/Order Compliance 1/17/2023 Partial Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 4/4/2023 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 4/27/2023 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 5/11/2023 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 5/15/2023 Partial Approval RAFAEL ESPINOZA
Final 8/16/2023 Corrections Issued RAFAEL ESPINOZA
Drywall Nailing 12/26/2023 Partial Approval NICK DANERI
Final 1/25/2024 Partial Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 1/25/2024 Approved RAFAEL ESPINOZA
Green Building Final 1/25/2024 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 1/25/2024 SGSOV Approved RAFAEL ESPINOZA
Smoke Detectors 1/25/2024 Approved RAFAEL ESPINOZA
Verify Sprinkler Sign Off 1/25/2024 Approved RAFAEL ESPINOZA
Wood Frame 1/25/2024 Partial Inspection RAFAEL ESPINOZA
Final 2/6/2024 OK to Issue CofO RAFAEL ESPINOZA
Wood Frame 2/6/2024 Approved RAFAEL ESPINOZA