1814 W 51ST ST 90062

Certificate Information: 1814 W 51ST ST 90062

Application / Permit
18010-10000-04602
Plan Check / Job No.
B18LA20128
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. **2 OF 2**
Permit Issued
Issued on 9/27/2018
Issuing Office
Metro
Current Status
CofO Issued on 6/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2018 APPLICANT
Assigned to Plan Check Engineer 9/20/2018 KEVIN MORALES
Corrections Issued 9/20/2018 KEVIN MORALES
Plan Check Approved 9/27/2018 MICHAEL LOPEZ
Issued 9/27/2018 LADBS
CofO in Progress 6/15/2023 SABAS ALONSO
Permit Finaled 6/27/2023 DEROLD HAUFF
CofO Issued 6/27/2023 DEROLD HAUFF
Permit Finaled 6/27/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/20/2018 NAZILA NOORIFAR
Eng Process Fee Ord 176,300 Cleared 9/20/2018 NAZILA NOORIFAR
Sewer availability Cleared 9/20/2018 NAZILA NOORIFAR
Low Impact Development Cleared 9/25/2018 JORGE MEJIA LEMUS
Miscellaneous Cleared 9/25/2018 SOPHEA EK
Hold Cleared 9/27/2018 LOURDES RAMIRO
Roof/Waste drainage to street Cleared 9/27/2018 MICHAEL CASTILLO

Contact Information

Engineer Cooke, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/18/2018 Corrections Issued VICTOR PUKHALSKY
Excavation/Setback/Form/Re-Bar 2/1/2019 Corrections Issued VICTOR PUKHALSKY
Footing/Foundation/Slab 2/8/2019 Partial Approval LUIS ALVAREZ
Floor/Roof Diaphrgm/Shear Wall 3/14/2019 Conditional Approval RAUL BARAJAS
BUILDING-Rough-Frame 3/19/2019 Not Ready for Inspection VICTOR PUKHALSKY
ELECTRICAL-Rough 3/19/2019 Corrections Issued VICTOR PUKHALSKY
Green Building Rough 3/19/2019 Not Ready for Inspection VICTOR PUKHALSKY
PLUMBING-Rough 3/19/2019 Corrections Issued VICTOR PUKHALSKY
Verify Sprinkler Sign Off 3/19/2019 Approved VICTOR PUKHALSKY
BUILDING-Rough-Frame 3/27/2019 Partial Approval VICTOR PUKHALSKY
ELECTRICAL-Rough 3/27/2019 Partial Approval VICTOR PUKHALSKY
Green Building Rough 3/27/2019 Corrections Issued VICTOR PUKHALSKY
PLUMBING-Rough 3/27/2019 Partial Approval VICTOR PUKHALSKY
ELECTRICAL-Rough 4/8/2019 Approved VICTOR PUKHALSKY
Green Building Rough 4/8/2019 Approved VICTOR PUKHALSKY
Insulation 4/8/2019 Approved VICTOR PUKHALSKY
PLUMBING-Rough 4/8/2019 Approved VICTOR PUKHALSKY
Drywall Nailing 4/23/2019 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/23/2022 Approved SABAS ALONSO
Final 9/23/2022 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 9/23/2022 Approved SABAS ALONSO
Green Building Final 9/23/2022 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/23/2022 SGSOV Not Ready SABAS ALONSO
Service/Power Release 9/23/2022 Not Required SABAS ALONSO
Smoke Detectors 9/23/2022 Approved SABAS ALONSO
Final 2/16/2023 Corrections Issued SABAS ALONSO
Green Building Final 2/16/2023 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 2/16/2023 SGSOV Not Ready SABAS ALONSO
Final 3/6/2023 Corrections Issued STUART CHAPMAN
Green Building Final 3/6/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 3/6/2023 SGSOV Approved STUART CHAPMAN
Final 3/22/2023 Corrections Issued ENRIQUE MIRELES
Final 5/31/2023 Corrections Issued ENRIQUE MIRELES
Final 6/14/2023 OK to Issue CofO SABAS ALONSO