11743 W AVON WAY 90066
Certificate Information: 11743 W AVON WAY 90066
- Application / Permit
- 18010-10000-04450
- Plan Check / Job No.
- B18LA19422
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 4 STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND ROOF DECK. (LOT 1) Small lot subdivision pursuant to Tentative Tract Map No./Preliminary Parcel Map No. 74945. A certificate of occupany (temporary or final) shall not be issued until after the final map has been recorded.
- Permit Issued
- Issued on 1/27/2020
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 9/28/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/11/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/11/2018 | TEODORO DIAZ RODRIGUEZ |
| Green Plans Picked Up | 10/23/2018 | APPLICANT |
| Corrections Issued | 10/25/2018 | TEODORO DIAZ RODRIGUEZ |
| Quality Review Completed | 11/1/2018 | SIAVOSH POURSABAHIAN |
| Building Plans Picked Up | 11/6/2018 | APPLICANT |
| Applicant returned to address corrections | 2/12/2019 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 12/13/2019 | TEODORO DIAZ RODRIGUEZ |
| Issued | 1/27/2020 | LADBS |
| CofO in Progress | 9/22/2021 | ENRIQUE MIRELES |
| Permit Finaled | 9/28/2021 | RONALD MYRICK |
| CofO Issued | 9/28/2021 | RONALD MYRICK |
| Permit Finaled | 9/28/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Green Code | Cleared | 2/11/2019 | TEODORO DIAZ RODRIGUEZ |
| Low Impact Development | Cleared | 4/8/2019 | ORVAL HERNANDEZ-MARCI |
| Eng Process Fee Ord 176,300 | Cleared | 6/19/2019 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 6/19/2019 | JEANETTE VONG |
| Miscellaneous | Cleared | 7/18/2019 | KATHLEEN HUGHEY |
| Permit | Cleared | 7/31/2019 | TAO YANG |
| Address approval | Cleared | 8/1/2019 | STEVEN JIN |
| Highway dedication | Cleared | 8/1/2019 | CHRISTOPHER LAW |
| Sewer availability | Cleared | 8/1/2019 | STEVEN JIN |
| Trees in Parkway | Cleared | 8/6/2019 | JOHN KIM |
| Hydrant and Access approval | Cleared | 8/27/2019 | GEORGE SUCHAND |
| Tract Map conditions | Cleared | 8/27/2019 | ANNA VAN |
| Specific Plan | Cleared | 9/4/2019 | VALERIA CEJA |
| Construction near power lines | Cleared | 12/8/2019 | RIDWAN HARDY |
| Building over 3-story or 36-ft | Cleared | 12/13/2019 | CALOSHA APPROVED |
Contact Information
| Contractor | Carteng Construction Corporation; Lic. No.: 1032972-B | 820 CAYO GRANDE CT NEWBURY PARK, CA 91320 |
| Engineer | , ; Lic. No.: S5432 | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/4/2020 | Partial Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 3/7/2020 | Conditional Approval | MATT KELLERMAN |
| Piling/Pier/Caisson | 3/7/2020 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 3/9/2020 | Conditional Approval | DAVID FEILER |
| Deputy Reinf. Concrete | 3/31/2020 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/1/2020 | Partial Approval | DAVID FEILER |
| Deputy Reinf. Concrete | 4/20/2020 | Conditional Approval | CRAIG DAVIS |
| Footing/Foundation/Slab | 4/21/2020 | Approved | DAVID FEILER |
| Deputy Reinf. Concrete | 4/23/2020 | Conditional Approval | DAVID FEILER |
| ELECTRICAL-Rough | 5/20/2020 | Partial Approval | DAVID FEILER |
| Underground Mechanical | 5/20/2020 | Partial Approval | DAVID FEILER |
| Deputy Wood Construction | 5/22/2020 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2020 | Partial Approval | DAVID FEILER |
| Interior/Exterior Lathing | 5/26/2020 | Partial Approval | DAVID FEILER |
| Special/Order Compliance | 5/29/2020 | Corrections Issued | DAVID FEILER |
| Special/Order Compliance | 6/4/2020 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2020 | Partial Approval | DAVID FEILER |
| Deputy Wood Construction | 6/16/2020 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2020 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 6/19/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Green Building Rough | 6/19/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Deputy Wood Construction | 7/1/2020 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Special/Order Compliance | 7/1/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 7/13/2020 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2020 | Partial Approval | JUAN VALENZUELA |
| Drywall Nailing | 7/22/2020 | Partial Approval | CRAIG DAVIS |
| Green Building Rough | 7/22/2020 | Not Ready for Inspection | CRAIG DAVIS |
| Deputy Wood Construction | 8/5/2020 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2020 | Partial Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 8/12/2020 | Partial Approval | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2020 | Partial Approval | CRAIG DAVIS |
| Drywall Nailing | 8/14/2020 | Partial Approval | CRAIG DAVIS |
| Green Building Rough | 8/14/2020 | Not Ready for Inspection | CRAIG DAVIS |
| Deputy Wood Construction | 9/2/2020 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2020 | Corrections Issued | JOHNNY MIRANDA |
| Deputy Wood Construction | 9/10/2020 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2020 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 9/15/2020 | Not Ready for Inspection | CRAIG DAVIS |
| Drywall Nailing | 9/15/2020 | Partial Approval | CRAIG DAVIS |
| Final | 9/15/2020 | Not Ready for Inspection | CRAIG DAVIS |
| Green Building Final | 9/15/2020 | Not Ready for Inspection | CRAIG DAVIS |
| Green Building Rough | 9/15/2020 | Not Ready for Inspection | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 9/15/2020 | SGSOV Not Ready | CRAIG DAVIS |
| Service/Power Release | 9/15/2020 | Not Ready for Inspection | CRAIG DAVIS |
| Smoke Detectors | 9/15/2020 | Not Ready for Inspection | CRAIG DAVIS |
| Verify Sprinkler Sign Off | 9/15/2020 | Not Ready for Inspection | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2020 | Partial Inspection | JUAN VALENZUELA |
| Deputy Wood Construction | 9/29/2020 | Approved | PIERRE VEGA |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2020 | Partial Approval | PIERRE VEGA |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2020 | Partial Approval | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Insulation | 11/23/2020 | Partial Approval | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/7/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 12/14/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/15/2020 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Wood Construction | 12/17/2020 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/22/2020 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 12/22/2020 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 12/22/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/23/2020 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 1/11/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/15/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/26/2021 | Approved | ENRIQUE MIRELES |
| Sewer | 4/26/2021 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 4/26/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 5/25/2021 | Approved | ENRIQUE MIRELES |
| Gas Test | 7/20/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 7/20/2021 | Approved | ENRIQUE MIRELES |
| Final | 7/23/2021 | Partial Inspection | ENRIQUE MIRELES |
| Green Building Final | 7/23/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 7/23/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 7/23/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Smoke Detectors | 7/23/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 8/4/2021 | Approved | ENRIQUE MIRELES |
| Final | 9/16/2021 | Corrections Issued | ENRIQUE MIRELES |
| Service/Power Release | 9/16/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 9/22/2021 | OK to Issue CofO | ENRIQUE MIRELES |
| Service/Power Release | 9/22/2021 | Approved | ENRIQUE MIRELES |