4515 N EAGLE ROCK BLVD LOT #31 90041

Certificate Information: 4515 N EAGLE ROCK BLVD LOT #31 90041

Application / Permit
18010-10000-04380
Plan Check / Job No.
B18LA19106
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3-STORY SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT) [Small lot subdivision pursuant to Tentative Tract No. VTTM-74078-SL. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded]
Permit Issued
Issued on 4/9/2019
Issuing Office
Metro
Current Status
CofO Issued on 8/21/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/19/2018 APPLICANT
Disabled Access Plans Picked Up 10/1/2018 APPLICANT
Assigned to Plan Check Engineer 10/5/2018 NILOOFAR MEHRAIN
Green Plans Picked Up 10/10/2018 APPLICANT
Corrections Issued 10/25/2018 NILOOFAR MEHRAIN
Quality Review Completed 10/30/2018 CHON CHIO KUO
Applicant returned to address corrections 2/15/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 2/21/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 3/6/2019 NILOOFAR MEHRAIN
Plan Check Approved 4/3/2019 NILOOFAR MEHRAIN
Issued 4/9/2019 LADBS
CofO in Progress 8/21/2020 SCOTT FINNILA
Permit Finaled 8/21/2020 DEROLD HAUFF
CofO Issued 8/21/2020 DEROLD HAUFF
Permit Finaled 8/21/2020 DEROLD HAUFF

Permit Application Clearance Information

GPI Written Notices Cleared 10/25/2018 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 10/25/2018 NILOOFAR MEHRAIN
Driveway location Cleared 2/21/2019 EDUARDO HERMOSO
Eng Process Fee Ord 176,300 Cleared 2/21/2019 CELINA MORENO
Hydrant and Access approval Cleared 2/21/2019 GEORGE SUCHAND
Green Code Cleared 2/22/2019 COLIN LOREDO
DAS Clearance Cleared 3/1/2019 COLIN LOREDO
Permit Cleared 3/8/2019 CELINA MORENO
Sewer availability Cleared 3/8/2019 CELINA MORENO
Highway dedication Cleared 3/14/2019 KARAN PATEL
Miscellaneous Cleared 3/14/2019 KARAN PATEL
Low Impact Development Cleared 3/18/2019 RYAN HUDSON
Building over 3-story or 36-ft Cleared 3/19/2019 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 3/19/2019 CALOSHA APPROVED
Address approval Cleared 3/22/2019 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 3/22/2019 ADRIAN SANCHEZ
"Q" conditions Cleared 4/5/2019 LATANYA ROUX
Miscellaneous Cleared 4/5/2019 LATANYA ROUX
Opn space landscape/Water mgmt Cleared 4/5/2019 LATANYA ROUX
Prkng lot landscape/Water mgmt Cleared 4/5/2019 LATANYA ROUX
Tract Map conditions Cleared 4/5/2019 LATANYA ROUX
ZA Case Cleared 4/5/2019 LATANYA ROUX
ZA Case Cleared 4/5/2019 LATANYA ROUX
ZA Case Cleared 4/5/2019 LATANYA ROUX

Contact Information

Architect Texter, Christopher S; Lic. No.: C25901 2 BUELLTON      IRVINE, CA 92602
Contractor Comstock Crosser & Associates Development Company Inc; Lic. No.: 717986-B 2301 ROSECRANS AVENUE   STE. 1150    EL SEGUNDO, CA 90245
Engineer Kim,, Hyun Jin; Lic. No.: C77214 6412 STANFORD AVENUE      GARDEN GROVE, CA 92845
Engineer Morris,, Kyle B.; Lic. No.: C72911 1401 DOVE ST   #520    NEWPORT BEACH, CA 92660
Geologist Lamont,, Edward H.; Lic. No.: EG1892 31971 VIA PAVO REAL      COTO DE CAZA, CA 92679

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/14/2019 Partial Approval SCOTT FINNILA
Underground Mechanical 5/28/2019 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 6/13/2019 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 6/18/2019 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 6/24/2019 Approved SCOTT FINNILA
Underground Mechanical 7/17/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/26/2019 Partial Approval SCOTT FINNILA
Drywall Nailing 8/29/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/11/2019 Not Ready for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/13/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/23/2019 Conditional Approval MICHAEL FAUNCE
Drywall Nailing 9/26/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/7/2019 Partial Approval SCOTT FINNILA
Deputy Wood Construction 10/10/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/10/2019 Partial Approval SCOTT FINNILA
Drywall Nailing 10/11/2019 Not Ready for Inspection SCOTT FINNILA
Drywall Nailing 10/16/2019 Not Ready for Inspection SCOTT FINNILA
Drywall Nailing 10/17/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/24/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/29/2019 Partial Approval SCOTT FINNILA
Drywall Nailing 10/30/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/20/2019 Partial Approval SCOTT FINNILA
Insulation 1/7/2020 Partial Approval SCOTT FINNILA
Rough-Elec/Plmb/HVAC 1/7/2020 Partial Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/17/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 2/5/2020 Conditional Approval MICHAEL FAUNCE
Interior/Exterior Lathing 2/28/2020 Conditional Approval SCOTT FINNILA
ELECTRICAL-Rough 3/3/2020 Conditional Approval SCOTT FINNILA
HVAC-Rough 3/3/2020 Conditional Approval SCOTT FINNILA
PLUMBING-Rough 3/3/2020 Conditional Approval SCOTT FINNILA
Wood Frame 3/3/2020 Approved SCOTT FINNILA
Insulation 3/11/2020 Partial Approval SCOTT FINNILA
Insulation 3/12/2020 Approved SCOTT FINNILA
Shower Pan 3/19/2020 Approved SCOTT FINNILA
Drywall Nailing 3/20/2020 Corrections Issued SCOTT FINNILA
Drywall Nailing 3/27/2020 Approved SCOTT FINNILA
Interior/Exterior Lathing 4/9/2020 Approved SCOTT FINNILA
Underground Mechanical 5/28/2020 Partial Approval SCOTT FINNILA
ELECTRICAL-Final 5/29/2020 Not Ready for Inspection SCOTT FINNILA
Underground Mechanical 6/12/2020 Partial Approval SCOTT FINNILA
Gas Test 6/30/2020 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 7/29/2020 SGSOV Approved SCOTT FINNILA
Service/Power Release 8/11/2020 Approved SCOTT FINNILA
BUILDING-Rough-Frame 8/14/2020 Approved SCOTT FINNILA
Final 8/14/2020 Partial Approval SCOTT FINNILA
Green Building Final 8/14/2020 Approved SCOTT FINNILA
Green Building Rough 8/14/2020 Approved SCOTT FINNILA
Smoke Detectors 8/14/2020 Approved SCOTT FINNILA
Verify Sprinkler Sign Off 8/14/2020 Approved SCOTT FINNILA
ELECTRICAL-Final 8/21/2020 Approved SCOTT FINNILA
Final 8/21/2020 OK to Issue CofO SCOTT FINNILA
HVAC-Final 8/21/2020 Approved SCOTT FINNILA
PLUMBING-Final 8/21/2020 Approved SCOTT FINNILA