3451 S MOTOR AVE #1-30 90034

Certificate Information: 3451 S MOTOR AVE #1-30 90034

Application / Permit
18010-10000-04349
Plan Check / Job No.
B18LA19105
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 30 UNIT TOC ___ X ___ (6 STORY) APARTMENT BUILDING WITH ONE LEVEL OF SUBTERRANEAN PARKING AND ROOFTOP DECK. TWO LEVELS OF TYPE 1A CONSTRUCTION UNDER 5 LEVELS OF TYPE IIA CONSTRUCTION. NFPA 13 SPRINKLERS THROUGHOUT
Permit Issued
No
Current Status
Verifications in Progress on 4/23/2019

Permit Application Status History

Submitted 9/7/2018 APPLICANT
Disabled Access Plans Picked Up 10/10/2018 APPLICANT
Assigned to Plan Check Engineer 10/11/2018 MICHAEL PEREZ
Corrections Issued 10/25/2018 MICHAEL PEREZ
Reviewed by Supervisor 10/29/2018 SIAVOSH POURSABAHIAN
Building Plans Picked Up 10/31/2018 APPLICANT
Green Plans Picked Up 2/25/2019 APPLICANT
Applicant returned to address corrections 4/23/2019 MICHAEL PEREZ

Permit Application Clearance Information

Building over 3-story or 36-ft Not Cleared 10/18/2018 MICHAEL PEREZ
Density Bonus 12.22.A.31 Not Cleared 10/18/2018 MICHAEL PEREZ
Excavation more than 5-ft deep Not Cleared 10/18/2018 MICHAEL PEREZ
GPI Written Notices Not Cleared 10/18/2018 MICHAEL PEREZ
Grading Pre-Inspection Not Cleared 10/18/2018 MICHAEL PEREZ
Low Impact Development Not Cleared 10/18/2018 MICHAEL PEREZ
Roof/Waste drainage to street Not Cleared 10/18/2018 MICHAEL PEREZ
Trees in Parkway Not Cleared 10/18/2018 MICHAEL PEREZ
Work Adjacent to Public Way Not Cleared 10/18/2018 MICHAEL PEREZ
Address approval Cleared 2/26/2019 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 2/26/2019 ELENA LOPEZ
Permit Cleared 2/26/2019 ELENA LOPEZ
Encroachment in public way Cleared 4/23/2019 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 5/9/2019 ROBERT DUFF
Miscellaneous Not Cleared 5/15/2019 MICHAEL PEREZ
CPC Cleared 7/18/2019 RICHARD REASER
CPC Cleared 7/18/2019 RICHARD REASER
Prkng lot landscape/Water mgmt Cleared 7/18/2019 DIANA JIMENEZ
Green Code Cleared 8/21/2019 MICHAEL PEREZ
Miscellaneous Not Cleared 10/30/2019 MICHAEL PEREZ
Bicycle Parking Cleared 11/5/2019 ELAINE LEI
Highway dedication Cleared 11/7/2019 OSCAR GUTIERREZ
Sewer availability Cleared 11/21/2019 THOMAS LANG
DAS Clearance Cleared 1/13/2020 SHINE LIN
Opn space landscape/Water mgmt Not Cleared 3/3/2020 ANNA VIDAL