3620 N LATROBE ST 90031
Certificate Information: 3620 N LATROBE ST 90031
- Application / Permit
- 18010-10000-04346
- Plan Check / Job No.
- B18LA19079
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY SINGLE FAMILY DWELLING WITH ATTACHED BASEMENT 2 CAR GARAGE. FULLY SPRINKLERED NFPA-13D
- Permit Issued
- Issued on 3/4/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/6/2018 | APPLICANT |
| Green Plans Picked Up | 10/4/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/11/2018 | JOSE MENDOZA |
| Corrections Issued | 10/22/2018 | JOSE MENDOZA |
| Quality Review Completed | 10/23/2018 | STEVEN KIM |
| Building Plans Picked Up | 11/7/2018 | APPLICANT |
| Applicant returned to address corrections | 1/10/2019 | JOSE MENDOZA |
| Applicant returned to address corrections | 5/24/2019 | JOSE MENDOZA |
| Applicant returned to address corrections | 7/16/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 7/25/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 9/11/2019 | CHON CHIO KUO |
| Applicant returned to address corrections | 1/16/2020 | CHON CHIO KUO |
| Plan Check Approved | 3/3/2020 | CHON CHIO KUO |
| Issued | 3/4/2020 | LADBS |
| CofO in Progress | 12/22/2022 | AMY COLIN |
| Permit Finaled | 12/28/2022 | DEROLD HAUFF |
| CofO Issued | 12/28/2022 | DEROLD HAUFF |
| Permit Finaled | 12/28/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/30/2018 | JEANETTE VONG |
| BHO/Hillside ordinance | Cleared | 11/30/2018 | JEANETTE VONG |
| BHO/Hillside ordinance | Cleared | 11/30/2018 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/30/2018 | JEANETTE VONG |
| Permit | Cleared | 11/30/2018 | JEANETTE VONG |
| Encroachment in public way | Cleared | 12/4/2018 | KARAN PATEL |
| Hydrant and Access approval | Cleared | 12/4/2018 | GEORGE SUCHAND |
| Work Adjacent to Public Way | Cleared | 12/4/2018 | CHIU TAM |
| CPC | Cleared | 1/10/2019 | DIANA JIMENEZ |
| Disturb/Remove Protected Trees | Cleared | 1/25/2019 | ADRIAN SANCHEZ |
| Trees in Parkway | Cleared | 1/25/2019 | ADRIAN SANCHEZ |
| "D" conditions | Cleared | 2/11/2019 | SANTOS SANCHEZ |
| "Q" conditions | Cleared | 2/11/2019 | SANTOS SANCHEZ |
| ZI | Cleared | 2/11/2019 | SANTOS SANCHEZ |
| Private street | Cleared | 3/22/2019 | JOSE ROMERO-NAVARRO |
| Building over 3-story or 36-ft | Cleared | 5/24/2019 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 5/24/2019 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 5/24/2019 | JOSE MENDOZA |
| BHO/Hillside ordinance | Cleared | 9/10/2019 | THOMAS LANG |
| Green Code | Cleared | 9/10/2019 | DONALD CRICHLOW |
| Sewer availability | Cleared | 9/10/2019 | THOMAS LANG |
| GPI Written Notices | Cleared | 9/11/2019 | JOSE MENDOZA |
| Low Impact Development | Cleared | 1/9/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 1/9/2020 | JEANIE LAM |
Contact Information
| Architect | Bojana, Banyasz; Lic. No.: C32926 | 600 MOULTON AVE #405 LOS ANGELES,, CA 90031 |
| Contractor | Owner-Builder | , |
| Engineer | Elizabeth, Mahlow; Lic. No.: C80463 | , |
| Engineer | Jonathan, Edward Mahn; Lic. No.: C60293 | , |
| Geologist | Mark, J Triebold; Lic. No.: EG1796 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/26/2020 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 5/14/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Special/Order Compliance | 5/14/2020 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/20/2020 | Partial Approval | ENRIQUE MIRELES |
| Special/Order Compliance | 5/20/2020 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 6/2/2020 | Approved | ENRIQUE MIRELES |
| Masonry Wall/Backfill | 6/2/2020 | Partial Approval | ENRIQUE MIRELES |
| Deputy Reinf. Masonry | 6/5/2020 | Approved | ENRIQUE MIRELES |
| Piling/Pier/Caisson | 6/10/2020 | Partial Approval | OSVALDO PARAMO |
| Piling/Pier/Caisson | 6/11/2020 | Partial Approval | ENRIQUE MIRELES |
| Deputy Reinf. Concrete | 6/12/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Piling/Pier/Caisson | 6/15/2020 | Partial Approval | ENRIQUE MIRELES |
| Deputy Reinf. Concrete | 6/16/2020 | Approved | ELMER BLAND |
| PLUMBING-Rough | 7/9/2020 | Partial Approval | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 7/27/2020 | Approved | ENRIQUE MIRELES |
| Deputy Reinf. Concrete | 7/29/2020 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 8/18/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Reinforced Concrete Frame | 8/18/2020 | Partial Approval | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 8/18/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Deputy Reinf. Concrete | 8/19/2020 | Conditional Approval | DAVID MATSON |
| Deputy Drilled-In Anchors | 8/27/2020 | No Access for Inspection | ELMER BLAND |
| Excavation/Setback/Form/Re-Bar | 9/1/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 9/16/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Reinf. Masonry | 9/24/2020 | No Access for Inspection | ELMER BLAND |
| Excavation/Setback/Form/Re-Bar | 9/24/2020 | Corrections Issued | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 9/28/2020 | Conditional Approval | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 9/30/2020 | Not Ready for Inspection | COREY HUPP |
| Masonry Wall/Backfill | 10/16/2020 | Partial Approval | COREY HUPP |
| Deputy Reinf. Masonry | 10/21/2020 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 10/29/2020 | Conditional Approval | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 11/4/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Masonry Wall/Backfill | 11/12/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Reinforced Masonry Frame | 11/12/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 11/12/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Deputy Reinf. Masonry | 11/13/2020 | No Access for Inspection | ELMER BLAND |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2020 | Partial Approval | OSVALDO PARAMO |
| Masonry Wall/Backfill | 11/16/2020 | Partial Approval | OSVALDO PARAMO |
| Deputy Wood Construction | 11/17/2020 | No Access for Inspection | ELMER BLAND |
| Deputy Reinf. Masonry | 11/18/2020 | No Access for Inspection | ELMER BLAND |
| Deputy Wood Construction | 12/21/2020 | No Access for Inspection | ELMER BLAND |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2020 | Partial Approval | COREY HUPP |
| Special/Order Compliance | 7/15/2021 | Approved | ELMER BLAND |
| ELECTRICAL-Rough | 7/21/2021 | Not Ready for Inspection | COREY HUPP |
| HVAC-Rough | 7/21/2021 | Not Ready for Inspection | COREY HUPP |
| PLUMBING-Rough | 7/21/2021 | Partial Approval | COREY HUPP |
| ELECTRICAL-Rough | 8/6/2021 | Approved | RUBEN SALAS |
| BUILDING-Rough-Frame | 9/8/2021 | Corrections Issued | RUBEN SALAS |
| Green Building Rough | 9/8/2021 | Not Ready for Inspection | RUBEN SALAS |
| HVAC-Rough | 9/8/2021 | Corrections Issued | RUBEN SALAS |
| Verify Sprinkler Sign Off | 9/8/2021 | Not Ready for Inspection | RUBEN SALAS |
| BUILDING-Rough-Frame | 9/30/2021 | Partial Inspection | COREY HUPP |
| Green Building Rough | 9/30/2021 | Approved | COREY HUPP |
| Verify Sprinkler Sign Off | 9/30/2021 | Not Ready for Inspection | COREY HUPP |
| HVAC-Rough | 10/8/2021 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Rough | 10/15/2021 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 10/18/2021 | Approved | COREY HUPP |
| Verify Sprinkler Sign Off | 10/18/2021 | Approved | COREY HUPP |
| Drywall Nailing | 11/16/2021 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 11/16/2021 | Partial Approval | COREY HUPP |
| Interior/Exterior Lathing | 12/27/2021 | Approved | RUBEN SALAS |
| Sewer | 5/17/2022 | Approved | RUBEN SALAS |
| ELECTRICAL-Final | 6/23/2022 | Approved | AMY COLIN |
| Gas Test | 6/28/2022 | Not Ready for Inspection | AMY COLIN |
| HVAC-Final | 6/28/2022 | Approved | AMY COLIN |
| PLUMBING-Final | 6/28/2022 | Approved | AMY COLIN |
| Gas Test | 8/15/2022 | Approved | AMY COLIN |
| Final | 8/31/2022 | Corrections Issued | AMY COLIN |
| Green Building Final | 8/31/2022 | Corrections Issued | AMY COLIN |
| Reinforced Concrete Frame | 8/31/2022 | Approved | AMY COLIN |
| Reinforced Masonry Frame | 8/31/2022 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 8/31/2022 | SGSOV Approved | AMY COLIN |
| Service/Power Release | 8/31/2022 | Not Ready for Inspection | AMY COLIN |
| Smoke Detectors | 8/31/2022 | Approved | AMY COLIN |
| Structural Steel Frame | 8/31/2022 | Approved | AMY COLIN |
| Final | 10/7/2022 | Partial Inspection | AMY COLIN |
| Green Building Final | 10/7/2022 | Approved | AMY COLIN |
| Service/Power Release | 10/7/2022 | Approved | AMY COLIN |
| Final | 12/19/2022 | Conditional Approval | ENRIQUE MIRELES |
| Final | 12/22/2022 | OK to Issue CofO | AMY COLIN |