3620 N LATROBE ST 90031

Certificate Information: 3620 N LATROBE ST 90031

Application / Permit
18010-10000-04346
Plan Check / Job No.
B18LA19079
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY SINGLE FAMILY DWELLING WITH ATTACHED BASEMENT 2 CAR GARAGE. FULLY SPRINKLERED NFPA-13D
Permit Issued
Issued on 3/4/2020
Issuing Office
Metro
Current Status
CofO Issued on 12/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2018 APPLICANT
Green Plans Picked Up 10/4/2018 APPLICANT
Assigned to Plan Check Engineer 10/11/2018 JOSE MENDOZA
Corrections Issued 10/22/2018 JOSE MENDOZA
Quality Review Completed 10/23/2018 STEVEN KIM
Building Plans Picked Up 11/7/2018 APPLICANT
Applicant returned to address corrections 1/10/2019 JOSE MENDOZA
Applicant returned to address corrections 5/24/2019 JOSE MENDOZA
Applicant returned to address corrections 7/16/2019 CHON CHIO KUO
Applicant returned to address corrections 7/25/2019 CHON CHIO KUO
Applicant returned to address corrections 9/11/2019 CHON CHIO KUO
Applicant returned to address corrections 1/16/2020 CHON CHIO KUO
Plan Check Approved 3/3/2020 CHON CHIO KUO
Issued 3/4/2020 LADBS
CofO in Progress 12/22/2022 AMY COLIN
Permit Finaled 12/28/2022 DEROLD HAUFF
CofO Issued 12/28/2022 DEROLD HAUFF
Permit Finaled 12/28/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/30/2018 JEANETTE VONG
BHO/Hillside ordinance Cleared 11/30/2018 JEANETTE VONG
BHO/Hillside ordinance Cleared 11/30/2018 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 11/30/2018 JEANETTE VONG
Permit Cleared 11/30/2018 JEANETTE VONG
Encroachment in public way Cleared 12/4/2018 KARAN PATEL
Hydrant and Access approval Cleared 12/4/2018 GEORGE SUCHAND
Work Adjacent to Public Way Cleared 12/4/2018 CHIU TAM
CPC Cleared 1/10/2019 DIANA JIMENEZ
Disturb/Remove Protected Trees Cleared 1/25/2019 ADRIAN SANCHEZ
Trees in Parkway Cleared 1/25/2019 ADRIAN SANCHEZ
"D" conditions Cleared 2/11/2019 SANTOS SANCHEZ
"Q" conditions Cleared 2/11/2019 SANTOS SANCHEZ
ZI Cleared 2/11/2019 SANTOS SANCHEZ
Private street Cleared 3/22/2019 JOSE ROMERO-NAVARRO
Building over 3-story or 36-ft Cleared 5/24/2019 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 5/24/2019 CALOSHA APPROVED
Grading Pre-Inspection Cleared 5/24/2019 JOSE MENDOZA
BHO/Hillside ordinance Cleared 9/10/2019 THOMAS LANG
Green Code Cleared 9/10/2019 DONALD CRICHLOW
Sewer availability Cleared 9/10/2019 THOMAS LANG
GPI Written Notices Cleared 9/11/2019 JOSE MENDOZA
Low Impact Development Cleared 1/9/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 1/9/2020 JEANIE LAM

Contact Information

Architect Bojana, Banyasz; Lic. No.: C32926 600 MOULTON AVE   #405    LOS ANGELES,, CA 90031
Contractor Owner-Builder       ,
Engineer Elizabeth, Mahlow; Lic. No.: C80463       ,
Engineer Jonathan, Edward Mahn; Lic. No.: C60293       ,
Geologist Mark, J Triebold; Lic. No.: EG1796       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/26/2020 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 5/14/2020 Not Ready for Inspection OSVALDO PARAMO
Special/Order Compliance 5/14/2020 Approved OSVALDO PARAMO
Footing/Foundation/Slab 5/20/2020 Partial Approval ENRIQUE MIRELES
Special/Order Compliance 5/20/2020 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 6/2/2020 Approved ENRIQUE MIRELES
Masonry Wall/Backfill 6/2/2020 Partial Approval ENRIQUE MIRELES
Deputy Reinf. Masonry 6/5/2020 Approved ENRIQUE MIRELES
Piling/Pier/Caisson 6/10/2020 Partial Approval OSVALDO PARAMO
Piling/Pier/Caisson 6/11/2020 Partial Approval ENRIQUE MIRELES
Deputy Reinf. Concrete 6/12/2020 Partial Approval CHRISTOPHER DELLEFIELD
Piling/Pier/Caisson 6/15/2020 Partial Approval ENRIQUE MIRELES
Deputy Reinf. Concrete 6/16/2020 Approved ELMER BLAND
PLUMBING-Rough 7/9/2020 Partial Approval ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 7/27/2020 Approved ENRIQUE MIRELES
Deputy Reinf. Concrete 7/29/2020 Approved ENRIQUE MIRELES
Green Building Rough 8/18/2020 Not Ready for Inspection ENRIQUE MIRELES
Reinforced Concrete Frame 8/18/2020 Partial Approval ENRIQUE MIRELES
Verify Sprinkler Sign Off 8/18/2020 Not Ready for Inspection ENRIQUE MIRELES
Deputy Reinf. Concrete 8/19/2020 Conditional Approval DAVID MATSON
Deputy Drilled-In Anchors 8/27/2020 No Access for Inspection ELMER BLAND
Excavation/Setback/Form/Re-Bar 9/1/2020 Approved ENRIQUE MIRELES
PLUMBING-Rough 9/16/2020 Partial Approval HAMIK HARTOUNIAN
Deputy Reinf. Masonry 9/24/2020 No Access for Inspection ELMER BLAND
Excavation/Setback/Form/Re-Bar 9/24/2020 Corrections Issued COREY HUPP
Excavation/Setback/Form/Re-Bar 9/28/2020 Conditional Approval COREY HUPP
Excavation/Setback/Form/Re-Bar 9/30/2020 Not Ready for Inspection COREY HUPP
Masonry Wall/Backfill 10/16/2020 Partial Approval COREY HUPP
Deputy Reinf. Masonry 10/21/2020 Conditional Approval THOMAS LOGRASSO
Deputy Drilled-In Anchors 10/29/2020 Conditional Approval COREY HUPP
Excavation/Setback/Form/Re-Bar 11/4/2020 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 11/12/2020 Corrections Issued HAMIK HARTOUNIAN
Masonry Wall/Backfill 11/12/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Reinforced Masonry Frame 11/12/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 11/12/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Deputy Reinf. Masonry 11/13/2020 No Access for Inspection ELMER BLAND
Floor/Roof Diaphrgm/Shear Wall 11/16/2020 Partial Approval OSVALDO PARAMO
Masonry Wall/Backfill 11/16/2020 Partial Approval OSVALDO PARAMO
Deputy Wood Construction 11/17/2020 No Access for Inspection ELMER BLAND
Deputy Reinf. Masonry 11/18/2020 No Access for Inspection ELMER BLAND
Deputy Wood Construction 12/21/2020 No Access for Inspection ELMER BLAND
Floor/Roof Diaphrgm/Shear Wall 12/21/2020 Partial Approval COREY HUPP
Special/Order Compliance 7/15/2021 Approved ELMER BLAND
ELECTRICAL-Rough 7/21/2021 Not Ready for Inspection COREY HUPP
HVAC-Rough 7/21/2021 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 7/21/2021 Partial Approval COREY HUPP
ELECTRICAL-Rough 8/6/2021 Approved RUBEN SALAS
BUILDING-Rough-Frame 9/8/2021 Corrections Issued RUBEN SALAS
Green Building Rough 9/8/2021 Not Ready for Inspection RUBEN SALAS
HVAC-Rough 9/8/2021 Corrections Issued RUBEN SALAS
Verify Sprinkler Sign Off 9/8/2021 Not Ready for Inspection RUBEN SALAS
BUILDING-Rough-Frame 9/30/2021 Partial Inspection COREY HUPP
Green Building Rough 9/30/2021 Approved COREY HUPP
Verify Sprinkler Sign Off 9/30/2021 Not Ready for Inspection COREY HUPP
HVAC-Rough 10/8/2021 Corrections Issued OSVALDO PARAMO
HVAC-Rough 10/15/2021 Approved COREY HUPP
BUILDING-Rough-Frame 10/18/2021 Approved COREY HUPP
Verify Sprinkler Sign Off 10/18/2021 Approved COREY HUPP
Drywall Nailing 11/16/2021 Approved COREY HUPP
Interior/Exterior Lathing 11/16/2021 Partial Approval COREY HUPP
Interior/Exterior Lathing 12/27/2021 Approved RUBEN SALAS
Sewer 5/17/2022 Approved RUBEN SALAS
ELECTRICAL-Final 6/23/2022 Approved AMY COLIN
Gas Test 6/28/2022 Not Ready for Inspection AMY COLIN
HVAC-Final 6/28/2022 Approved AMY COLIN
PLUMBING-Final 6/28/2022 Approved AMY COLIN
Gas Test 8/15/2022 Approved AMY COLIN
Final 8/31/2022 Corrections Issued AMY COLIN
Green Building Final 8/31/2022 Corrections Issued AMY COLIN
Reinforced Concrete Frame 8/31/2022 Approved AMY COLIN
Reinforced Masonry Frame 8/31/2022 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 8/31/2022 SGSOV Approved AMY COLIN
Service/Power Release 8/31/2022 Not Ready for Inspection AMY COLIN
Smoke Detectors 8/31/2022 Approved AMY COLIN
Structural Steel Frame 8/31/2022 Approved AMY COLIN
Final 10/7/2022 Partial Inspection AMY COLIN
Green Building Final 10/7/2022 Approved AMY COLIN
Service/Power Release 10/7/2022 Approved AMY COLIN
Final 12/19/2022 Conditional Approval ENRIQUE MIRELES
Final 12/22/2022 OK to Issue CofO AMY COLIN