937 E 25TH ST 1-17 90011
Certificate Information: 937 E 25TH ST 1-17 90011
- Application / Permit
- 18010-10000-04286
- Plan Check / Job No.
- B18LA18845
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- (N) 3-STORY 17-UNIT 100% AFFORDABLE HOUSING APARTMENT BUILDING W/ MANAGER'S OFFICE. NO VEHICLE PARKING.
- Permit Issued
- Issued on 9/1/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/4/2018 | APPLICANT |
| Green Plans Picked Up | 10/2/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2018 | HERNAN ARREOLA |
| Disabled Access Plans Picked Up | 10/10/2018 | APPLICANT |
| Corrections Issued | 10/24/2018 | HERNAN ARREOLA |
| Quality Review Completed | 10/24/2018 | BILL STUTSMAN |
| Building Plans Picked Up | 10/26/2018 | APPLICANT |
| Applicant returned to address corrections | 4/30/2019 | HERNAN ARREOLA |
| Applicant returned to address corrections | 6/27/2019 | HERNAN ARREOLA |
| Applicant returned to address corrections | 3/3/2020 | HERNAN ARREOLA |
| Applicant returned to address corrections | 1/15/2021 | HERNAN ARREOLA |
| Plan Check Approved | 8/30/2021 | HERNAN ARREOLA |
| Issued | 9/1/2021 | APPLICANT |
| TCO Issued (Expire Date: 01-08-2024) | 7/12/2023 | ERNESTO CORRAL |
| CofO in Progress | 8/7/2023 | JAMES POWERS |
| CofO Issued | 8/7/2023 | ERNESTO CORRAL |
| Permit Finaled | 8/7/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 11/7/2018 | NAZILA NOORIFAR |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2018 | NAZILA NOORIFAR |
| Highway dedication | Cleared | 11/7/2018 | NAZILA NOORIFAR |
| Hydrant and Access approval | Cleared | 5/30/2019 | GILBERT URREA |
| Green Code | Cleared | 6/5/2019 | KHEDER ALRAZAA |
| Low Impact Development | Cleared | 6/5/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/5/2019 | ELENA LOPEZ |
| DAS Clearance | Cleared | 6/10/2019 | ELIZABETH TOMS |
| Opn space landscape/Water mgmt | Cleared | 6/10/2019 | ANNA VAN |
| Fire Marshall Fire Life Safety | Cleared | 6/11/2019 | DOMINIQUE MEDINA |
| Sewer availability | Cleared | 6/11/2019 | ADRIAN SANCHEZ |
| Density Bonus 12.22.A.31 | Cleared | 5/10/2021 | KENNETH LE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Bozorgnia, Behrouz; Lic. No.: C79581 | 1557 WESTWOOD BLVD 145 LOS ANGELES, CA 90024 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/29/2021 | Not Ready for Inspection | JAMES POWERS |
| Pre-Inspection | 9/29/2021 | Partial Inspection | SORIN CIRSTOIU |
| Pre-Inspection | 10/13/2021 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 10/18/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Footing/Foundation/Slab | 11/8/2021 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Reinf. Concrete | 11/15/2021 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 11/24/2021 | Partial Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 11/29/2021 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 12/20/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Green Building Rough | 12/20/2021 | Partial Inspection | RUSSELL BONVOULOIR |
| Verify Sprinkler Sign Off | 12/20/2021 | Partial Inspection | RUSSELL BONVOULOIR |
| Wood Frame | 12/20/2021 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Wood Construction | 1/11/2022 | Approved | SORIN CIRSTOIU |
| Green Building Rough | 1/11/2022 | Partial Inspection | SORIN CIRSTOIU |
| Verify Sprinkler Sign Off | 1/11/2022 | Partial Inspection | SORIN CIRSTOIU |
| Wood Frame | 1/11/2022 | Partial Approval | SORIN CIRSTOIU |
| Deputy Wood Construction | 3/17/2022 | Conditional Approval | SORIN CIRSTOIU |
| Green Building Rough | 3/23/2022 | Partial Inspection | SORIN CIRSTOIU |
| Verify Sprinkler Sign Off | 3/23/2022 | Partial Inspection | SORIN CIRSTOIU |
| Wood Frame | 3/23/2022 | Partial Inspection | SORIN CIRSTOIU |
| Deputy Wood Construction | 4/4/2022 | Conditional Approval | SORIN CIRSTOIU |
| Wood Frame | 4/6/2022 | Corrections Issued | SORIN CIRSTOIU |
| Drywall Nailing | 5/18/2022 | Conditional Approval | DARRYL ARNOLD |
| Green Building Rough | 5/18/2022 | Conditional Approval | DARRYL ARNOLD |
| Insulation | 5/18/2022 | Conditional Approval | DARRYL ARNOLD |
| Insulation | 5/24/2022 | Partial Inspection | SORIN CIRSTOIU |
| Insulation | 6/3/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Interior/Exterior Lathing | 7/11/2022 | Approved | RUSSELL BONVOULOIR |
| Pre-Inspection | 7/18/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Insulation | 9/19/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Pre-Inspection | 9/19/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Insulation | 9/23/2022 | Approved | RAFAEL ESPINOZA |
| Drywall Nailing | 10/6/2022 | Partial Approval | GREGORY POMISH |
| Green Building Rough | 10/6/2022 | Not Ready for Inspection | GREGORY POMISH |
| T-Bar Ceiling | 10/6/2022 | Not Ready for Inspection | GREGORY POMISH |
| Drywall Nailing | 11/4/2022 | Approved | RUSSELL BONVOULOIR |
| Green Building Rough | 11/4/2022 | Approved | RUSSELL BONVOULOIR |
| Insulation | 3/16/2023 | Not Ready for Inspection | JAMES POWERS |
| Final | 5/15/2023 | Not Ready for Inspection | GREGORY POMISH |
| Footing/Foundation/Slab | 5/15/2023 | Not Ready for Inspection | GREGORY POMISH |
| Green Building Final | 5/15/2023 | Not Ready for Inspection | GREGORY POMISH |
| SGSOV-Seismic Gas S/O Valve | 5/15/2023 | SGSOV Not Ready | GREGORY POMISH |
| Smoke Detectors | 5/15/2023 | Not Ready for Inspection | GREGORY POMISH |
| Verify Sprinkler Sign Off | 5/15/2023 | Not Ready for Inspection | GREGORY POMISH |
| Wood Frame | 5/15/2023 | Not Ready for Inspection | GREGORY POMISH |
| Final | 5/16/2023 | OK for TCO | JAMES POWERS |
| Footing/Foundation/Slab | 5/16/2023 | Approved | JAMES POWERS |
| Green Building Final | 5/16/2023 | Approved | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 5/16/2023 | SGSOV Approved | JAMES POWERS |
| Smoke Detectors | 5/16/2023 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 5/16/2023 | Approved | JAMES POWERS |
| Wood Frame | 5/16/2023 | Approved | JAMES POWERS |
| Pre-Inspection | 5/31/2023 | Partial Inspection | RAFAEL ESPINOZA |
| Final | 7/3/2023 | OK for TCO | JAMES POWERS |
| Final | 8/7/2023 | OK to Issue CofO | JAMES POWERS |