10475 W OLYMPIC BLVD 90025

Certificate Information: 10475 W OLYMPIC BLVD 90025

Application / Permit
18010-10000-04274
Plan Check / Job No.
B18LA18799
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED TWO-STORY ACCESSORY DWELLING UNIT PER AB 494 & SB 229
Permit Issued
Issued on 2/13/2019
Issuing Office
Metro
Current Status
CofO Issued on 11/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/4/2018 APPLICANT
Assigned to Plan Check Engineer 10/4/2018 YAQUB MIRZA
Green Plans Picked Up 10/5/2018 APPLICANT
Corrections Issued 10/17/2018 YAQUB MIRZA
Quality Review Completed 10/18/2018 HERNAN ARREOLA
Building Plans Picked Up 10/22/2018 APPLICANT
Plan Check Approved 12/13/2018 YAQUB MIRZA
Issued 2/13/2019 LADBS
CofO in Progress 9/23/2025 DANIEL VERA
Permit Finaled 11/6/2025 RICHARD STEINBACH
CofO Issued 11/6/2025 RICHARD STEINBACH
Permit Finaled 11/6/2025 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/29/2018 PATRICK MISCHLICH
Address approval Cleared 11/6/2018 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 11/6/2018 STEVE MELGAR
Permit Cleared 11/6/2018 STEVE MELGAR
Sewer availability Cleared 11/14/2018 JEANETTE VONG
Trees in Parkway Cleared 11/15/2018 ADRIAN SANCHEZ
Green Code Cleared 11/20/2018 KHEDER ALRAZAA
Disturb/Remove Protected Trees Cleared 11/28/2018 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 11/29/2018 JOHN CONNEALLY
Low Impact Development Cleared 11/29/2018 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 11/29/2018 JEANETTE VONG
GPI Written Notices Cleared 11/30/2018 YAQUB MIRZA

Contact Information

Architect , ; Lic. No.: C36083       , CA
Contractor Owner-Builder       ,
Engineer , ; Lic. No.: C85373       , CA

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/6/2019 Corrections Issued DANNY TOLENTINO
Pre-Inspection 8/6/2019 Not Ready for Inspection DANNY TOLENTINO
Sewer 8/6/2019 Not Ready for Inspection DANNY TOLENTINO
METHANE-Rough 8/28/2019 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 8/28/2019 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Pre-Inspection 8/28/2019 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Deputy Methane Barrier 10/24/2019 No Access for Inspection MATT KELLERMAN
METHANE-Subgrade 10/25/2019 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 10/25/2019 Partial Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 11/5/2019 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 11/13/2019 Partial Inspection GERMAN RODRIGUEZ MENDOZA
METHANE-Barrier 11/13/2019 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 1/22/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
METHANE-Barrier 1/22/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 1/30/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
METHANE-Barrier 1/30/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 2/27/2020 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Barrier 2/27/2020 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Final 2/27/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
METHANE-Rough 2/27/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 6/24/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Green Building Rough 6/24/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
METHANE-Rough 6/24/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 6/24/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Wood Frame 6/24/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 6/30/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 7/16/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 2/4/2021 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 2/4/2021 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
Green Building Rough 2/4/2021 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
METHANE-Rough 2/4/2021 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 2/4/2021 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
Wood Frame 3/1/2021 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 3/15/2021 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 3/15/2021 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
Wood Frame 3/15/2021 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 5/18/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 5/18/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 10/21/2021 Partial Approval BRENDAN LOONEY
PLUMBING-Rough 10/21/2021 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 10/27/2021 Not Ready for Inspection BRENDAN LOONEY
Wood Frame 10/27/2021 Partial Approval BRENDAN LOONEY
HVAC-Rough 11/9/2021 Approved BRENDAN LOONEY
Interior/Exterior Lathing 11/17/2021 Corrections Issued BRENDAN LOONEY
Wood Frame 11/17/2021 Not Ready for Inspection BRENDAN LOONEY
Interior/Exterior Lathing 12/7/2021 Partial Approval BRENDAN LOONEY
PLUMBING-Rough 12/7/2021 Corrections Issued BRENDAN LOONEY
Wood Frame 12/9/2021 No Access for Inspection BRENDAN LOONEY
BUILDING-Rough-Frame 12/13/2021 Conditional Approval CHRISTOPHER WILSON
Green Building Rough 12/13/2021 Approved CHRISTOPHER WILSON
PLUMBING-Rough 12/13/2021 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 12/16/2021 Approved BRENDAN LOONEY
METHANE-Rough 12/16/2021 Approved BRENDAN LOONEY
Verify Sprinkler Sign Off 12/16/2021 Approved BRENDAN LOONEY
Insulation 12/30/2021 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 1/6/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 1/19/2022 No Access for Inspection BRENDAN LOONEY
Drywall Nailing 1/25/2022 Approved BRENDAN LOONEY
Pre-Inspection 7/25/2022 Partial Inspection PATRICK QUALEY
Gas Test 10/28/2022 Corrections Issued STEPHANIE SWANSON
Underground Mechanical 11/4/2022 Approved STEPHANIE SWANSON
ELECTRICAL-Final 8/7/2024 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 9/16/2024 Not Ready for Inspection STEPHANIE SWANSON
Final 9/16/2024 Corrections Issued STEPHANIE SWANSON
Green Building Final 9/16/2024 Not Ready for Inspection STEPHANIE SWANSON
HVAC-Final 9/16/2024 Not Ready for Inspection STEPHANIE SWANSON
PLUMBING-Final 9/16/2024 Not Ready for Inspection STEPHANIE SWANSON
ELECTRICAL-Final 5/1/2025 Not Ready for Inspection DANIEL VERA
Gas Test 5/1/2025 Approved DANIEL VERA
PLUMBING-Final 5/1/2025 Not Ready for Inspection DANIEL VERA
Final 6/16/2025 Corrections Issued DANIEL VERA
Green Building Final 6/16/2025 Not Ready for Inspection DANIEL VERA
SGSOV-Seismic Gas S/O Valve 6/16/2025 SGSOV Not Ready DANIEL VERA
Service/Power Release 6/16/2025 Not Ready for Inspection DANIEL VERA
Smoke Detectors 6/16/2025 Approved DANIEL VERA
ELECTRICAL-Final 7/29/2025 Approved DANIEL VERA
Green Building Final 7/29/2025 Not Ready for Inspection DANIEL VERA
HVAC-Final 7/29/2025 Corrections Issued DANIEL VERA
PLUMBING-Final 7/29/2025 Approved DANIEL VERA
SGSOV-Seismic Gas S/O Valve 7/29/2025 SGSOV Not Ready DANIEL VERA
Service/Power Release 7/29/2025 Approved DANIEL VERA
Final 9/23/2025 OK to Issue CofO DANIEL VERA
Green Building Final 9/23/2025 Approved DANIEL VERA
SGSOV-Seismic Gas S/O Valve 9/23/2025 SGSOV Approved DANIEL VERA
Service/Power Release 9/23/2025 Approved DANIEL VERA