10209 N SAMOA AVE #1-11 91042

Certificate Information: 10209 N SAMOA AVE #1-11 91042

Application / Permit
18010-10000-04255
Plan Check / Job No.
B18LA18604
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) 3-STORY TYPE III-A 11-UNIT APT BLDG OVER TYPE IIII-A BASEMENT PARKING GARAGE (NFPA-13 FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 2/14/2020
Issuing Office
Valley
Current Status
Issued on 2/14/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/30/2018 APPLICANT
Assigned to Plan Check Engineer 9/20/2018 NILOOFAR MEHRAIN
Corrections Issued 9/24/2018 NILOOFAR MEHRAIN
Quality Review Completed 9/27/2018 CHON CHIO KUO
Green Plans Picked Up 9/28/2018 APPLICANT
Building Plans Picked Up 10/1/2018 APPLICANT
Applicant returned to address corrections 11/5/2018 NILOOFAR MEHRAIN
Applicant returned to address corrections 11/14/2018 NILOOFAR MEHRAIN
Applicant returned to address corrections 12/21/2018 NILOOFAR MEHRAIN
Applicant returned to address corrections 1/10/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 3/7/2019 NILOOFAR MEHRAIN
Plan Check Approved 3/28/2019 NILOOFAR MEHRAIN
Issued 2/14/2020 LADBS

Permit Application Clearance Information

Highway dedication Cleared 10/12/2018 MARKOS PEREZ-BRAN
Miscellaneous Cleared 10/12/2018 MARKOS PEREZ-BRAN
Permit Cleared 10/12/2018 MARKOS PEREZ-BRAN
Work Adjacent to Public Way Cleared 10/16/2018 MARKOS PEREZ-BRAN
GPI Written Notices Cleared 10/23/2018 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 10/23/2018 NILOOFAR MEHRAIN
DAS Clearance Cleared 10/24/2018 WAI LAU
Eng Process Fee Ord 176,300 Cleared 10/24/2018 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 10/24/2018 JOHN DALLAS
Sewer availability Cleared 10/24/2018 MARKOS PEREZ-BRAN
Frnt yard landscape/Water mgmt Cleared 10/26/2018 BLAYNE SUTTON-WILLS
Opn space landscape/Water mgmt Cleared 10/26/2018 BLAYNE SUTTON-WILLS
Green Code Cleared 10/30/2018 KHEDER ALRAZAA
Green Code Cleared 10/30/2018 NILOOFAR MEHRAIN
Low Impact Development Cleared 10/31/2018 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/31/2018 MICHAEL CASTILLO
Specific Plan Cleared 11/20/2018 DANG NGUYEN
Specific Plan Cleared 11/20/2018 DANG NGUYEN
Fire Marshall Fire Life Safety Cleared 12/4/2018 OSCAR SALGADO JR
DAS Clearance Cleared 1/10/2019 NILOOFAR MEHRAIN
Excavation more than 5-ft deep Cleared 3/26/2019 CALOSHA APPROVED
Address approval Cleared 3/29/2019 JEANETTE VONG
Miscellaneous Cleared 3/29/2019 MOTOUMI SASAKI
Haul Route Cleared 5/28/2019 NILOOFAR MEHRAIN

Contact Information

Architect Saroian, Varoozh; Lic. No.: C13791 128 S KENWOOD STREET      GLENDALE, CA 91205
Contractor Razmik Construction Inc; Lic. No.: 544544-B 3571 E CHEVY CHASE DR      GLENDALE, CA 91206
Engineer Carrizosa, Richard Garcia; Lic. No.: C25828 1505 LYNDHURST AVE      HACIENDA HEIGHTS, CA 917452932

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/20/2020 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 12/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 2/10/2021 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 2/11/2021 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 2/12/2021 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 2/17/2021 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 3/9/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 5/12/2021 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 5/13/2021 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 5/17/2021 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 6/7/2021 Partial Approval DANIEL MC AULIFFE
Deputy Shotcrete 6/23/2021 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 7/1/2021 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 7/1/2021 Corrections Issued DANNY RODRIGUEZ
Deputy Reinf. Concrete 7/13/2021 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 7/13/2021 Partial Approval JOE VELASQUEZ
Deputy Reinf. Concrete 7/15/2021 Conditional Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 6/14/2022 Corrections Issued DANNY RODRIGUEZ
Footing/Foundation/Slab 6/17/2022 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 7/13/2022 Partial Approval KENNETH ROBERTS
Masonry Wall/Backfill 7/25/2022 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 8/3/2022 Partial Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 10/11/2022 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 11/21/2022 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 11/22/2022 Partial Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 11/23/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/30/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/22/2022 Conditional Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/7/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 2/9/2023 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/28/2023 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/16/2023 Partial Approval DANNY RODRIGUEZ
Deputy Wood Construction 6/23/2023 Conditional Approval DANNY RODRIGUEZ
Wood Frame 6/27/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Wood Construction 9/29/2023 Conditional Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/10/2023 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/12/2023 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 11/8/2023 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 11/16/2023 Partial Inspection DANNY RODRIGUEZ
Wood Frame 1/3/2024 Partial Approval DANNY RODRIGUEZ
Wood Frame 1/5/2024 Partial Approval DANNY RODRIGUEZ
Wood Frame 1/10/2024 Partial Approval DANNY RODRIGUEZ
Insulation 1/18/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 2/7/2024 Partial Approval DANNY RODRIGUEZ
Interior/Exterior Lathing 3/8/2024 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 4/26/2024 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 4/26/2024 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 5/3/2024 Partial Approval DANNY RODRIGUEZ
Wood Frame 5/3/2024 Partial Approval DANNY RODRIGUEZ
Insulation 5/29/2024 Not Ready for Inspection ANDREW DORSO
Wood Frame 5/29/2024 Partial Inspection ANDREW DORSO
Insulation 6/10/2024 Partial Approval ROBERT DAVIS
Wood Frame 6/10/2024 Partial Approval ROBERT DAVIS
Insulation 6/24/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 8/14/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 8/20/2024 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 8/22/2024 Corrections Issued DANNY RODRIGUEZ
Drywall Nailing 8/27/2024 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 8/27/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 8/30/2024 Not Ready for Inspection GREGORY POMISH
Drywall Nailing 9/3/2024 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 9/4/2024 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 9/13/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 9/25/2024 Partial Inspection DANNY RODRIGUEZ
Drywall Nailing 10/21/2024 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 11/26/2024 Partial Inspection ANDREW DORSO
Drywall Nailing 11/27/2024 Partial Approval JOHN KITCKO
Drywall Nailing 12/16/2024 Partial Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 2/12/2025 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 11/12/2025 Partial Inspection JOHN KITCKO
Verify Rec and Parks Fee Memo 11/12/2025 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 7/17/2026 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 7/22/2026 Partial Approval SEAN GRIFFITH