331 E WINDWARD AVE 90291
Certificate Information: 331 E WINDWARD AVE 90291
- Application / Permit
- 18010-10000-04167
- Plan Check / Job No.
- B18LA17977
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) CARPORT WITH SECOND STORY RECREATION ROOM
- Permit Issued
- Issued on 1/16/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2018 | APPLICANT |
| Green Plans Picked Up | 9/12/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2018 | KEVIN MORALES |
| Corrections Issued | 9/17/2018 | KEVIN MORALES |
| Quality Review Completed | 9/19/2018 | DAVID CHANG |
| Building Plans Picked Up | 9/24/2018 | APPLICANT |
| Plan Check Approved | 1/9/2019 | KEVIN MORALES |
| Issued | 1/16/2019 | LADBS |
| CofO in Progress | 9/27/2022 | DAVID FEILER |
| Permit Finaled | 9/29/2022 | DANIEL ORRANTE |
| CofO Issued | 9/29/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/29/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2018 | CELINA MORENO |
| Sewer availability | Cleared | 10/1/2018 | CELINA MORENO |
| Specific Plan | Cleared | 10/9/2018 | BINDU KANNAN |
| Historic monument | Cleared | 10/10/2018 | LAMBERT GIESSINGER |
| Coastal Zone | Cleared | 11/9/2018 | SOPHIE GABEL-SCHEINBAU |
| Green Code | Cleared | 11/15/2018 | KHEDER ALRAZAA |
| Low Impact Development | Cleared | 12/7/2018 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/7/2018 | JAMES MORALEZ |
Contact Information
| Contractor | Lyons Glenn Construction Inc; Lic. No.: 640172-B | 1335 APPLETON WAY VENICE, CA 90291 |
| Engineer | Erdelyi, Peter Tibor; Lic. No.: C26962 | 1950 SAWTELLE BLVD STE 175 LOS ANGELES, CA 90025 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/9/2019 | Partial Approval | DAVID HEINE |
| Deputy Reinf. Concrete | 6/14/2019 | Partial Approval | DAVID HEINE |
| Excavation/Setback/Form/Re-Bar | 6/26/2019 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 2/11/2020 | Partial Approval | DAVID HEINE |
| Deputy Wood Construction | 11/3/2021 | Approved | DAVID FEILER |
| Green Building Rough | 11/3/2021 | Not Ready for Inspection | DAVID FEILER |
| METHANE-Rough | 11/3/2021 | Conditional Approval | DAVID FEILER |
| Wood Frame | 11/3/2021 | Partial Approval | DAVID FEILER |
| Deputy Drilled-In Anchors | 1/21/2022 | No Access for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 1/26/2022 | Partial Approval | DAVID FEILER |
| Green Building Rough | 1/27/2022 | Not Ready for Inspection | DAVID FEILER |
| METHANE-Rough | 1/27/2022 | Not Ready for Inspection | DAVID FEILER |
| Wood Frame | 1/27/2022 | Partial Approval | DAVID FEILER |
| Masonry Wall/Backfill | 2/2/2022 | Partial Approval | DAVID FEILER |
| Deputy Wood Construction | 2/8/2022 | Conditional Approval | DAVID FEILER |
| Wood Frame | 4/13/2022 | Corrections Issued | DAVID FEILER |
| Green Building Rough | 5/11/2022 | Not Ready for Inspection | DAVID FEILER |
| METHANE-Rough | 5/11/2022 | Approved | DAVID FEILER |
| Wood Frame | 5/11/2022 | Partial Approval | DAVID FEILER |
| Green Building Rough | 5/19/2022 | Approved | JESUS RODRIGUEZ |
| Wood Frame | 5/24/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Insulation | 6/6/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Deputy Wood Construction | 6/7/2022 | Conditional Approval | RICHARD STEINBACH |
| Green Building Final | 6/13/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 6/13/2022 | Approved | JESUS RODRIGUEZ |
| Wood Frame | 6/13/2022 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 6/29/2022 | Approved | DAVID FEILER |
| Final | 9/1/2022 | Corrections Issued | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 9/1/2022 | SGSOV Approved | DAVID FEILER |
| Smoke Detectors | 9/1/2022 | Not Ready for Inspection | DAVID FEILER |
| Final | 9/13/2022 | Partial Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 9/13/2022 | Approved | DAVID FEILER |
| Smoke Detectors | 9/13/2022 | Approved | DAVID FEILER |
| Final | 9/26/2022 | OK to Issue CofO | DAVID FEILER |