1255 N AVENUE 50 90042

Certificate Information: 1255 N AVENUE 50 90042

Application / Permit
18010-10000-04086
Plan Check / Job No.
B18LA17460
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY ACCESSORY DWELLING UNIT PER AB 494 & SB 229.
Permit Issued
Issued on 11/27/2019
Issuing Office
Metro
Current Status
CofO Issued on 5/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/20/2018 APPLICANT
Green Plans Picked Up 9/12/2018 APPLICANT
Assigned to Plan Check Engineer 9/20/2018 SELLA BENYAMIN
Corrections Issued 9/25/2018 SELLA BENYAMIN
Quality Review Completed 9/27/2018 STEVEN KIM
Building Plans Picked Up 9/28/2018 APPLICANT
Plan Check Approved 1/8/2019 SELLA BENYAMIN
Issued 11/27/2019 LADBS
CofO in Progress 5/2/2022 CRAIG VAUGHAN
CofO in Progress 5/2/2022 CRAIG VAUGHAN
Permit Finaled 5/7/2022 DEROLD HAUFF
CofO Issued 5/7/2022 DEROLD HAUFF
Permit Finaled 5/7/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/9/2018 KARAN PATEL
Eng Process Fee Ord 176,300 Cleared 10/9/2018 KARAN PATEL
Hydrant and Access approval Cleared 10/9/2018 ROBERT DUFF
Permit Cleared 10/9/2018 KARAN PATEL
Sewer availability Cleared 10/9/2018 KARAN PATEL
Low Impact Development Cleared 10/10/2018 RYAN HUDSON
Roof/Waste drainage to street Cleared 10/10/2018 ADRIAN SANCHEZ
Green Code Cleared 11/9/2018 NEGAR NEJAD

Contact Information

Contractor Wronske Kevin Architects Corp; Lic. No.: 1036523-B 1313 PALMETTO STREET      LOS ANGELES, CA 90013

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/30/2019 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 4/22/2020 Partial Inspection COREY HUPP
Pre-Inspection 3/23/2021 Partial Inspection CRAIG VAUGHAN
Pre-Inspection 3/31/2021 Partial Inspection CRAIG VAUGHAN
Sewer 4/19/2021 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/20/2021 Approved CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/27/2021 Approved CRAIG VAUGHAN
Deputy Steel/Welding 5/12/2021 No Access for Inspection ELMER BLAND
ELECTRICAL-Rough 5/17/2021 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/24/2021 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 5/26/2021 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 6/8/2021 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/9/2021 Partial Approval KATHRYN BUTTERWORTH
PLUMBING-Rough 7/9/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 7/16/2021 Approved CRAIG VAUGHAN
HVAC-Rough 7/16/2021 Approved CRAIG VAUGHAN
Deputy Wood Construction 7/21/2021 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/22/2021 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 7/22/2021 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 7/22/2021 Corrections Issued CRAIG VAUGHAN
Verify Sprinkler Sign Off 7/22/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 7/30/2021 Partial Approval CRAIG VAUGHAN
Green Building Rough 7/30/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 7/30/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 8/11/2021 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 8/16/2021 Partial Approval CRAIG VAUGHAN
Insulation 8/27/2021 Approved CRAIG VAUGHAN
Shower Pan 8/27/2021 Approved CRAIG VAUGHAN
Drywall Nailing 9/7/2021 Approved HAMIK HARTOUNIAN
Sewer 11/22/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Special/Order Compliance 11/30/2021 Partial Inspection SHAVONNE ESPINOZA
Underground Mechanical 11/30/2021 Partial Approval OSVALDO PARAMO
Underground Mechanical 12/7/2021 Approved OSVALDO PARAMO
Underground Mechanical 12/13/2021 Partial Approval COREY HUPP
ELECTRICAL-Final 4/12/2022 Corrections Issued CRAIG VAUGHAN
Gas Test 4/12/2022 Approved CRAIG VAUGHAN
HVAC-Final 4/12/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 4/12/2022 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 4/18/2022 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Final 4/18/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 4/18/2022 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 4/18/2022 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 4/29/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Final 4/29/2022 Approved CRAIG VAUGHAN
Final 4/29/2022 OK to Issue CofO CRAIG VAUGHAN
Footing/Foundation/Slab 4/29/2022 Approved CRAIG VAUGHAN
Green Building Final 4/29/2022 Approved CRAIG VAUGHAN
Service/Power Release 4/29/2022 Approved CRAIG VAUGHAN