1255 N AVENUE 50 90042
Certificate Information: 1255 N AVENUE 50 90042
- Application / Permit
- 18010-10000-04086
- Plan Check / Job No.
- B18LA17460
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ACCESSORY DWELLING UNIT PER AB 494 & SB 229.
- Permit Issued
- Issued on 11/27/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/20/2018 | APPLICANT |
| Green Plans Picked Up | 9/12/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2018 | SELLA BENYAMIN |
| Corrections Issued | 9/25/2018 | SELLA BENYAMIN |
| Quality Review Completed | 9/27/2018 | STEVEN KIM |
| Building Plans Picked Up | 9/28/2018 | APPLICANT |
| Plan Check Approved | 1/8/2019 | SELLA BENYAMIN |
| Issued | 11/27/2019 | LADBS |
| CofO in Progress | 5/2/2022 | CRAIG VAUGHAN |
| CofO in Progress | 5/2/2022 | CRAIG VAUGHAN |
| Permit Finaled | 5/7/2022 | DEROLD HAUFF |
| CofO Issued | 5/7/2022 | DEROLD HAUFF |
| Permit Finaled | 5/7/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/9/2018 | KARAN PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 10/9/2018 | KARAN PATEL |
| Hydrant and Access approval | Cleared | 10/9/2018 | ROBERT DUFF |
| Permit | Cleared | 10/9/2018 | KARAN PATEL |
| Sewer availability | Cleared | 10/9/2018 | KARAN PATEL |
| Low Impact Development | Cleared | 10/10/2018 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 10/10/2018 | ADRIAN SANCHEZ |
| Green Code | Cleared | 11/9/2018 | NEGAR NEJAD |
Contact Information
| Contractor | Wronske Kevin Architects Corp; Lic. No.: 1036523-B | 1313 PALMETTO STREET LOS ANGELES, CA 90013 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/30/2019 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 4/22/2020 | Partial Inspection | COREY HUPP |
| Pre-Inspection | 3/23/2021 | Partial Inspection | CRAIG VAUGHAN |
| Pre-Inspection | 3/31/2021 | Partial Inspection | CRAIG VAUGHAN |
| Sewer | 4/19/2021 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/20/2021 | Approved | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/27/2021 | Approved | CRAIG VAUGHAN |
| Deputy Steel/Welding | 5/12/2021 | No Access for Inspection | ELMER BLAND |
| ELECTRICAL-Rough | 5/17/2021 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2021 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2021 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 7/9/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 7/9/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 7/16/2021 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 7/16/2021 | Approved | CRAIG VAUGHAN |
| Deputy Wood Construction | 7/21/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/22/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 7/22/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/22/2021 | Corrections Issued | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 7/22/2021 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 7/30/2021 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 7/30/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/30/2021 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/11/2021 | Partial Approval | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/16/2021 | Partial Approval | CRAIG VAUGHAN |
| Insulation | 8/27/2021 | Approved | CRAIG VAUGHAN |
| Shower Pan | 8/27/2021 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 9/7/2021 | Approved | HAMIK HARTOUNIAN |
| Sewer | 11/22/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Special/Order Compliance | 11/30/2021 | Partial Inspection | SHAVONNE ESPINOZA |
| Underground Mechanical | 11/30/2021 | Partial Approval | OSVALDO PARAMO |
| Underground Mechanical | 12/7/2021 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 12/13/2021 | Partial Approval | COREY HUPP |
| ELECTRICAL-Final | 4/12/2022 | Corrections Issued | CRAIG VAUGHAN |
| Gas Test | 4/12/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 4/12/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 4/12/2022 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Final | 4/18/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Final | 4/18/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/18/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 4/18/2022 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 4/29/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 4/29/2022 | Approved | CRAIG VAUGHAN |
| Final | 4/29/2022 | OK to Issue CofO | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/29/2022 | Approved | CRAIG VAUGHAN |
| Green Building Final | 4/29/2022 | Approved | CRAIG VAUGHAN |
| Service/Power Release | 4/29/2022 | Approved | CRAIG VAUGHAN |