811 S CENTRAL AVE 90021
Certificate Information: 811 S CENTRAL AVE 90021
- Application / Permit
- 18010-10000-04057
- Plan Check / Job No.
- B18LA17335
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- WAREHOUSE ( UNCONDITIONED SPACE) WITH SURFACE PARKING
- Permit Issued
- Issued on 7/11/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2018 | RUDOLF KINAR MELIKOFF |
| Corrections Issued | 9/10/2018 | RUDOLF KINAR MELIKOFF |
| Disabled Access Plans Picked Up | 9/11/2018 | APPLICANT |
| Green Plans Picked Up | 9/11/2018 | APPLICANT |
| Quality Review Completed | 9/12/2018 | STEVEN KIM |
| Building Plans Picked Up | 9/17/2018 | APPLICANT |
| Applicant returned to address corrections | 12/18/2018 | RUDOLF KINAR MELIKOFF |
| Applicant returned to address corrections | 1/8/2019 | RUDOLF KINAR MELIKOFF |
| Applicant returned to address corrections | 2/5/2019 | RUDOLF KINAR MELIKOFF |
| Plan Check Approved | 2/12/2019 | RUDOLF KINAR MELIKOFF |
| Issued | 7/11/2019 | LADBS |
| CofO in Progress | 1/26/2023 | KATY RAMIREZ |
| CofO Issued | 1/27/2023 | ERNESTO CORRAL |
| Permit Finaled | 1/27/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| "D" conditions | Cleared | 10/11/2018 | SOPHIE GABEL-SCHEINBAU |
| Address approval | Cleared | 10/11/2018 | JEANETTE VONG |
| Project located in CRA area | Cleared | 10/26/2018 | JIM URQUHART |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2018 | NAZILA NOORIFAR |
| Hydrant and Access approval | Cleared | 10/31/2018 | GEORGE SUCHAND |
| Sewer availability | Cleared | 10/31/2018 | NAZILA NOORIFAR |
| Green Code | Cleared | 12/4/2018 | DONALD CRICHLOW |
| Prkng lot landscape/Water mgmt | Cleared | 12/4/2018 | BLAYNE SUTTON-WILLS |
| DAS Clearance | Cleared | 1/9/2019 | SHINE LIN |
| Highway dedication | Cleared | 1/24/2019 | JAMES MORALEZ |
| Low Impact Development | Cleared | 2/1/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 2/5/2019 | CELINA MORENO |
Contact Information
| Architect | Segal,, Barry William; Lic. No.: C17861 | P O BOX 6108 ALTADENA, CA 91003 |
| Contractor | Owner-Builder | , |
| Engineer | Tan, Charles; Lic. No.: S4758 | 3161 DRIGGS AVENUE ROSEMEAD, CA 91770 |
Inspector Information
| NICK DANERI, (213) 202-5615 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/2/2021 | Approved | KATY RAMIREZ |
| Deputy Reinf. Concrete | 4/9/2021 | Conditional Approval | NICK DANERI |
| Masonry Wall/Backfill | 7/9/2021 | Partial Approval | KATY RAMIREZ |
| Masonry Wall/Backfill | 7/12/2021 | Partial Approval | KATY RAMIREZ |
| Masonry Wall/Backfill | 7/16/2021 | Partial Approval | KATY RAMIREZ |
| Wood Frame | 7/27/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Special/Order Compliance | 7/29/2021 | Approved | KATY RAMIREZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Wood Frame | 8/4/2021 | Corrections Issued | KATY RAMIREZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2021 | Not Ready for Inspection | DANIEL COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2021 | Corrections Issued | KATY RAMIREZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Drywall Nailing | 11/8/2021 | Partial Approval | KATY RAMIREZ |
| Green Building Rough | 11/8/2021 | Approved | KATY RAMIREZ |
| Insulation | 11/8/2021 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 11/8/2021 | Partial Approval | KATY RAMIREZ |
| Insulation | 11/10/2021 | Partial Approval | KATY RAMIREZ |
| Excavation/Setback/Form/Re-Bar | 12/1/2021 | Partial Approval | KATY RAMIREZ |
| Insulation | 12/3/2021 | Partial Approval | KATY RAMIREZ |
| Interior/Exterior Lathing | 12/20/2021 | Approved | NICK DANERI |
| Special/Order Compliance | 1/27/2022 | Partial Inspection | KATY RAMIREZ |
| Special/Order Compliance | 2/3/2022 | Approved | KATY RAMIREZ |
| Special/Order Compliance | 3/15/2022 | Approved | KATY RAMIREZ |
| Green Building Final | 4/14/2022 | Approved | KATY RAMIREZ |
| Special/Order Compliance | 6/30/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| Drywall Nailing | 7/1/2022 | Approved | KATY RAMIREZ |
| Final | 7/1/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Footing/Foundation/Slab | 7/1/2022 | Partial Approval | KATY RAMIREZ |
| METHANE-Barrier | 7/1/2022 | Approved | KATY RAMIREZ |
| METHANE-Final | 7/1/2022 | Approved | KATY RAMIREZ |
| METHANE-Rough | 7/1/2022 | Approved | KATY RAMIREZ |
| METHANE-Subgrade | 7/1/2022 | Approved | KATY RAMIREZ |
| Reinforced Masonry Frame | 7/1/2022 | Partial Approval | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 7/1/2022 | SGSOV No Gas | KATY RAMIREZ |
| Smoke Detectors | 7/1/2022 | Approved | KATY RAMIREZ |
| Structural Steel Frame | 7/1/2022 | Partial Approval | KATY RAMIREZ |
| Verify Sprinkler Sign Off | 7/1/2022 | Approved | KATY RAMIREZ |
| Final | 1/27/2023 | OK to Issue CofO | KATY RAMIREZ |
| Footing/Foundation/Slab | 1/27/2023 | Approved | KATY RAMIREZ |
| Reinforced Masonry Frame | 1/27/2023 | Approved | KATY RAMIREZ |
| Structural Steel Frame | 1/27/2023 | Approved | KATY RAMIREZ |