831 S WESTLAKE AVE 1-79 90057

Certificate Information: 831 S WESTLAKE AVE 1-79 90057

Application / Permit
18010-10000-04038
Plan Check / Job No.
B18LA17222
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 7 STORY with a Total of 79 UNIT APARTMENT BUILDING with 6-units Very Low Income and 6-units Extermely Low Income. FIRST 2 LEVELS Type I-A for Parking Podium AND 5 LEVELS Type III-A for Residential. TOC and AFFORDABLE HOUSING project per DIR-2019-2893-TOC. (builidng is per 2020LABC) "Comply with Department Order effective date 01/03/2020.
Permit Issued
Issued on 9/30/2022
Issuing Office
Valley
Current Status
Issued on 9/30/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/16/2018 APPLICANT
Assigned to Plan Check Engineer 9/6/2018 WING SUEN
Corrections Issued 10/11/2018 WING SUEN
Quality Review Completed 10/12/2018 CHARLES CHANG
Applicant returned to address corrections 11/14/2018 WING SUEN
Applicant returned to address corrections 7/1/2020 WING SUEN
Applicant returned to address corrections 7/7/2020 WING SUEN
Applicant returned to address corrections 7/13/2020 WING SUEN
Applicant returned to address corrections 7/14/2020 WING SUEN
Applicant returned to address corrections 7/23/2020 WING SUEN
Applicant returned to address corrections 7/28/2020 WING SUEN
Applicant returned to address corrections 7/30/2020 WING SUEN
Applicant returned to address corrections 8/10/2020 WING SUEN
Applicant returned to address corrections 8/26/2020 WING SUEN
Applicant returned to address corrections 9/9/2020 WING SUEN
Applicant returned to address corrections 9/15/2020 WING SUEN
Applicant returned to address corrections 9/23/2020 WING SUEN
Applicant returned to address corrections 11/24/2020 WING SUEN
Applicant returned to address corrections 2/17/2021 LARRY LEE
Applicant returned to address corrections 3/15/2021 LARRY LEE
Applicant returned to address corrections 5/11/2021 LARRY LEE
Applicant returned to address corrections 9/29/2021 LARRY LEE
Applicant returned to address corrections 11/4/2021 LARRY LEE
Plan Check Approved 4/6/2022 LARRY LEE
Building Plans Picked Up 5/10/2022 APPLICANT
Issued 9/30/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/7/2018 NAZILA NOORIFAR
Miscellaneous Cleared 11/14/2018 MOTOUMI SASAKI
Site Plan review Cleared 11/14/2018 MOTOUMI SASAKI
Highway dedication Cleared 11/30/2018 JEANETTE VONG
Project located in CRA area Cleared 7/9/2019 JIM URQUHART
Address approval Cleared 10/14/2020 ELAINE LEI
Address approval Cleared 10/14/2020 ELAINE LEI
Bicycle Parking Cleared 10/14/2020 ELAINE LEI
Highway dedication Cleared 10/14/2020 ELAINE LEI
Permit Cleared 10/15/2020 ELAINE LEI
Hydrant and Access approval Cleared 10/30/2020 MATTHEW CRAIG
Sewer availability Cleared 10/30/2020 ELAINE LEI
Building over 3-story or 36-ft Cleared 11/9/2020 CALOSHA APPROVED
Historic Resource Verification Cleared 2/2/2021 MICAELA TORRES-GIL
Internal circulation Cleared 2/11/2021 EDUARDO HERMOSO
Redevelopment Project Area Cleared 3/4/2021 DAVID URITA
Redevelopment Project Area Cleared 3/4/2021 DAVID URITA
ZI Cleared 3/4/2021 DAVID URITA
Low Impact Development Cleared 5/5/2021 AMMAR ELTAWIL
Density Bonus 12.22.A.31 Cleared 5/12/2021 NGHIEM TRAN
DCP conditions approval Cleared 5/13/2021 NGHIEM TRAN
Green Code Cleared 5/13/2021 AARON COSTA
Roof/Waste drainage to street Cleared 5/13/2021 THAN WIN
Fire Marshall Fire Life Safety Cleared 11/22/2021 OSCAR SALGADO JR
DAS Clearance Cleared 12/29/2021 WING SUEN
Frnt yard landscape/Water mgmt Cleared 2/9/2022 MAXFIELD VERMY
Miscellaneous Cleared 2/9/2022 MAXFIELD VERMY
Miscellaneous Cleared 2/9/2022 MAXFIELD VERMY
Opn space landscape/Water mgmt Cleared 2/9/2022 MAXFIELD VERMY
Site Plan review Cleared 2/9/2022 MAXFIELD VERMY
Work Adjacent to Public Way Cleared 3/9/2022 STEVE MELGAR

Contact Information

Contractor Stonewall Construction Inc; Lic. No.: 1014817-B P O BOX 103      SAN FERNANDO, CA 91340
Engineer Afshar,, Rouzbeh; Lic. No.: C87032 1133 CAMELBACK ST 9038      NEWPORT BEACH, CA 92658
Engineer Bozorgnia,, Behrouz; Lic. No.: C79581 1557 WESTWOOD BLVD 145      LOS ANGELES, CA 90024

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/6/2022 Not Ready for Inspection DAVID BURKHEAD
Deputy Other (see comments) 4/27/2023 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 4/27/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 5/1/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/8/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/12/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/15/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 5/15/2023 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 5/17/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/19/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 6/2/2023 Conditional Approval NICK DANERI
Green Building Rough 6/2/2023 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 6/2/2023 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 6/2/2023 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 6/21/2023 Conditional Approval NICK DANERI
Green Building Rough 6/21/2023 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 6/21/2023 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 6/21/2023 Not Ready for Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 6/22/2023 Partial Approval NICK DANERI
Deputy Reinf. Concrete 7/11/2023 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 7/11/2023 Partial Approval GREGORY POMISH
Green Building Rough 7/26/2023 Partial Inspection GREGORY POMISH
Reinforced Concrete Frame 7/26/2023 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 7/26/2023 Partial Inspection GREGORY POMISH
Deputy Reinf. Concrete 8/4/2023 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 8/18/2023 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 8/22/2023 Conditional Approval NICK DANERI
Green Building Rough 9/8/2023 Partial Inspection GREGORY POMISH
Reinforced Concrete Frame 9/8/2023 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 9/8/2023 Partial Inspection GREGORY POMISH
Deputy Reinf. Concrete 9/13/2023 Conditional Approval NICK DANERI
Green Building Rough 9/13/2023 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 9/13/2023 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 9/13/2023 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 9/18/2023 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/27/2023 Conditional Approval NICK DANERI
Green Building Rough 9/27/2023 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 9/27/2023 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 9/27/2023 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 9/28/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 10/12/2023 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 12/4/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 1/4/2024 Conditional Approval NICK DANERI
Special/Order Compliance 1/4/2024 Partial Inspection NICK DANERI
Deputy Drilled-In Anchors 1/5/2024 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 1/5/2024 Conditional Approval NICK DANERI
Green Building Rough 1/5/2024 Partial Inspection NICK DANERI
Reinforced Concrete Frame 1/5/2024 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 1/5/2024 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 1/11/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 2/2/2024 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 2/6/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 2/6/2024 Partial Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 2/7/2024 Partial Inspection NICK DANERI
Deputy Wood Construction 2/8/2024 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 2/8/2024 Partial Approval NICK DANERI
Deputy Wood Construction 2/9/2024 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 4/5/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/18/2024 Not Ready for Inspection LARRY ARNICK
Deputy Wood Construction 4/19/2024 Conditional Approval NICK DANERI
Wood Frame 4/19/2024 Partial Approval NICK DANERI
Deputy Wood Construction 5/3/2024 Conditional Approval NICK DANERI
Deputy Wood Construction 5/6/2024 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/6/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/31/2024 Partial Approval NICK DANERI
Green Building Rough 6/21/2024 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 6/21/2024 Not Ready for Inspection NICK DANERI
Wood Frame 6/21/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 7/26/2024 Partial Approval DANIEL VARNUM
Insulation 7/31/2024 Partial Approval NICK DANERI
Deputy Wood Construction 8/6/2024 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 8/6/2024 Not Ready for Inspection LARRY ARNICK
Deputy Wood Construction 8/7/2024 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 8/7/2024 Partial Approval NICK DANERI
Insulation 8/26/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 10/11/2024 Partial Approval NICK DANERI
Interior/Exterior Lathing 10/28/2024 Partial Approval NICK DANERI
Insulation 11/5/2024 Partial Approval NICK DANERI
Insulation 12/31/2024 Partial Inspection NICK DANERI
Insulation 1/13/2025 Partial Approval NICK DANERI
Insulation 2/6/2025 Partial Approval NICK DANERI
Drywall Nailing 2/14/2025 Partial Approval NICK DANERI
Green Building Rough 2/14/2025 Partial Approval NICK DANERI
Interior/Exterior Lathing 3/3/2025 Partial Approval PAUL BAZERKANIAN
Interior/Exterior Lathing 3/19/2025 Partial Approval LARRY ARNICK
Insulation 4/1/2025 Partial Approval NICK DANERI
Drywall Nailing 4/10/2025 Partial Approval NICK DANERI
Green Building Rough 4/10/2025 Not Ready for Inspection NICK DANERI
Drywall Nailing 4/18/2025 Partial Approval NICK DANERI
Green Building Rough 4/18/2025 Not Ready for Inspection NICK DANERI
Drywall Nailing 4/25/2025 Partial Approval NICK DANERI
Green Building Rough 4/25/2025 Not Ready for Inspection NICK DANERI
Drywall Nailing 5/1/2025 Partial Approval RAFAEL CORTES
Green Building Rough 5/1/2025 Not Ready for Inspection RAFAEL CORTES
Drywall Nailing 6/10/2025 Not Ready for Inspection JOEY BUCHANAN
Green Building Rough 6/10/2025 Approved JOEY BUCHANAN
Light Gage Steel Frame 6/17/2025 Conditional Approval JOEY BUCHANAN
Drywall Nailing 7/7/2025 Partial Approval JOEY BUCHANAN
Interior/Exterior Lathing 7/7/2025 Partial Approval JOEY BUCHANAN
Drywall Nailing 7/31/2025 Partial Approval JOEY BUCHANAN
Interior/Exterior Lathing 8/4/2025 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 10/15/2025 Not Ready for Inspection JOEY BUCHANAN
Masonry Wall/Backfill 10/20/2025 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 11/13/2025 Approved JOEY BUCHANAN
Masonry Wall/Backfill 12/2/2025 Partial Approval JOEY BUCHANAN
Light Gage Steel Frame 12/10/2025 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 12/18/2025 Partial Approval JOEY BUCHANAN
Special/Order Compliance 3/31/2026 Approved JOEY BUCHANAN