1874 N MORTON AVE 90026

Certificate Information: 1874 N MORTON AVE 90026

Application / Permit
18010-10000-03999
Plan Check / Job No.
B18LA16917
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
PROPOSED 1 STORY RECREATION ROOM WITH ROOF DECK.
Permit Issued
Issued on 5/20/2019
Issuing Office
Metro
Current Status
CofO Issued on 3/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2018 APPLICANT
Assigned to Plan Check Engineer 9/13/2018 MICHAEL LOPEZ
Corrections Issued 9/18/2018 MICHAEL LOPEZ
Green Plans Picked Up 9/20/2018 APPLICANT
Quality Review Completed 9/21/2018 DAVID CHANG
Building Plans Picked Up 9/27/2018 APPLICANT
Applicant returned to address corrections 1/23/2019 MICHAEL LOPEZ
Plan Check Approved 4/3/2019 MICHAEL LOPEZ
Issued 5/20/2019 LADBS
CofO in Progress 5/23/2021 STUART CHAPMAN
Permit Finaled 3/7/2023 DANIEL ORRANTE
CofO Issued 3/7/2023 DANIEL ORRANTE
Permit Finaled 3/7/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/18/2018 CELINA MORENO
Sewer availability Cleared 10/18/2018 CELINA MORENO
Low Impact Development Cleared 11/1/2018 MITESH PATEL
Roof/Waste drainage to street Cleared 11/1/2018 MICHAEL CASTILLO
Green Code Cleared 11/15/2018 MICHAEL LOPEZ
Grading Pre-Inspection Cleared 1/11/2019 JOHNNY KAZARIAN
Hydrant and Access approval Cleared 1/15/2019 GEORGE SUCHAND

Contact Information

Contractor L A Green Building; Lic. No.: 989835-B 319 W FAIRVIEW BLVD      INGLEWOOD, CA 90302
Engineer Garza,, Omar Leonel; Lic. No.: S5593 4215 TOLAND WAY      LOS ANGELES, CA 90065
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Geologist Irvine,, Jon A; Lic. No.: EG1691 819 W HERITAGE OAK CT      ALTADENA, CA 91001

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/24/2019 Partial Approval DAVID CHAN
Piling/Pier/Caisson 6/24/2019 Partial Approval DAVID CHAN
Footing/Foundation/Slab 7/25/2019 Partial Approval DAVID CHAN
Pre-Inspection 8/6/2019 Conditional Approval RUBEN SALAS
PLUMBING-Rough 8/16/2019 Partial Approval ROBERT VORHIS
Footing/Foundation/Slab 8/27/2019 Partial Approval DAVID CHAN
PLUMBING-Rough 8/29/2019 Partial Approval DAVID CHAN
ELECTRICAL-Rough 10/4/2019 Approved DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 10/4/2019 Approved DAVID CHAN
PLUMBING-Rough 10/4/2019 Not Ready for Inspection DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 10/11/2019 Approved DAVID CHAN
PLUMBING-Rough 10/11/2019 Approved DAVID CHAN
Wood Frame 10/11/2019 Conditional Approval DAVID CHAN
BUILDING-Rough-Frame 10/23/2019 Partial Approval DAVID CHAN
Insulation 11/15/2019 Approved AJA COLLAY
Interior/Exterior Lathing 11/15/2019 Corrections Issued AJA COLLAY
Drywall Nailing 11/20/2019 Approved AJA COLLAY
Final 6/19/2020 Corrections Issued COREY HUPP
SGSOV-Seismic Gas S/O Valve 6/19/2020 SGSOV Approved COREY HUPP
Smoke Detectors 6/19/2020 Approved COREY HUPP
Verify Sprinkler Sign Off 6/19/2020 Approved COREY HUPP
BUILDING-Rough-Frame 7/13/2020 Approved ENRIQUE MIRELES
Final 7/13/2020 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 7/13/2020 Approved ENRIQUE MIRELES
Green Building Final 7/13/2020 Approved ENRIQUE MIRELES
Green Building Rough 7/13/2020 Approved ENRIQUE MIRELES
Service/Power Release 7/13/2020 Not Ready for Inspection ENRIQUE MIRELES
Final 7/15/2020 Partial Inspection DAVID CHAN
Service/Power Release 7/15/2020 Not Required DAVID CHAN
ELECTRICAL-Final 9/8/2020 Approved STUART CHAPMAN
Final 9/8/2020 Conditional Approval STUART CHAPMAN
HVAC-Final 9/8/2020 Approved STUART CHAPMAN
Final 5/21/2021 OK to Issue CofO STUART CHAPMAN