14623 W SUTTON ST 91403

Certificate Information: 14623 W SUTTON ST 91403

Application / Permit
18010-10000-03960
Plan Check / Job No.
B18LA16762
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW DETACHED RECREATION ROOM
Permit Issued
Issued on 12/13/2018
Issuing Office
Valley
Current Status
CofO Issued on 5/19/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2018 APPLICANT
Assigned to Plan Check Engineer 8/10/2018 PRANITA SHAH
Corrections Issued 8/10/2018 PRANITA SHAH
Plan Check Approved 12/5/2018 PRANITA SHAH
Issued 12/13/2018 LADBS
CofO in Progress 4/17/2026 MICHAEL CORTEZ
Permit Finaled 5/19/2026 RUBEN SALAS
CofO Issued 5/19/2026 RUBEN SALAS
Permit Finaled 5/19/2026 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/13/2018 LEE GUILBEAUX
Hydrant and Access approval Cleared 8/13/2018 GILBERT URREA
Sewer availability Cleared 8/13/2018 LEE GUILBEAUX
Green Code Cleared 10/10/2018 PRANITA SHAH
Low Impact Development Cleared 10/10/2018 RYAN HUDSON
Roof/Waste drainage to street Cleared 10/10/2018 JEANETTE VONG
Construction near power lines Cleared 11/30/2018 RIDWAN HARDY

Contact Information

Contractor Roth Craig D; Lic. No.: 1006385-B 602 ROSARIO DRIVE      THOUSAND OAKS, CA 91362

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 12/19/2018 Approved CHRISTOPHE COCHRAN
Underground Mechanical 1/24/2019 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 3/1/2019 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 11/20/2019 Approved CHRISTOPHE COCHRAN
Gas Test 9/9/2020 Approved CHARLES POWELL
HVAC-Rough 9/9/2020 Approved CHARLES POWELL
PLUMBING-Rough 9/9/2020 Approved CHARLES POWELL
BUILDING-Rough-Frame 9/17/2020 Not Ready for Inspection CHARLES POWELL
ELECTRICAL-Rough 9/17/2020 Approved CHARLES POWELL
Green Building Rough 9/17/2020 Approved CHARLES POWELL
Verify Sprinkler Sign Off 9/17/2020 Not Ready for Inspection CHARLES POWELL
BUILDING-Rough-Frame 10/15/2020 Approved CHARLES POWELL
Underground Mechanical 10/15/2020 Corrections Issued CHARLES POWELL
Verify Sprinkler Sign Off 10/15/2020 Approved CHARLES POWELL
Insulation 11/2/2020 Not Ready for Inspection DAVID MATSON
Insulation 11/9/2020 Approved CHARLES POWELL
HVAC-Rough 1/5/2021 Approved CHARLES POWELL
Drywall Nailing 3/10/2021 Approved CHARLES POWELL
Special/Order Compliance 10/10/2024 Corrections Issued JUAN VALENZUELA
PLUMBING-Final 1/15/2025 Corrections Issued CHRISTOPHE COCHRAN
PLUMBING-Final 1/17/2025 Approved JACK KARGODORIAN
Final 3/6/2026 No Access for Inspection MISAEL ESPARZA
Green Building Final 3/6/2026 No Access for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/6/2026 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 3/6/2026 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 3/6/2026 No Access for Inspection MISAEL ESPARZA
Final 3/10/2026 Corrections Issued MICHAEL CORTEZ
Green Building Final 3/10/2026 Approved MICHAEL CORTEZ
SGSOV-Seismic Gas S/O Valve 3/10/2026 SGSOV Approved MICHAEL CORTEZ
Smoke Detectors 3/10/2026 Approved MICHAEL CORTEZ
Final 4/17/2026 OK to Issue CofO MICHAEL CORTEZ
Service/Power Release 4/17/2026 Approved MICHAEL CORTEZ