718 S CITRUS AVE 90036
Certificate Information: 718 S CITRUS AVE 90036
- Application / Permit
- 18010-10000-03895
- Plan Check / Job No.
- B18LA16414
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY (40' X 29.5') ACCESSORY DWELLING UNIT PER AB 494 AND SB 299
- Permit Issued
- Issued on 1/23/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/7/2018 | APPLICANT |
| Green Plans Picked Up | 9/12/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2018 | MONICA RAMIREZ |
| Corrections Issued | 9/17/2018 | MONICA RAMIREZ |
| Quality Review Completed | 10/3/2018 | BILL STUTSMAN |
| Building Plans Picked Up | 10/10/2018 | APPLICANT |
| Applicant returned to address corrections | 1/31/2019 | MONICA RAMIREZ |
| Plan Check Approved | 7/2/2019 | MONICA RAMIREZ |
| Issued | 1/23/2020 | LADBS |
| CofO in Progress | 12/2/2021 | JOSEPH MCGARRY |
| Permit Finaled | 1/8/2022 | DEROLD HAUFF |
| CofO Issued | 1/8/2022 | DEROLD HAUFF |
| Permit Finaled | 1/8/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 11/6/2018 | GEORGE SUCHAND |
| Green Code | Cleared | 1/15/2019 | NEGAR NEJAD |
| Address approval | Cleared | 6/20/2019 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/20/2019 | JEANETTE VONG |
| Low Impact Development | Cleared | 6/20/2019 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 6/20/2019 | JEANETTE VONG |
| Sewer availability | Cleared | 6/20/2019 | JEANETTE VONG |
Contact Information
| Contractor | Sheene Paul Corporation; Lic. No.: 1015399-B | 639 N BROADWAY #563 LOS ANGELES, CA 90012 |
| Engineer | Park, Juntae; Lic. No.: C65104 | 1444 HI POINT ST LOS ANGELES, CA 90035 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/28/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 1/28/2020 | Corrections Issued | ARTHUR SARGSYAN |
| METHANE-Barrier | 1/28/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| METHANE-Subgrade | 1/28/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 2/14/2020 | Partial Inspection | ARTHUR SARGSYAN |
| Pre-Inspection | 2/14/2020 | Partial Inspection | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 2/20/2020 | Approved | ARTHUR SARGSYAN |
| Special/Order Compliance | 2/20/2020 | Approved | BRAD BESCOS |
| Underground Mechanical | 2/20/2020 | Approved | ARTHUR SARGSYAN |
| Underground Mechanical | 3/9/2020 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2020 | Partial Approval | ARTHUR SARGSYAN |
| PLUMBING-Rough | 4/16/2020 | Approved | ARTHUR SARGSYAN |
| Deputy Wood Construction | 4/28/2020 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 4/28/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| HVAC-Rough | 4/28/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| PLUMBING-Rough | 4/28/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 4/30/2020 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 4/30/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| PLUMBING-Rough | 4/30/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| PLUMBING-Rough | 5/1/2020 | Approved | ARTHUR SARGSYAN |
| Insulation | 5/8/2020 | Approved | ARTHUR SARGSYAN |
| Wood Frame | 5/8/2020 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 5/12/2020 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 5/29/2020 | Approved | ARTHUR SARGSYAN |
| Sewer | 11/4/2020 | Approved | DONALD CRICHLOW |
| Deputy Drilled-In Anchors | 1/26/2021 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 1/26/2021 | Approved | JOSEPH MCGARRY |
| METHANE-Barrier | 1/26/2021 | Approved | JOSEPH MCGARRY |
| METHANE-Subgrade | 1/26/2021 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 2/11/2021 | Corrections Issued | JOSEPH MCGARRY |
| Final | 2/11/2021 | Corrections Issued | JOSEPH MCGARRY |
| Gas Test | 2/11/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Final | 2/11/2021 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Final | 2/11/2021 | Corrections Issued | JOSEPH MCGARRY |
| Service/Power Release | 2/11/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 2/18/2021 | Approved | JOSEPH MCGARRY |
| Final | 2/18/2021 | Corrections Issued | JOSEPH MCGARRY |
| Gas Test | 2/18/2021 | Approved | JOSEPH MCGARRY |
| Green Building Final | 2/18/2021 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 2/18/2021 | Approved | JOSEPH MCGARRY |
| METHANE-Final | 2/18/2021 | Approved | JOSEPH MCGARRY |
| METHANE-Rough | 2/18/2021 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 2/18/2021 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 2/18/2021 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 2/18/2021 | Approved | JOSEPH MCGARRY |
| Final | 7/14/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Service/Power Release | 7/14/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 11/30/2021 | OK to Issue CofO | JOSEPH MCGARRY |
| Service/Power Release | 11/30/2021 | Approved | JOSEPH MCGARRY |