718 S CITRUS AVE 90036

Certificate Information: 718 S CITRUS AVE 90036

Application / Permit
18010-10000-03895
Plan Check / Job No.
B18LA16414
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY (40' X 29.5') ACCESSORY DWELLING UNIT PER AB 494 AND SB 299
Permit Issued
Issued on 1/23/2020
Issuing Office
Metro
Current Status
CofO Issued on 1/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/7/2018 APPLICANT
Green Plans Picked Up 9/12/2018 APPLICANT
Assigned to Plan Check Engineer 9/13/2018 MONICA RAMIREZ
Corrections Issued 9/17/2018 MONICA RAMIREZ
Quality Review Completed 10/3/2018 BILL STUTSMAN
Building Plans Picked Up 10/10/2018 APPLICANT
Applicant returned to address corrections 1/31/2019 MONICA RAMIREZ
Plan Check Approved 7/2/2019 MONICA RAMIREZ
Issued 1/23/2020 LADBS
CofO in Progress 12/2/2021 JOSEPH MCGARRY
Permit Finaled 1/8/2022 DEROLD HAUFF
CofO Issued 1/8/2022 DEROLD HAUFF
Permit Finaled 1/8/2022 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 11/6/2018 GEORGE SUCHAND
Green Code Cleared 1/15/2019 NEGAR NEJAD
Address approval Cleared 6/20/2019 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 6/20/2019 JEANETTE VONG
Low Impact Development Cleared 6/20/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 6/20/2019 JEANETTE VONG
Sewer availability Cleared 6/20/2019 JEANETTE VONG

Contact Information

Contractor Sheene Paul Corporation; Lic. No.: 1015399-B 639 N BROADWAY #563      LOS ANGELES, CA 90012
Engineer Park, Juntae; Lic. No.: C65104 1444 HI POINT ST      LOS ANGELES, CA 90035

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/28/2020 Not Ready for Inspection ARTHUR SARGSYAN
Footing/Foundation/Slab 1/28/2020 Corrections Issued ARTHUR SARGSYAN
METHANE-Barrier 1/28/2020 Not Ready for Inspection ARTHUR SARGSYAN
METHANE-Subgrade 1/28/2020 Not Ready for Inspection ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 2/14/2020 Partial Inspection ARTHUR SARGSYAN
Pre-Inspection 2/14/2020 Partial Inspection ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 2/20/2020 Approved ARTHUR SARGSYAN
Special/Order Compliance 2/20/2020 Approved BRAD BESCOS
Underground Mechanical 2/20/2020 Approved ARTHUR SARGSYAN
Underground Mechanical 3/9/2020 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/7/2020 Partial Approval ARTHUR SARGSYAN
PLUMBING-Rough 4/16/2020 Approved ARTHUR SARGSYAN
Deputy Wood Construction 4/28/2020 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 4/28/2020 Not Ready for Inspection ARTHUR SARGSYAN
HVAC-Rough 4/28/2020 Not Ready for Inspection ARTHUR SARGSYAN
PLUMBING-Rough 4/28/2020 Not Ready for Inspection ARTHUR SARGSYAN
ELECTRICAL-Rough 4/30/2020 Approved ARTHUR SARGSYAN
HVAC-Rough 4/30/2020 Not Ready for Inspection ARTHUR SARGSYAN
PLUMBING-Rough 4/30/2020 Not Ready for Inspection ARTHUR SARGSYAN
PLUMBING-Rough 5/1/2020 Approved ARTHUR SARGSYAN
Insulation 5/8/2020 Approved ARTHUR SARGSYAN
Wood Frame 5/8/2020 Approved ARTHUR SARGSYAN
Drywall Nailing 5/12/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 5/29/2020 Approved ARTHUR SARGSYAN
Sewer 11/4/2020 Approved DONALD CRICHLOW
Deputy Drilled-In Anchors 1/26/2021 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 1/26/2021 Approved JOSEPH MCGARRY
METHANE-Barrier 1/26/2021 Approved JOSEPH MCGARRY
METHANE-Subgrade 1/26/2021 Approved JOSEPH MCGARRY
ELECTRICAL-Final 2/11/2021 Corrections Issued JOSEPH MCGARRY
Final 2/11/2021 Corrections Issued JOSEPH MCGARRY
Gas Test 2/11/2021 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Final 2/11/2021 Corrections Issued JOSEPH MCGARRY
PLUMBING-Final 2/11/2021 Corrections Issued JOSEPH MCGARRY
Service/Power Release 2/11/2021 Not Ready for Inspection JOSEPH MCGARRY
BUILDING-Rough-Frame 2/18/2021 Approved JOSEPH MCGARRY
Final 2/18/2021 Corrections Issued JOSEPH MCGARRY
Gas Test 2/18/2021 Approved JOSEPH MCGARRY
Green Building Final 2/18/2021 Approved JOSEPH MCGARRY
Green Building Rough 2/18/2021 Approved JOSEPH MCGARRY
METHANE-Final 2/18/2021 Approved JOSEPH MCGARRY
METHANE-Rough 2/18/2021 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 2/18/2021 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 2/18/2021 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 2/18/2021 Approved JOSEPH MCGARRY
Final 7/14/2021 Not Ready for Inspection JOSEPH MCGARRY
Service/Power Release 7/14/2021 Not Ready for Inspection JOSEPH MCGARRY
Final 11/30/2021 OK to Issue CofO JOSEPH MCGARRY
Service/Power Release 11/30/2021 Approved JOSEPH MCGARRY