6315 N BEEMAN AVE 91606
Certificate Information: 6315 N BEEMAN AVE 91606
- Application / Permit
- 18010-10000-03883
- Plan Check / Job No.
- B18LA16310
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 28'-11" x 23'-9" TWO-STORY ACCESSORY DWELLING UNIT WITH OPEN ROOFTOP DECK PER AB 494 AND SB 229.
- Permit Issued
- Issued on 1/14/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/6/2018 | APPLICANT |
| Green Plans Picked Up | 8/30/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2018 | OMID HEDAYAT |
| Corrections Issued | 9/19/2018 | OMID HEDAYAT |
| Quality Review Completed | 9/21/2018 | STEVEN KIM |
| Building Plans Picked Up | 9/25/2018 | APPLICANT |
| Plan Check Approved | 11/18/2019 | OMID HEDAYAT |
| Issued | 1/14/2021 | APPLICANT |
| CofO in Progress | 10/21/2021 | CHRISTOPHE COCHRAN |
| CofO Issued | 10/23/2021 | MICHAEL SMITH |
| Permit Finaled | 10/23/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/28/2019 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2019 | ELAINE LEI |
| Hydrant and Access approval | Cleared | 3/5/2019 | GILBERT URREA |
| Sewer availability | Cleared | 3/5/2019 | ELAINE LEI |
| Low Impact Development | Cleared | 8/14/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/14/2019 | JEANIE LAM |
| Construction within easement | Cleared | 9/7/2019 | WALTER RAMIREZ |
| Green Code | Cleared | 11/18/2019 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mehran, Mansuri; Lic. No.: C78614 | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/2/2021 | Partial Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 2/24/2021 | Partial Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 3/1/2021 | Not Ready for Inspection | JOHN HAYES |
| Pre-Inspection | 3/2/2021 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 3/5/2021 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 3/17/2021 | Partial Approval | BRENDAN LOONEY |
| Green Building Rough | 3/17/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 3/17/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2021 | Partial Approval | RICHARD DOCKUS |
| Green Building Rough | 4/5/2021 | Approved | RICHARD DOCKUS |
| Verify Sprinkler Sign Off | 4/5/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2021 | Partial Approval | RICHARD DOCKUS |
| PLUMBING-Rough | 4/9/2021 | Corrections Issued | RICHARD DOCKUS |
| Underground Mechanical | 4/15/2021 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 4/21/2021 | No Access for Inspection | BEAU COLLINS |
| HVAC-Rough | 4/21/2021 | Not Ready for Inspection | BEAU COLLINS |
| Verify Sprinkler Sign Off | 4/21/2021 | No Access for Inspection | BEAU COLLINS |
| HVAC-Rough | 4/22/2021 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 5/6/2021 | Approved | RICHARD DOCKUS |
| Verify Sprinkler Sign Off | 5/6/2021 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 5/19/2021 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 5/19/2021 | Partial Approval | RICHARD DOCKUS |
| Insulation | 5/25/2021 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 6/4/2021 | Approved | RICHARD DOCKUS |
| Shower Pan | 6/17/2021 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 6/24/2021 | Approved | DEANDRE HOFFMAN |
| Final | 10/8/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 10/8/2021 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 10/8/2021 | SGSOV Not Ready | CHRISTOPHE COCHRAN |
| Service/Power Release | 10/8/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 10/8/2021 | Approved | CHRISTOPHE COCHRAN |
| Final | 10/14/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 10/14/2021 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 10/14/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 10/21/2021 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Service/Power Release | 10/21/2021 | Approved | CHRISTOPHE COCHRAN |