471 1/4 E 41ST PL 90011
Certificate Information: 471 1/4 E 41ST PL 90011
- Application / Permit
- 18010-10000-03879
- Plan Check / Job No.
- B18LA16293
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New unpermitted dwelling unit (UDU) in accordance with ordinance 184907 per ADM-2018-7522-UDU.
- Permit Issued
- Issued on 8/27/2019
- Issuing Office
- Metro
- Current Status
- Issued on 8/27/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/6/2018 | APPLICANT |
| Green Plans Picked Up | 8/20/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2018 | HELEN NGUYEN |
| Corrections Issued | 9/4/2018 | HELEN NGUYEN |
| Quality Review Completed | 9/12/2018 | BILL STUTSMAN |
| Building Plans Picked Up | 9/14/2018 | APPLICANT |
| Applicant returned to address corrections | 11/20/2018 | HELEN NGUYEN |
| Applicant returned to address corrections | 12/20/2018 | HELEN NGUYEN |
| Applicant returned to address corrections | 7/24/2019 | HELEN NGUYEN |
| Plan Check Approved | 7/29/2019 | HELEN NGUYEN |
| Issued | 8/27/2019 | LADBS |
Permit Application Clearance Information
| Green Code | Cleared | 9/18/2018 | SARAH ABOULHOSN |
| Address approval | Cleared | 11/15/2018 | NAZILA NOORIFAR |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2018 | NAZILA NOORIFAR |
| Housing rent stabilization | Cleared | 11/15/2018 | STEVEN HOFSTAD |
| Low Impact Development | Cleared | 11/15/2018 | RYAN HUDSON |
| Sewer availability | Cleared | 11/15/2018 | NAZILA NOORIFAR |
| Roof/Waste drainage to street | Cleared | 11/19/2018 | NAZILA NOORIFAR |
| Density Bonus 14.00.A.10 | Cleared | 6/17/2019 | KENNETH LE |
| Unpermitted Dwelling Unit | Cleared | 7/9/2019 | ERIC CLAROS |
| Hydrant and Access approval | Cleared | 7/24/2019 | GILBERT URREA |
Contact Information
| Engineer | Carrillo, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
| Engineer | Zhong, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/24/2019 | Corrections Issued | JOAQUIN GREENOUGH |
| Deputy Drilled-In Anchors | 3/1/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/1/2024 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 4/1/2024 | Not Ready for Inspection | SABAS ALONSO |
| Verify Sprinkler Sign Off | 4/1/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 4/17/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 4/17/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/15/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 7/15/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/19/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 7/19/2024 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 7/19/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 7/19/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 7/19/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 7/19/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/19/2024 | Approved | ALEJANDRO DE ARTOLA |
| Shower Pan | 7/19/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 7/24/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Shower Pan | 7/24/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 7/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 7/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Shower Pan | 7/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 7/29/2024 | Approved | ALEX COLIN |
| Shower Pan | 7/29/2024 | Approved | ALEX COLIN |
| Final | 9/13/2024 | Corrections Issued | WILLIAM SIERRA |
| Footing/Foundation/Slab | 9/13/2024 | Partial Inspection | WILLIAM SIERRA |
| Green Building Final | 9/13/2024 | Corrections Issued | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 9/13/2024 | SGSOV Not Ready | WILLIAM SIERRA |
| Service/Power Release | 9/13/2024 | Corrections Issued | WILLIAM SIERRA |
| Smoke Detectors | 9/13/2024 | Approved | WILLIAM SIERRA |
| Pre-Inspection | 4/7/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 2/10/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |