6517 W LEXINGTON AVE UNIT #10 90038
Certificate Information: 6517 W LEXINGTON AVE UNIT #10 90038
- Application / Permit
- 18010-10000-03864
- Plan Check / Job No.
- B18LA12004
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PDPP - SMALL LOT SUBDIVISION - SINGLE FAMILY DWELLING WITH ATTACHED GARAGE PER VTT 74942-SL-1A . 10 OF 18.
- Permit Issued
- Issued on 12/16/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2018 | QUAN NGHIEM |
| Corrections Issued | 8/10/2018 | QUAN NGHIEM |
| Quality Review Completed | 8/17/2018 | SHAHEN AKELYAN |
| Building Plans Picked Up | 8/24/2018 | APPLICANT |
| Green Plans Picked Up | 8/30/2018 | APPLICANT |
| Applicant returned to address corrections | 6/27/2019 | QUAN NGHIEM |
| Applicant returned to address corrections | 7/5/2019 | QUAN NGHIEM |
| Applicant returned to address corrections | 7/22/2019 | QUAN NGHIEM |
| Plan Check Approved | 7/26/2019 | QUAN NGHIEM |
| Issued | 12/16/2019 | LADBS |
| CofO in Progress | 1/26/2022 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 1/29/2022 | DEROLD HAUFF |
| CofO Issued | 1/29/2022 | DEROLD HAUFF |
| Permit Finaled | 1/29/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2018 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 9/26/2018 | STEVE MELGAR |
| Highway dedication | Cleared | 10/23/2018 | JEANETTE VONG |
| Address approval | Cleared | 6/25/2019 | ELAINE LEI |
| Permit | Cleared | 6/25/2019 | VICTOR MENDOZA |
| Green Code | Cleared | 7/8/2019 | KHEDER ALRAZAA |
| Low Impact Development | Cleared | 7/10/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 7/10/2019 | NGOC KIEM |
| Hydrant and Access approval | Cleared | 7/11/2019 | ROBERT DUFF |
| Miscellaneous | Cleared | 7/12/2019 | ANNA VAN |
| Tract Map conditions | Cleared | 7/12/2019 | ANNA VAN |
Contact Information
| Architect | Maly, Farzin; Lic. No.: C33731 | PO BOX 57002 SHERMAN OAKS, CA 91413 |
| Contractor | Raimondo Construction Company; Lic. No.: 683445-B | 756 BUBBLING WELL DR GLENDORA, CA 91741 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/21/2020 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 5/1/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 5/6/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 5/8/2020 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 5/8/2020 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2020 | Partial Inspection | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/19/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 6/25/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 6/25/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 8/14/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 8/14/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 8/31/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 9/8/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 9/8/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 9/30/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 9/30/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 12/22/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 12/22/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/23/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/4/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 1/4/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 1/4/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 2/25/2021 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 3/9/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 3/11/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 3/12/2021 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 3/17/2021 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/5/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 4/5/2021 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 4/5/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/6/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 4/6/2021 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 4/8/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/9/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/23/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 4/23/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 6/18/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 6/24/2021 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/9/2021 | Approved | ALEJANDRO DE ARTOLA |
| Shower Pan | 9/20/2021 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/6/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Gas Test | 10/12/2021 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 11/24/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/15/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/27/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/28/2021 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/29/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/30/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 1/4/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 1/5/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 1/7/2022 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 1/10/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 1/10/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 1/10/2022 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 1/10/2022 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 1/10/2022 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 1/10/2022 | Approved | ALEJANDRO DE ARTOLA |
| Structural Steel Frame | 1/10/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 1/11/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 1/25/2022 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Service/Power Release | 1/25/2022 | Approved | ALEJANDRO DE ARTOLA |