Excavation/Setback/Form/Re-Bar
|
4/4/2019
|
Partial Approval
|
NICK DANERI
|
|
Green Building Rough
|
4/4/2019
|
Not Ready for Inspection
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
4/4/2019
|
Partial Inspection
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
4/4/2019
|
Not Ready for Inspection
|
NICK DANERI
|
|
Masonry Wall/Backfill
|
4/9/2019
|
Partial Approval
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
5/6/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
5/8/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
5/9/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
5/10/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Green Building Rough
|
5/13/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Reinforced Concrete Frame
|
5/13/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Verify Sprinkler Sign Off
|
5/13/2019
|
Partial Inspection
|
LESLIE TRUJILLO
|
|
Footing/Foundation/Slab
|
5/14/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Piling/Pier/Caisson
|
5/14/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Deputy Shotcrete
|
5/20/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Shotcrete
|
5/21/2019
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Shotcrete
|
5/22/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Shotcrete
|
5/23/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Shotcrete
|
5/24/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Shotcrete
|
5/28/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Footing/Foundation/Slab
|
5/28/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Deputy Shotcrete
|
5/29/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Shotcrete
|
5/30/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
6/17/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Footing/Foundation/Slab
|
6/17/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
6/18/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
6/20/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Footing/Foundation/Slab
|
6/20/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
6/21/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Pre-Stress Concrete
|
7/10/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Pre-Stress Concrete
|
7/11/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Pre-Stress Concrete
|
7/12/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Pre-Stress Concrete
|
7/15/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Pre-Stress Concrete
|
7/16/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Pre-Stress Concrete
|
7/17/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Pre-Stress Concrete
|
7/18/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Deputy Pre-Stress Concrete
|
7/19/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Pre-Stress Concrete
|
7/22/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Pre-Stress Concrete
|
7/23/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Pre-Stress Concrete
|
7/24/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Pre-Stress Concrete
|
7/25/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Pre-Stress Concrete
|
7/26/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Pre-Stress Concrete
|
7/29/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Excavation/Setback/Form/Re-Bar
|
7/29/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Deputy Pre-Stress Concrete
|
7/30/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Concrete
|
7/30/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Deputy Pre-Stress Concrete
|
8/5/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/16/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Masonry Wall/Backfill
|
8/19/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Deputy Reinf. Masonry
|
8/20/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/29/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Deputy Pre-Stress Concrete
|
8/30/2019
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
9/3/2019
|
Conditional Approval
|
LESLIE TRUJILLO
|
|
Footing/Foundation/Slab
|
9/3/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/11/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/7/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/17/2019
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/30/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/6/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Insulation
|
11/6/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Drywall Nailing
|
11/14/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Insulation
|
11/14/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/19/2019
|
Partial Inspection
|
LESLIE TRUJILLO
|
|
Insulation
|
11/19/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Insulation
|
11/26/2019
|
Partial Approval
|
DAVID BURKHEAD
|
|
Wood Frame
|
12/3/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Drywall Nailing
|
12/9/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Insulation
|
12/9/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Wood Frame
|
1/15/2020
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Insulation
|
1/21/2020
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Drywall Nailing
|
1/27/2020
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Insulation
|
1/27/2020
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Wood Frame
|
1/27/2020
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Drywall Nailing
|
1/30/2020
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Insulation
|
1/30/2020
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Wood Frame
|
1/30/2020
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Insulation
|
2/4/2020
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Drywall Nailing
|
2/6/2020
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Insulation
|
2/12/2020
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Interior/Exterior Lathing
|
2/12/2020
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Light Gage Steel Frame
|
4/6/2020
|
Not Ready for Inspection
|
LESLIE TRUJILLO
|
|
Light Gage Steel Frame
|
4/14/2020
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Insulation
|
4/23/2020
|
Approved
|
LESLIE TRUJILLO
|
|
Drywall Nailing
|
5/5/2020
|
Approved
|
JONATHAN QUACH
|
|
Footing/Foundation/Slab
|
6/17/2020
|
Partial Approval
|
NICK DANERI
|
|
T-Bar Ceiling
|
7/10/2020
|
Partial Approval
|
NICK DANERI
|
|
SGSOV-Seismic Gas S/O Valve
|
8/11/2020
|
SGSOV Approved
|
RAFAEL ESPINOZA
|
|
Special/Order Compliance
|
8/25/2020
|
Partial Approval
|
NICK DANERI
|
|
Final
|
9/18/2020
|
Not Ready for Inspection
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
9/18/2020
|
Approved
|
NICK DANERI
|
|
Green Building Final
|
9/18/2020
|
Not Ready for Inspection
|
NICK DANERI
|
|
Green Building Rough
|
9/18/2020
|
Approved
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
9/18/2020
|
Not Ready for Inspection
|
NICK DANERI
|
|
Reinforced Masonry Frame
|
9/18/2020
|
Not Ready for Inspection
|
NICK DANERI
|
|
Smoke Detectors
|
9/18/2020
|
Approved
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
9/18/2020
|
Not Ready for Inspection
|
NICK DANERI
|
|
Special/Order Compliance
|
9/21/2020
|
Conditional Approval
|
NICK DANERI
|
|
Final
|
9/23/2020
|
Not Ready for Inspection
|
NICK DANERI
|
|
Green Building Final
|
9/23/2020
|
Approved
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
9/23/2020
|
Partial Inspection
|
NICK DANERI
|
|
Reinforced Masonry Frame
|
9/23/2020
|
Partial Inspection
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
9/23/2020
|
Not Ready for Inspection
|
NICK DANERI
|
|
Final
|
9/29/2020
|
Conditional Approval
|
NICK DANERI
|
|
Reinforced Concrete Frame
|
9/29/2020
|
Approved
|
NICK DANERI
|
|
Reinforced Masonry Frame
|
9/29/2020
|
Approved
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
9/29/2020
|
Approved
|
NICK DANERI
|