1606-1608 N LEMOYNE ST 90026
Certificate Information: 1606-1608 N LEMOYNE ST 90026
- Application / Permit
- 18010-10000-03795
- Plan Check / Job No.
- B18LA15849
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- New 2-story duplex with 4-car garage basement and storage.
- Permit Issued
- Issued on 2/11/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/31/2018 | APPLICANT |
| Green Plans Picked Up | 9/5/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2018 | HELEN NGUYEN |
| Corrections Issued | 9/25/2018 | HELEN NGUYEN |
| Quality Review Completed | 10/16/2018 | BILL STUTSMAN |
| Building Plans Picked Up | 11/8/2018 | APPLICANT |
| Applicant returned to address corrections | 1/15/2019 | HELEN NGUYEN |
| Applicant returned to address corrections | 2/8/2019 | HELEN NGUYEN |
| Applicant returned to address corrections | 4/11/2019 | HELEN NGUYEN |
| Applicant returned to address corrections | 5/10/2019 | HELEN NGUYEN |
| Applicant returned to address corrections | 5/24/2019 | HELEN NGUYEN |
| Applicant returned to address corrections | 7/16/2019 | HELEN NGUYEN |
| Applicant returned to address corrections | 7/25/2019 | HELEN NGUYEN |
| Plan Check Approved | 2/11/2020 | HELEN NGUYEN |
| Issued | 2/11/2020 | LADBS |
| CofO in Progress | 12/29/2023 | THOMAS LOGRASSO |
| Permit Finaled | 12/30/2023 | DEROLD HAUFF |
| CofO Issued | 12/30/2023 | DEROLD HAUFF |
| Permit Finaled | 12/30/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/29/2018 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/29/2018 | JEANETTE VONG |
| Permit | Cleared | 11/29/2018 | JEANETTE VONG |
| Sewer availability | Cleared | 11/29/2018 | JEANETTE VONG |
| Trees in Parkway | Cleared | 11/29/2018 | JOEL HERNANDEZ |
| Hydrant and Access approval | Cleared | 12/7/2018 | JOHN CONNEALLY |
| Green Code | Cleared | 12/18/2018 | COLIN LOREDO |
| Low Impact Development | Cleared | 3/26/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 3/26/2019 | KAREN LE |
| Grading Pre-Inspection | Cleared | 7/26/2019 | HELEN NGUYEN |
Contact Information
| Architect | Lu,, Alan S; Lic. No.: C34631 | 2125 SCOTT AVENUE LOS ANGELES, CA 90026 |
| Contractor | Murrieta General Construction Inc; Lic. No.: 939792-B | 17450 DEERFIELD AVE BELLFLOWER, CA 90706 |
| Engineer | , ; Lic. No.: S4029 | 17 SANTA EUGENIA IRVINE, CA 92606 |
| Engineer | Aoanan,, Virgilio Cendana; Lic. No.: C36079 | 1041 S GARFIELD AVE STE #210 ALHAMBRA, CA 91801 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/7/2020 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 10/9/2020 | Partial Approval | OSVALDO PARAMO |
| Masonry Wall/Backfill | 10/26/2020 | Corrections Issued | SCOTT FINNILA |
| Masonry Wall/Backfill | 11/2/2020 | Corrections Issued | SCOTT FINNILA |
| Masonry Wall/Backfill | 11/10/2020 | Corrections Issued | STUART CHAPMAN |
| Masonry Wall/Backfill | 11/16/2020 | Partial Approval | ROBERT VORHIS |
| Deputy Reinf. Masonry | 11/24/2020 | No Access for Inspection | ELMER BLAND |
| Masonry Wall/Backfill | 12/4/2020 | Partial Inspection | SCOTT FINNILA |
| Masonry Wall/Backfill | 12/7/2020 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Masonry | 12/21/2020 | Partial Approval | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 2/16/2021 | Corrections Issued | COREY HUPP |
| Deputy Reinf. Masonry | 2/26/2021 | Conditional Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 3/4/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Footing/Foundation/Slab | 3/4/2021 | Partial Inspection | ROBERT VORHIS |
| Masonry Wall/Backfill | 3/4/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Footing/Foundation/Slab | 3/10/2021 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 3/10/2021 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 3/16/2021 | Partial Approval | RUBEN SALAS |
| Masonry Wall/Backfill | 3/22/2021 | Partial Approval | STUART CHAPMAN |
| Deputy Reinf. Masonry | 3/26/2021 | Conditional Approval | STUART CHAPMAN |
| Masonry Wall/Backfill | 3/31/2021 | Partial Approval | STUART CHAPMAN |
| Deputy Reinf. Masonry | 4/1/2021 | No Access for Inspection | ELMER BLAND |
| Deputy Reinf. Masonry | 4/6/2021 | Approved | STUART CHAPMAN |
| Masonry Wall/Backfill | 4/9/2021 | Partial Approval | JOSEPH MCGARRY |
| Masonry Wall/Backfill | 4/19/2021 | Partial Approval | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 4/30/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Underground Mechanical | 4/30/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 5/12/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Underground Mechanical | 5/12/2021 | Partial Approval | ROBERT VORHIS |
| Masonry Wall/Backfill | 5/17/2021 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 5/18/2021 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2021 | Partial Approval | CRAIG VAUGHAN |
| Special/Order Compliance | 6/25/2021 | Partial Inspection | ROBERT VORHIS |
| Deputy Wood Construction | 7/8/2021 | Partial Approval | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2021 | Partial Approval | JUSTIN CURTIS |
| Special/Order Compliance | 11/3/2021 | Corrections Issued | RUBEN SALAS |
| PLUMBING-Rough | 2/11/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 2/16/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/16/2022 | Partial Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/22/2022 | Partial Approval | THOMAS LOGRASSO |
| Deputy Shotcrete | 3/23/2022 | Approved | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 4/27/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/10/2022 | Corrections Issued | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 6/30/2022 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/8/2022 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2022 | Conditional Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 9/16/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 9/16/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Pre-Inspection | 9/16/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 9/21/2022 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 9/21/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 9/26/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 9/26/2022 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 9/26/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 10/21/2022 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/2/2022 | Corrections Issued | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 11/2/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 11/14/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Wood Frame | 11/14/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/5/2022 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 12/5/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 12/5/2022 | Corrections Issued | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 12/5/2022 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 12/9/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Drywall Nailing | 12/19/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 12/19/2022 | Approved | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 4/25/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 5/1/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 5/4/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/4/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 5/6/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 5/9/2023 | Partial Approval | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 5/10/2023 | Conditional Approval | THOMAS LOGRASSO |
| Masonry Wall/Backfill | 5/15/2023 | Partial Approval | THOMAS LOGRASSO |
| Masonry Wall/Backfill | 5/17/2023 | Not Ready for Inspection | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 5/25/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/25/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 6/21/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Underground Mechanical | 8/1/2023 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 8/21/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Service/Power Release | 8/21/2023 | No Access for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 8/22/2023 | Partial Inspection | FREDDIE RIVERA |
| Service/Power Release | 8/22/2023 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Final | 8/24/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Service/Power Release | 8/24/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Final | 9/5/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Gas Test | 9/5/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Final | 9/5/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Final | 9/5/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Final | 9/8/2023 | Approved | THOMAS LOGRASSO |
| Service/Power Release | 9/8/2023 | Approved | THOMAS LOGRASSO |
| HVAC-Final | 9/15/2023 | Approved | THOMAS LOGRASSO |
| PLUMBING-Final | 9/15/2023 | Corrections Issued | THOMAS LOGRASSO |
| Gas Test | 9/22/2023 | Approved | THOMAS LOGRASSO |
| PLUMBING-Final | 9/22/2023 | Approved | THOMAS LOGRASSO |
| Final | 12/20/2023 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/20/2023 | Approved | THOMAS LOGRASSO |
| Green Building Final | 12/20/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Reinforced Masonry Frame | 12/20/2023 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 12/20/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 12/20/2023 | Approved | THOMAS LOGRASSO |
| Final | 12/27/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 12/27/2023 | Approved | THOMAS LOGRASSO |
| Final | 12/29/2023 | OK to Issue CofO | THOMAS LOGRASSO |