5114 E MERIDIAN ST 90042

Certificate Information: 5114 E MERIDIAN ST 90042

Application / Permit
18010-10000-03769
Plan Check / Job No.
B18LA15720
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2 STORY ADU 1,200 S.F. PER AB494 AND SB229
Permit Issued
Issued on 1/24/2020
Issuing Office
Metro
Current Status
CofO Issued on 1/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2018 APPLICANT
Assigned to Plan Check Engineer 9/7/2018 ANA AVELAR
Corrections Issued 9/12/2018 ANA AVELAR
Quality Review Completed 9/24/2018 KESETE HAREGOT
Building Plans Picked Up 10/9/2018 APPLICANT
Green Plans Picked Up 10/9/2018 APPLICANT
Applicant returned to address corrections 8/8/2019 RAHEL BEYENE
Applicant returned to address corrections 12/6/2019 RAHEL BEYENE
Plan Check Approved 1/17/2020 RAHEL BEYENE
Issued 1/24/2020 LADBS
CofO in Progress 11/19/2021 CRAIG VAUGHAN
Permit Finaled 1/10/2022 DEROLD HAUFF
CofO Issued 1/10/2022 DEROLD HAUFF
Permit Finaled 1/10/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/27/2018 KARAN PATEL
Eng Process Fee Ord 176,300 Cleared 11/27/2018 KARAN PATEL
Sewer availability Cleared 11/27/2018 KARAN PATEL
Hydrant and Access approval Cleared 11/30/2018 JOHN CONNEALLY
Low Impact Development Cleared 3/22/2019 SARAH YOUSSEF
"Q" conditions Cleared 5/1/2019 LATANYA ROUX
Green Code Cleared 11/4/2019 KHEDER ALRAZAA
GPI Written Notices Cleared 12/6/2019 ANA AVELAR
Grading Pre-Inspection Cleared 12/6/2019 RAHEL BEYENE
Roof/Waste drainage to street Cleared 12/9/2019 JEANIE LAM

Contact Information

Contractor American Tech Construction; Lic. No.: 662300-B 9468 GUESS ST      ROSEMEAD, CA 91770
Engineer Chan, Terence Ka-Hing; Lic. No.: C48893 560 W MAIN STREET C 278      ALHAMBRA, CA 91801

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 8/7/2020 Partial Inspection CRAIG VAUGHAN
PLUMBING-Rough 9/17/2020 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 9/28/2020 Corrections Issued CRAIG VAUGHAN
Sewer 9/28/2020 Approved CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 10/2/2020 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 10/13/2020 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 10/22/2020 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 10/30/2020 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 2/1/2021 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 2/1/2021 Partial Approval CRAIG VAUGHAN
HVAC-Rough 2/1/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 2/1/2021 Approved CRAIG VAUGHAN
Underground Mechanical 2/1/2021 Partial Inspection CRAIG VAUGHAN
Wood Frame 2/1/2021 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 2/5/2021 Approved COREY HUPP
Wood Frame 2/5/2021 Approved COREY HUPP
Insulation 2/24/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 2/24/2021 Partial Approval OSVALDO PARAMO
Drywall Nailing 3/11/2021 Approved OSVALDO PARAMO
Green Building Rough 3/11/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 3/26/2021 Approved CRAIG VAUGHAN
Shower Pan 4/6/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Final 8/13/2021 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Final 8/13/2021 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Final 8/13/2021 Not Ready for Inspection CRAIG VAUGHAN
Service/Power Release 8/13/2021 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 11/3/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Final 11/3/2021 Corrections Issued CRAIG VAUGHAN
Final 11/3/2021 Corrections Issued CRAIG VAUGHAN
Gas Test 11/3/2021 Approved CRAIG VAUGHAN
Green Building Final 11/3/2021 Approved CRAIG VAUGHAN
HVAC-Final 11/3/2021 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 11/3/2021 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 11/3/2021 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 11/3/2021 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 11/3/2021 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 11/3/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Final 11/18/2021 Approved CRAIG VAUGHAN
Final 11/18/2021 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 11/18/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 11/18/2021 Approved CRAIG VAUGHAN
Service/Power Release 11/18/2021 Approved CRAIG VAUGHAN