459 S HARTFORD AVE 90017

Certificate Information: 459 S HARTFORD AVE 90017

Application / Permit
18010-10000-03723
Plan Check / Job No.
B18LA15398
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
PROPOSED 7 STORY, 101 UNIT AFFORDABLE APARTMENT (100 VERY LOW INCOME UNITS) OVER 1 LEVEL OF PARKING. TYPE IIIA OVER TYPE IA. PARKING IS BASED ON AB 744 (.3 SPACES PER UNIT)
Permit Issued
Issued on 12/7/2018
Issuing Office
Metro
Current Status
CofO Issued on 5/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/1/2018 APPLICANT
Assigned to Plan Check Engineer 8/29/2018 JOHN VASQUEZ
Corrections Issued 9/6/2018 JOHN VASQUEZ
Quality Review Completed 9/11/2018 CHARLES CHANG
Building Plans Picked Up 9/11/2018 APPLICANT
Applicant returned to address corrections 10/31/2018 JOHN VASQUEZ
Applicant returned to address corrections 11/14/2018 JOHN VASQUEZ
Applicant returned to address corrections 11/20/2018 JOHN VASQUEZ
Applicant returned to address corrections 11/29/2018 JOHN VASQUEZ
Plan Check Approved 12/6/2018 JOHN VASQUEZ
Issued 12/7/2018 LADBS
TCO Issued (Expire Date: 05-01-2022) 11/2/2021 ERNESTO CORRAL
CofO in Progress 4/29/2022 RAFAEL ESPINOZA
Permit Finaled 5/2/2022 ERNESTO CORRAL
CofO Issued 5/2/2022 ERNESTO CORRAL
Permit Finaled 5/2/2022 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 9/19/2018 ADOLFO GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 10/19/2018 NAZILA NOORIFAR
Permit Cleared 10/19/2018 NAZILA NOORIFAR
Sewer availability Cleared 10/19/2018 NAZILA NOORIFAR
Highway dedication Cleared 10/31/2018 KARAN PATEL
Hydrant and Access approval Cleared 10/31/2018 GEORGE SUCHAND
Green Code Cleared 11/9/2018 DONALD CRICHLOW
GPI Written Notices Cleared 11/14/2018 JOHN VASQUEZ
Grading Pre-Inspection Cleared 11/14/2018 JOHN VASQUEZ
DCP conditions approval Cleared 11/27/2018 KENNETH LE
Density Bonus 12.22.A.25 Cleared 11/27/2018 KENNETH LE
Driveway location Cleared 11/29/2018 MOHAMMAD HASAN
Fire Marshall Fire Life Safety Cleared 11/29/2018 VIDAL GARCIA
Miscellaneous Cleared 11/29/2018 VIDAL GARCIA
Specific Plan Cleared 11/29/2018 MOHAMMAD HASAN
Trees in Parkway Cleared 11/30/2018 ADRIAN SANCHEZ
Work Adjacent to Public Way Cleared 11/30/2018 TERRY PHAN
Building over 3-story or 36-ft Cleared 12/3/2018 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 12/3/2018 CALOSHA APPROVED
DAS Clearance Cleared 12/4/2018 JOHN VASQUEZ
Haul Route Cleared 12/4/2018 JOHN VASQUEZ
Low Impact Development Cleared 12/4/2018 RYAN HUDSON
Stormwater Pollution Mitigatn Cleared 12/4/2018 IDA MEISAMI-FARD
Frnt yard landscape/Water mgmt Cleared 12/5/2018 ULISES GONZALEZ
Miscellaneous Cleared 12/5/2018 ULISES GONZALEZ
Miscellaneous Cleared 12/5/2018 ULISES GONZALEZ
Miscellaneous Cleared 12/5/2018 ULISES GONZALEZ
Opn space landscape/Water mgmt Cleared 12/5/2018 ULISES GONZALEZ
Roof/Waste drainage to street Cleared 12/5/2018 NAZILA NOORIFAR
Site Plan review Cleared 12/5/2018 ULISES GONZALEZ
Specific Plan Cleared 12/5/2018 ULISES GONZALEZ
Miscellaneous Cleared 12/6/2018 ULISES GONZALEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 3/15/2019 Approved ERNESTO CORRAL
Pre-Inspection 3/15/2019 Approved ERNESTO CORRAL
Deputy Steel/Welding 5/22/2019 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 5/23/2019 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 5/23/2019 Partial Inspection ERNESTO CORRAL
Masonry Wall/Backfill 6/27/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 6/28/2019 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 7/1/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 7/2/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 7/3/2019 Conditional Approval ERNESTO CORRAL
Masonry Wall/Backfill 7/3/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Masonry 7/5/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 11/7/2019 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 11/7/2019 Partial Inspection ERNESTO CORRAL
Footing/Foundation/Slab 11/7/2019 Partial Inspection ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 11/8/2019 Not Ready for Inspection ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 11/15/2019 Partial Inspection ERNESTO CORRAL
Footing/Foundation/Slab 11/15/2019 Partial Inspection ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 11/18/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 11/19/2019 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 11/19/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 12/3/2019 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 12/3/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 12/4/2019 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 12/4/2019 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 12/5/2019 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 12/6/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 12/17/2019 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 12/17/2019 Not Ready for Inspection ERNESTO CORRAL
Footing/Foundation/Slab 12/17/2019 Not Ready for Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 12/18/2019 Conditional Approval ERNESTO CORRAL
Green Building Rough 12/18/2019 Approved ERNESTO CORRAL
Reinforced Concrete Frame 12/18/2019 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 12/18/2019 Not Ready for Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 12/19/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 12/20/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 1/6/2020 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 1/6/2020 Partial Inspection ERNESTO CORRAL
Footing/Foundation/Slab 1/6/2020 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 1/8/2020 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 1/9/2020 Partial Inspection ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 1/10/2020 Partial Inspection ERNESTO CORRAL
Deputy Shotcrete 1/14/2020 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 1/15/2020 Not Ready for Inspection ERNESTO CORRAL
Reinforced Concrete Frame 1/16/2020 Partial Inspection ERNESTO CORRAL
Verify Sprinkler Sign Off 1/16/2020 Not Ready for Inspection ERNESTO CORRAL
Deputy Shotcrete 1/21/2020 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 1/22/2020 Partial Inspection ERNESTO CORRAL
Pre-Inspection 1/23/2020 Partial Inspection ERNESTO CORRAL
Deputy Shotcrete 1/27/2020 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 2/19/2020 Partial Inspection ERNESTO CORRAL
Footing/Foundation/Slab 2/19/2020 Partial Inspection ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 3/2/2020 Partial Inspection ERNESTO CORRAL
Footing/Foundation/Slab 3/2/2020 Partial Inspection ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 3/26/2020 Partial Inspection ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 3/31/2020 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 4/1/2020 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 4/2/2020 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 4/20/2020 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 4/20/2020 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/21/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/22/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/23/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/27/2020 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 4/28/2020 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 4/28/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/29/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/30/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/1/2020 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 5/7/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/14/2020 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 5/14/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/15/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/18/2020 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 5/18/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/19/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 6/17/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 6/18/2020 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 6/18/2020 Partial Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 6/19/2020 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 6/29/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Masonry 6/30/2020 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 7/2/2020 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/7/2020 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/8/2020 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 7/9/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/10/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 7/13/2020 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 7/13/2020 Partial Approval RAFAEL ESPINOZA
Reinforced Masonry Frame 7/13/2020 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 7/20/2020 Partial Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 7/22/2020 Partial Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 8/5/2020 Partial Approval RAFAEL ESPINOZA
Reinforced Masonry Frame 8/11/2020 Partial Approval RAFAEL ESPINOZA
Verify Sprinkler Sign Off 8/11/2020 Not Ready for Inspection RAFAEL ESPINOZA
Masonry Wall/Backfill 8/17/2020 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 8/18/2020 Partial Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 8/20/2020 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 8/26/2020 Partial Approval DANIEL COLLINS
Reinforced Concrete Frame 9/3/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/5/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/6/2020 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Wood Construction 10/8/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/8/2020 Partial Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 10/20/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/20/2020 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 10/21/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/26/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/9/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/10/2020 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/13/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/17/2020 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/19/2020 Partial Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 11/19/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 11/20/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 12/1/2020 Partial Approval RAFAEL ESPINOZA
Wood Frame 12/1/2020 Corrections Issued RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/4/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/7/2020 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 12/9/2020 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 12/9/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/10/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/17/2020 Partial Approval RAFAEL ESPINOZA
Insulation 12/17/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/21/2020 Corrections Issued RAFAEL ESPINOZA
Insulation 12/21/2020 No Access for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/23/2020 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 12/29/2020 Partial Approval RAFAEL ESPINOZA
Wood Frame 1/4/2021 Conditional Approval RAFAEL ESPINOZA
Insulation 1/5/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 1/11/2021 Conditional Approval RAFAEL ESPINOZA
Wood Frame 2/5/2021 Partial Approval RAFAEL ESPINOZA
Insulation 2/9/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/10/2021 Partial Approval RAFAEL ESPINOZA
Insulation 2/10/2021 Partial Approval RAFAEL ESPINOZA
Wood Frame 2/10/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 2/12/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 2/16/2021 Partial Approval RAFAEL ESPINOZA
Insulation 2/16/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 2/19/2021 Partial Approval NICK DANERI
Insulation 2/23/2021 Partial Approval RAFAEL ESPINOZA
Insulation 2/25/2021 Partial Approval RAFAEL ESPINOZA
Wood Frame 2/25/2021 Partial Approval RAFAEL ESPINOZA
Insulation 2/26/2021 Partial Approval NICK DANERI
Insulation 3/1/2021 Partial Approval RAFAEL ESPINOZA
Wood Frame 3/1/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 3/2/2021 Partial Approval RAFAEL ESPINOZA
Wood Frame 3/2/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/3/2021 Partial Approval RAFAEL ESPINOZA
Insulation 3/3/2021 Partial Approval RAFAEL ESPINOZA
Insulation 3/5/2021 Partial Approval RAFAEL ESPINOZA
Insulation 3/8/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 3/10/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 3/11/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 3/15/2021 Partial Approval RAFAEL ESPINOZA
Insulation 3/15/2021 Partial Approval RAFAEL ESPINOZA
Insulation 3/17/2021 Not Ready for Inspection RAFAEL ESPINOZA
Insulation 3/18/2021 Partial Approval RAFAEL ESPINOZA
Insulation 3/19/2021 Partial Approval NICK DANERI
Drywall Nailing 3/22/2021 Not Ready for Inspection RAFAEL ESPINOZA
Interior/Exterior Lathing 3/22/2021 Partial Approval RAFAEL ESPINOZA
Insulation 3/24/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 3/26/2021 Partial Approval NICK DANERI
Light Gage Steel Frame 3/26/2021 Partial Approval NICK DANERI
Drywall Nailing 3/31/2021 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 4/1/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/12/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 4/12/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 4/16/2021 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 4/16/2021 Partial Approval JONATHAN QUACH
Drywall Nailing 4/22/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 4/22/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 4/28/2021 Not Ready for Inspection RAFAEL ESPINOZA
Special/Order Compliance 4/29/2021 Not Ready for Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 5/12/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 5/24/2021 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 6/2/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 6/11/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 6/18/2021 Partial Approval RAFAEL ESPINOZA
Wood Frame 6/25/2021 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 7/9/2021 Approved RAFAEL ESPINOZA
T-Bar Ceiling 7/22/2021 Not Ready for Inspection JONATHAN QUACH
T-Bar Ceiling 7/29/2021 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 8/24/2021 Approved RAFAEL ESPINOZA
Special/Order Compliance 8/24/2021 Partial Inspection RAFAEL ESPINOZA
Final 9/21/2021 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 9/21/2021 Approved RAFAEL ESPINOZA
Green Building Final 9/21/2021 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 9/21/2021 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 9/21/2021 Not Ready for Inspection RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 9/21/2021 SGSOV Not Ready RAFAEL ESPINOZA
SUSMP-Std. Urban Storm Water 9/21/2021 Not Ready for Inspection RAFAEL ESPINOZA
Smoke Detectors 9/21/2021 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 9/21/2021 Not Ready for Inspection RAFAEL ESPINOZA
Special/Order Compliance 10/4/2021 Partial Approval RAFAEL ESPINOZA
Special/Order Compliance 10/15/2021 Approved RAFAEL ESPINOZA
Final 10/27/2021 Partial Inspection RAFAEL ESPINOZA
Green Building Final 10/27/2021 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Concrete Frame 10/27/2021 Approved RAFAEL ESPINOZA
Reinforced Masonry Frame 10/27/2021 Approved RAFAEL ESPINOZA
SGSOV-Seismic Gas S/O Valve 10/27/2021 SGSOV Approved RAFAEL ESPINOZA
SUSMP-Std. Urban Storm Water 10/27/2021 Approved RAFAEL ESPINOZA
Smoke Detectors 10/27/2021 Not Ready for Inspection RAFAEL ESPINOZA
Verify Sprinkler Sign Off 10/27/2021 Approved RAFAEL ESPINOZA
Special/Order Compliance 4/6/2022 Partial Inspection RAFAEL ESPINOZA
Final 4/29/2022 OK to Issue CofO RAFAEL ESPINOZA
Green Building Final 4/29/2022 Approved RAFAEL ESPINOZA
Smoke Detectors 4/29/2022 Approved RAFAEL ESPINOZA