856 S GRAMERCY DR 90005

Certificate Information: 856 S GRAMERCY DR 90005

Application / Permit
18010-10000-03680
Plan Check / Job No.
B18LA14989
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
PROPOSED 53 UNIT TOC (TIER 3) AFFORDABLE HOUSING PROJECT, 5 STORY TYPE III-A FULLY SPRINKLERED (NFPA-13) OVER 1 LEVEL R2 RESIDENTIAL AND 1 LEVEL TYPE 1-A BASEMENT PARKING.
Permit Issued
Issued on 5/23/2022
Issuing Office
Metro
Current Status
Issued on 5/23/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/24/2018 APPLICANT
Assigned to Plan Check Engineer 8/23/2018 JOHN VASQUEZ
Corrections Issued 8/30/2018 JOHN VASQUEZ
Quality Review Completed 9/4/2018 CHARLES CHANG
Building Plans Picked Up 9/4/2018 APPLICANT
Applicant returned to address corrections 3/5/2020 JOHN VASQUEZ
Applicant returned to address corrections 3/26/2020 JOHN VASQUEZ
Applicant returned to address corrections 4/29/2020 JOHN VASQUEZ
Applicant returned to address corrections 5/13/2020 JOHN VASQUEZ
Applicant returned to address corrections 5/19/2020 JOHN VASQUEZ
Applicant returned to address corrections 5/29/2020 JOHN VASQUEZ
Applicant returned to address corrections 6/4/2020 JOHN VASQUEZ
Applicant returned to address corrections 6/8/2020 JOHN VASQUEZ
Applicant returned to address corrections 2/4/2021 LARRY LEE
Applicant returned to address corrections 7/13/2021 LARRY LEE
Applicant returned to address corrections 10/19/2021 LARRY LEE
Plan Check Approved 1/26/2022 LARRY LEE
Issued 5/23/2022 APPLICANT

Permit Application Clearance Information

Driveway location Cleared 10/29/2018 JOHNATHAN YU
Highway dedication Cleared 10/29/2018 MICHAEL CASTILLO
Internal circulation Cleared 10/29/2018 JOHNATHAN YU
Address approval Cleared 1/24/2019 ERIK BEASLEY
Permit Cleared 3/15/2019 ELAINE LEI
Work Adjacent to Public Way Cleared 4/17/2019 TERRY PHAN
Trees in Parkway Cleared 9/6/2019 ADRIAN SANCHEZ
DCP conditions approval Cleared 9/26/2019 MICHAEL ZIRBES
Density Bonus 12.22.A.31 Cleared 9/26/2019 MICHAEL ZIRBES
Eng Process Fee Ord 176,300 Cleared 10/3/2019 ERIK BEASLEY
Sewer availability Cleared 10/3/2019 ERIK BEASLEY
Frnt yard landscape/Water mgmt Cleared 10/8/2019 ANNA VAN
Miscellaneous Cleared 10/8/2019 ANNA VAN
Miscellaneous Cleared 10/8/2019 ANNA VAN
Opn space landscape/Water mgmt Cleared 10/8/2019 ANNA VAN
Site Plan review Cleared 10/8/2019 ANNA VAN
Low Impact Development Cleared 1/14/2020 JORGE MEJIA LEMUS
Stormwater Pollution Mitigatn Cleared 1/14/2020 JORGE MEJIA LEMUS
Green Code Cleared 11/30/2020 DONALD CRICHLOW
Fire Marshall Fire Life Safety Cleared 3/23/2021 MENOA AGHAJANI
Hydrant and Access approval Cleared 5/10/2021 MATTHEW CRAIG
DAS Clearance Cleared 6/2/2021 JOHN VASQUEZ
Building over 3-story or 36-ft Cleared 7/12/2021 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 7/12/2021 CALOSHA APPROVED
Roof/Waste drainage to street Cleared 7/14/2021 CECILIO NAVARRO
Bicycle Parking Cleared 7/22/2021 MSTAFA AL-MSARI

Contact Information

Architect Kudelka, Phillip Roman; Lic. No.: C19548 PK ARCHITECTURE   22663 COLLINS ST    WOODLAND HILLS, CA 913674433
Contractor Owner-Builder       ,

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 12/28/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 1/24/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 1/24/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 1/26/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 1/31/2023 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 1/31/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 2/1/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 2/2/2023 Partial Approval EDWIN GREGORYONA
Green Building Rough 2/2/2023 Not Ready for Inspection EDWIN GREGORYONA
Masonry Wall/Backfill 2/2/2023 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 2/2/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 2/8/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 2/8/2023 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 2/8/2023 Partial Approval EDWIN GREGORYONA
Reinforced Concrete Frame 2/8/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 2/9/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 2/9/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 2/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 2/14/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 2/15/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 2/16/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 2/16/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 2/17/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 4/10/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 5/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/19/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 5/24/2023 Partial Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 6/2/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 6/6/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 6/13/2023 Conditional Approval MICHAEL ROSENBERG
Pre-Inspection 6/16/2023 Partial Approval EDWIN GREGORYONA
Pre-Inspection 6/21/2023 Partial Inspection GREGORY POMISH
Masonry Wall/Backfill 7/6/2023 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 7/13/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 7/13/2023 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 7/21/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/3/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 8/11/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 8/14/2023 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 8/14/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 8/28/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 8/31/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 9/12/2023 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 9/13/2023 Not Ready for Inspection GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 9/21/2023 Partial Approval EDWIN GREGORYONA
Wood Frame 9/21/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 10/5/2023 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 10/5/2023 Not Ready for Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 10/10/2023 Not Ready for Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 10/10/2023 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 10/10/2023 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 10/10/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Drilled-In Anchors 10/12/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 10/12/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 10/31/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 11/2/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 11/3/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/3/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 11/9/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/22/2023 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 11/22/2023 Not Ready for Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/27/2023 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 11/30/2023 Partial Approval GREGORY POMISH
Drywall Nailing 12/1/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 12/5/2023 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 12/15/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 1/2/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 1/8/2024 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 1/17/2024 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 1/18/2024 Conditional Approval ALFREDO LOPEZ
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Partial Approval ALFREDO LOPEZ
Wood Frame 1/18/2024 Partial Inspection ALFREDO LOPEZ
Deputy Wood Construction 1/19/2024 No Access for Inspection MICHAEL ROSENBERG
Deputy Wood Construction 1/23/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 1/23/2024 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 1/24/2024 No Access for Inspection MICHAEL ROSENBERG
Deputy Wood Construction 1/25/2024 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 1/26/2024 No Access for Inspection MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 2/9/2024 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 2/15/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 2/15/2024 Partial Inspection EDWIN GREGORYONA
Deputy Wood Construction 2/16/2024 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 2/23/2024 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 3/14/2024 Partial Inspection EDWIN GREGORYONA
Wood Frame 4/9/2024 Partial Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 4/18/2024 Not Ready for Inspection EDWIN GREGORYONA
Insulation 4/18/2024 Partial Approval EDWIN GREGORYONA
Insulation 5/7/2024 Not Ready for Inspection EDWIN GREGORYONA
Insulation 5/8/2024 Partial Approval EDWIN GREGORYONA
Insulation 5/15/2024 Partial Approval EDWIN GREGORYONA
Insulation 5/29/2024 Partial Approval EDWIN GREGORYONA
Wood Frame 7/22/2024 Partial Inspection EDWIN GREGORYONA
Light Gage Steel Frame 7/24/2024 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 7/25/2024 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 7/25/2024 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 7/31/2024 Partial Inspection EDWIN GREGORYONA
Drywall Nailing 8/12/2024 Partial Approval EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 8/12/2024 SGSOV Not Ready EDWIN GREGORYONA
Light Gage Steel Frame 8/14/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 8/19/2024 Partial Approval JACOB MYERS
Insulation 8/19/2024 Partial Approval JACOB MYERS
Drywall Nailing 8/22/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 8/27/2024 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 8/29/2024 Not Ready for Inspection JEROME BLACKWOOD
Drywall Nailing 8/30/2024 Partial Approval MARTIN TAVITIAN
Interior/Exterior Lathing 8/30/2024 Partial Approval MARTIN TAVITIAN
Drywall Nailing 9/5/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 9/9/2024 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 9/13/2024 Partial Approval NICK DANERI
Interior/Exterior Lathing 9/19/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 9/23/2024 Partial Approval MARTIN TAVITIAN
Drywall Nailing 10/1/2024 Partial Approval EDWIN GREGORYONA
Insulation 10/7/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 10/15/2024 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 10/15/2024 Not Ready for Inspection EDWIN GREGORYONA
Light Gage Steel Frame 10/16/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 10/29/2024 Partial Approval EDWIN GREGORYONA
Interior/Exterior Lathing 10/29/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 11/5/2024 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 11/19/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 12/2/2024 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 1/13/2025 Not Ready for Inspection EDWIN GREGORYONA
Special/Order Compliance 9/30/2025 Approved EDWIN GREGORYONA
Special/Order Compliance 10/24/2025 Corrections Issued EDWIN GREGORYONA
Pre-Inspection 4/20/2026 Approved MARTIN TAVITIAN