3405 N SIERRA ST 90031
Certificate Information: 3405 N SIERRA ST 90031
- Application / Permit
- 18010-10000-03667
- Plan Check / Job No.
- B18LA14896
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING OVER BASEMENT WITH ATTACHED 2 CAR GARAGE **1 OF 4**
- Permit Issued
- Issued on 6/1/2022
- Issuing Office
- Metro
- Current Status
- Issued on 6/1/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/20/2018 | APPLICANT |
| Green Plans Picked Up | 8/8/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/23/2018 | ZAW HAN |
| Corrections Issued | 9/6/2018 | ZAW HAN |
| Quality Review Completed | 9/14/2018 | HERNAN ARREOLA |
| Building Plans Picked Up | 9/19/2018 | APPLICANT |
| Applicant returned to address corrections | 10/24/2018 | ZAW HAN |
| Applicant returned to address corrections | 3/22/2019 | ZAW HAN |
| Applicant returned to address corrections | 12/24/2019 | ZAW HAN |
| Applicant returned to address corrections | 10/8/2020 | ZAW HAN |
| Plan Check Approved | 2/18/2022 | ZAW HAN |
| Issued | 6/1/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/29/2019 | ELAINE LEI |
| BHO/Hillside ordinance | Cleared | 3/29/2019 | ELAINE LEI |
| BHO/Hillside ordinance | Cleared | 3/29/2019 | ELAINE LEI |
| BHO/Hillside ordinance | Cleared | 3/29/2019 | ELAINE LEI |
| Permit | Cleared | 3/29/2019 | ELAINE LEI |
| "D" conditions | Cleared | 12/16/2019 | SOPHIE GABEL-SCHEINBAU |
| "Q" conditions | Cleared | 12/16/2019 | SOPHIE GABEL-SCHEINBAU |
| CPC | Cleared | 12/16/2019 | SOPHIE GABEL-SCHEINBAU |
| Frnt yard landscape/Water mgmt | Cleared | 12/16/2019 | SOPHIE GABEL-SCHEINBAU |
| ZI | Cleared | 12/16/2019 | SOPHIE GABEL-SCHEINBAU |
| Green Code | Cleared | 2/4/2020 | COLIN LOREDO |
| Trees in Parkway | Cleared | 9/2/2020 | JOHN KIM |
| Low Impact Development | Cleared | 11/25/2020 | JORGE MEJIA LEMUS |
| Hydrant and Access approval | Cleared | 8/25/2021 | MATTHEW CRAIG |
| Disturb/Remove Protected Trees | Cleared | 8/31/2021 | STEPHEN DUPREY |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2021 | THOMAS LANG |
| Sewer availability | Cleared | 9/10/2021 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 9/14/2021 | THOMAS LANG |
| Excavation more than 5-ft deep | Cleared | 2/18/2022 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 2/18/2022 | TIMOTHY POWELL |
| Grading Pre-Inspection | Cleared | 2/18/2022 | TIMOTHY POWELL |
Contact Information
| Contractor | Yu Minghai; Lic. No.: 1024904-B | 15531 FACILIDAD ST HACIENDA HEIGHTS, CA 91745 |
| Engineer | Lee, Jack C; Lic. No.: C40870 | 576 E LAMBERT RD BREA, CA 92821 |
| Engineer | Lee, Jack C; Lic. No.: GE2153 | 576 E LAMBERT RD BREA, CA 92821 |
| Engineer | Song,, Jiansheng; Lic. No.: C71849 | 18728 BLOOMFIELD AVENUE CERRITOS, CA 90703 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 12/2/2022 | Corrections Issued | OSVALDO PARAMO |
| Pre-Inspection | 12/2/2022 | Approved | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 4/27/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Piling/Pier/Caisson | 4/27/2023 | Corrections Issued | OSVALDO PARAMO |
| Deputy Grading | 4/29/2024 | Conditional Approval | OSVALDO PARAMO |
| Deputy Grading | 4/30/2024 | Conditional Approval | OSVALDO PARAMO |
| Piling/Pier/Caisson | 5/3/2024 | Corrections Issued | OSVALDO PARAMO |
| Piling/Pier/Caisson | 5/20/2024 | Partial Approval | OSVALDO PARAMO |
| Piling/Pier/Caisson | 8/6/2024 | Approved | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 11/27/2024 | Partial Approval | WILLIAM SIERRA |
| Footing/Foundation/Slab | 11/27/2024 | Partial Approval | WILLIAM SIERRA |
| Footing/Foundation/Slab | 12/11/2024 | Corrections Issued | OSVALDO PARAMO |
| Pre-Inspection | 12/11/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 9/12/2025 | Partial Inspection | FREDDIE RIVERA |
| Green Building Rough | 9/12/2025 | Partial Inspection | FREDDIE RIVERA |
| Reinforced Concrete Frame | 9/12/2025 | Partial Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 9/12/2025 | Partial Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 9/16/2025 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 9/29/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 10/3/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 10/9/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Green Building Rough | 10/30/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 10/30/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 11/3/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Wood Frame | 12/15/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 2/6/2026 | Corrections Issued | ALIZAH MAYAGOITIA |
| Rough-Elec/Plmb/HVAC | 2/6/2026 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 2/6/2026 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 2/11/2026 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 2/13/2026 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 3/11/2026 | Approved | GEM DE OCAMPO |
| Green Building Rough | 3/11/2026 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 3/11/2026 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 4/22/2026 | Partial Approval | DAVID WILLIAMS |
| Shower Pan | 4/22/2026 | Approved | DAVID WILLIAMS |