Pre-Inspection
|
6/11/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
6/20/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
6/20/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
6/21/2019
|
Partial Approval
|
LESLIE TRUJILLO
|
|
Deputy Other (see comments)
|
6/24/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
6/24/2019
|
Approved
|
LARRY ARNICK
|
|
Piling/Pier/Caisson
|
6/26/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
6/27/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
7/1/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Other (see comments)
|
7/2/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
7/3/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
7/15/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
7/15/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
7/17/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
7/19/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
7/29/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
7/30/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Other (see comments)
|
7/31/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/5/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
8/8/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Footing/Foundation/Slab
|
8/8/2019
|
Approved
|
LARRY ARNICK
|
|
Masonry Wall/Backfill
|
8/8/2019
|
Partial Inspection
|
LARRY ARNICK
|
|
Deputy Other (see comments)
|
8/9/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/19/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
8/21/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/21/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/27/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Piling/Pier/Caisson
|
8/28/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Other (see comments)
|
8/29/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
8/29/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
8/30/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/5/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/9/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/10/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/13/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Drilled-In Anchors
|
9/17/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/17/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Drilled-In Anchors
|
9/24/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/1/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/3/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/16/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/18/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
10/18/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
10/21/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
10/24/2019
|
Not Ready for Inspection
|
JOEY BUCHANAN
|
|
Verify Sprinkler Sign Off
|
10/24/2019
|
Not Ready for Inspection
|
JOEY BUCHANAN
|
|
Wood Frame
|
10/24/2019
|
Not Ready for Inspection
|
JOEY BUCHANAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/29/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/31/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
11/1/2019
|
Partial Inspection
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/4/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
11/4/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Insulation
|
11/4/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
11/4/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wall Anchors
|
11/4/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/7/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
11/7/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
11/7/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
11/7/2019
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Wood Construction
|
11/19/2019
|
Conditional Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
11/20/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
11/27/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
12/3/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/3/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
12/12/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/13/2019
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/16/2019
|
Corrections Issued
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/6/2020
|
Corrections Issued
|
LARRY ARNICK
|
|
Green Building Rough
|
1/13/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
1/13/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
1/13/2020
|
Corrections Issued
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/15/2020
|
Not Ready for Inspection
|
HAMID PISHEHVAR
|
|
Green Building Rough
|
1/21/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
1/21/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
1/21/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Insulation
|
1/22/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
1/24/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Insulation
|
1/24/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
1/24/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
1/24/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Insulation
|
1/27/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
1/28/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
1/29/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
1/30/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
1/31/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Insulation
|
1/31/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
1/31/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
1/31/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Insulation
|
2/3/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Insulation
|
2/4/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
2/5/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Insulation
|
2/5/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Drywall Nailing
|
2/6/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Insulation
|
2/6/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
2/10/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
2/10/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
2/11/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
2/12/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
2/12/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Insulation
|
2/12/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
2/12/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
2/12/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
2/13/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Insulation
|
2/13/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Insulation
|
2/14/2020
|
Corrections Issued
|
LARRY ARNICK
|
|
Green Building Rough
|
2/18/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Insulation
|
2/18/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
2/18/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
2/18/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
2/19/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
2/20/2020
|
Partial Inspection
|
LARRY ARNICK
|
|
Green Building Rough
|
2/24/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Insulation
|
2/24/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
2/24/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Wood Frame
|
2/24/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
2/27/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Verify Sprinkler Sign Off
|
2/27/2020
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
2/27/2020
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Green Building Rough
|
3/10/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
3/10/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
3/10/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
3/23/2020
|
Approved
|
LARRY ARNICK
|
|
Drywall Nailing
|
3/26/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
4/8/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
4/8/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
4/8/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
4/16/2020
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Verify Sprinkler Sign Off
|
4/16/2020
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Wood Frame
|
4/16/2020
|
Partial Approval
|
JONATHAN QUACH
|
|
Green Building Rough
|
4/20/2020
|
Approved
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
4/20/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
4/20/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
4/22/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
4/29/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Insulation
|
4/30/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
5/1/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
5/11/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
5/13/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
5/14/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/19/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Insulation
|
5/21/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
5/21/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
5/21/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
6/16/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
T-Bar Ceiling
|
7/6/2020
|
Approved
|
TIMOTHY BUXTON
|
|
Excavation/Setback/Form/Re-Bar
|
7/7/2020
|
Approved
|
LARRY ARNICK
|
|
Light Gage Steel Frame
|
7/14/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Deputy Other (see comments)
|
7/20/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
7/21/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
7/28/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
7/29/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Piling/Pier/Caisson
|
7/31/2020
|
Order to Comply Issued
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
8/17/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Deputy Reinf. Concrete
|
9/11/2020
|
Conditional Approval
|
LARRY ARNICK
|
|
Piling/Pier/Caisson
|
9/17/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Final
|
9/29/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Green Building Final
|
9/29/2020
|
Approved
|
LARRY ARNICK
|
|
SGSOV-Seismic Gas S/O Valve
|
9/29/2020
|
SGSOV Not Ready
|
LARRY ARNICK
|
|
Smoke Detectors
|
9/29/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
9/29/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
9/29/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
9/30/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
10/1/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
10/2/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Final
|
10/5/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
SGSOV-Seismic Gas S/O Valve
|
10/5/2020
|
SGSOV Not Ready
|
LARRY ARNICK
|
|
Smoke Detectors
|
10/5/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
10/5/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
10/5/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
10/5/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
10/6/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
10/7/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Final
|
10/9/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
SGSOV-Seismic Gas S/O Valve
|
10/9/2020
|
SGSOV Not Ready
|
LARRY ARNICK
|
|
Smoke Detectors
|
10/9/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
10/9/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
10/9/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
10/13/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
10/15/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Final
|
10/19/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
SGSOV-Seismic Gas S/O Valve
|
10/19/2020
|
SGSOV Not Ready
|
LARRY ARNICK
|
|
Smoke Detectors
|
10/19/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
10/19/2020
|
Partial Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
10/19/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
10/19/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
10/20/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Special/Order Compliance
|
10/21/2020
|
Partial Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
10/22/2020
|
Partial Approval
|
LARRY ARNICK
|
|
Final
|
10/23/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
SGSOV-Seismic Gas S/O Valve
|
10/23/2020
|
SGSOV Approved
|
LARRY ARNICK
|
|
Smoke Detectors
|
10/23/2020
|
Approved
|
LARRY ARNICK
|
|
Special/Order Compliance
|
10/23/2020
|
Partial Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
10/23/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
10/23/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
10/24/2020
|
Partial Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
10/26/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
10/27/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
10/28/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Final
|
10/29/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Special/Order Compliance
|
10/29/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
10/29/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
10/29/2020
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Final
|
11/16/2020
|
Partial Inspection
|
DANIEL COLLINS
|
|
Verify Sprinkler Sign Off
|
11/16/2020
|
Partial Inspection
|
DANIEL COLLINS
|
|
Wood Frame
|
11/16/2020
|
Partial Inspection
|
DANIEL COLLINS
|
|
Final
|
11/20/2020
|
OK for TCO
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
11/20/2020
|
Approved
|
EDWIN GREGORYONA
|
|
Wood Frame
|
11/20/2020
|
Approved
|
EDWIN GREGORYONA
|
|
Special/Order Compliance
|
4/28/2021
|
Approved
|
EDWIN GREGORYONA
|
|
Special/Order Compliance
|
10/13/2021
|
Approved
|
EDWIN GREGORYONA
|
|
Special/Order Compliance
|
10/26/2021
|
Approved
|
EDWIN GREGORYONA
|