2311 W EFFIE ST 90026
Certificate Information: 2311 W EFFIE ST 90026
- Application / Permit
- 18010-10000-03615
- Plan Check / Job No.
- B18LA14657
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY SINGLE FAMILY DWELLING WITH ATTACHED 2 CAR GARAGE.
- Permit Issued
- Issued on 4/23/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/18/2018 | APPLICANT |
| Green Plans Picked Up | 8/15/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2018 | ZAW HAN |
| Corrections Issued | 9/5/2018 | ZAW HAN |
| Building Plans Picked Up | 9/18/2018 | APPLICANT |
| Quality Review Completed | 11/7/2018 | HERNAN ARREOLA |
| Applicant returned to address corrections | 12/3/2018 | ZAW HAN |
| Applicant returned to address corrections | 2/8/2019 | ZAW HAN |
| Plan Check Approved | 4/4/2019 | ZAW HAN |
| Issued | 4/23/2019 | LADBS |
| CofO in Progress | 3/23/2024 | THOMAS LOGRASSO |
| Permit Finaled | 3/29/2024 | DEROLD HAUFF |
| CofO Issued | 3/29/2024 | DEROLD HAUFF |
| Permit Finaled | 3/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/15/2018 | NAZILA NOORIFAR |
| Permit | Cleared | 11/15/2018 | NAZILA NOORIFAR |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2018 | NAZILA NOORIFAR |
| Hydrant and Access approval | Cleared | 12/3/2018 | ROBERT DUFF |
| Sewer availability | Cleared | 12/3/2018 | NAZILA NOORIFAR |
| Green Code | Cleared | 1/8/2019 | NEGAR NEJAD |
| Low Impact Development | Cleared | 2/5/2019 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 2/8/2019 | ADRIAN SANCHEZ |
| Frnt yard landscape/Water mgmt | Cleared | 2/21/2019 | SOPHIE GABEL-SCHEINBAU |
| Specific Plan | Cleared | 2/21/2019 | EDUARDO HERMOSO |
| Disturb/Remove Protected Trees | Cleared | 2/27/2019 | ADRIAN SANCHEZ |
| Trees in Parkway | Cleared | 2/27/2019 | ADRIAN SANCHEZ |
| GPI Written Notices | Cleared | 4/4/2019 | ROBERT HUGHES |
| Grading Pre-Inspection | Cleared | 4/4/2019 | ROBERT HUGHES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hansen,, Neil Christian; Lic. No.: L9027 | 135 N LAMER STREET APT A BURBANK, CA 91506 |
| Engineer | Li, Dacheng David; Lic. No.: C58075 | 23240 RIDGELINE DR DIAMOND BAR, CA 91765 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/26/2019 | Partial Inspection | DAVID CHAN |
| Special/Order Compliance | 5/21/2021 | Partial Inspection | HAMIK HARTOUNIAN |
| Pre-Inspection | 5/25/2021 | Corrections Issued | RUBEN SALAS |
| Piling/Pier/Caisson | 10/21/2021 | Partial Approval | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 10/25/2021 | Partial Approval | RUBEN SALAS |
| Piling/Pier/Caisson | 11/8/2021 | Approved | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/9/2021 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 1/6/2022 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 1/18/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 1/20/2022 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 1/31/2022 | Corrections Issued | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 2/3/2022 | No Access for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/28/2022 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 3/7/2022 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2022 | Partial Approval | THOMAS LOGRASSO |
| Deputy Wood Construction | 4/26/2022 | Conditional Approval | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2022 | Partial Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 10/18/2022 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2022 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 10/18/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 10/18/2022 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 11/1/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 11/1/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 11/1/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 11/14/2022 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 11/14/2022 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 11/14/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 11/14/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 11/14/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Shower Pan | 11/14/2022 | Approved | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 11/14/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 11/23/2022 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 11/23/2022 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 12/7/2022 | Approved | THOMAS LOGRASSO |
| Gas Test | 12/14/2023 | Approved | THOMAS LOGRASSO |
| Green Building Final | 1/26/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Final | 1/26/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 1/26/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/14/2024 | Approved | THOMAS LOGRASSO |
| Final | 3/14/2024 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 3/14/2024 | Approved | THOMAS LOGRASSO |
| Green Building Final | 3/14/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 3/14/2024 | SGSOV Approved | THOMAS LOGRASSO |
| Service/Power Release | 3/14/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 3/14/2024 | Approved | THOMAS LOGRASSO |
| Final | 3/22/2024 | OK to Issue CofO | THOMAS LOGRASSO |
| Green Building Final | 3/22/2024 | Approved | THOMAS LOGRASSO |
| Service/Power Release | 3/22/2024 | Approved | THOMAS LOGRASSO |