3064 W AVENUE 35 90065

Certificate Information: 3064 W AVENUE 35 90065

Application / Permit
18010-10000-03399
Plan Check / Job No.
B18LA13541
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 20'X26' 2-STORY SFD (H3). NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 12/18/2019
Issuing Office
Metro
Current Status
CofO Issued on 7/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/3/2018 APPLICANT
Green Plans Picked Up 8/6/2018 APPLICANT
Assigned to Plan Check Engineer 8/16/2018 GEORGE ALVAREZ
Corrections Issued 9/13/2018 GEORGE ALVAREZ
Quality Review Completed 9/18/2018 MICHAEL PEREZ
Building Plans Picked Up 9/18/2018 APPLICANT
Plan Check Approved 8/12/2019 GEORGE ALVAREZ
Plan Check Approved 8/12/2019 GEORGE ALVAREZ
Plan Check Approved 8/12/2019 GEORGE ALVAREZ
Issued 12/18/2019 LADBS
CofO in Progress 7/5/2023 HAMIK HARTOUNIAN
Permit Finaled 7/16/2023 DEROLD HAUFF
CofO Issued 7/16/2023 DEROLD HAUFF
Permit Finaled 7/16/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/6/2018 NAZILA NOORIFAR
Address approval Cleared 11/6/2018 NAZILA NOORIFAR
Eng Process Fee Ord 176,300 Cleared 11/6/2018 NAZILA NOORIFAR
Hydrant and Access approval Cleared 11/6/2018 GEORGE SUCHAND
Sewer availability Cleared 11/6/2018 NAZILA NOORIFAR
Street width determination Cleared 11/6/2018 NAZILA NOORIFAR
Green Code Cleared 12/7/2018 GEORGE ALVAREZ
Grading Pre-Inspection Cleared 1/18/2019 GEORGE ALVAREZ
Low Impact Development Cleared 3/1/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 3/13/2019 JEANETTE VONG
ZI Cleared 7/8/2019 SOPHIE GABEL-SCHEINBAU

Contact Information

Contractor Lightning Construction Company; Lic. No.: 900084-B 16804 CALIFORNIA AVE      BELLFLOWER, CA 90706
Engineer Barakat, Fouad Chafic; Lic. No.: C67449 5211 GOLDEN WEST AVE      TEMPLE CITY, CA 91780

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/30/2020 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 5/11/2020 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/16/2020 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/20/2020 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 11/10/2020 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 12/9/2020 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 12/9/2020 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 7/26/2021 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/3/2021 Corrections Issued HAMIK HARTOUNIAN
Gas Test 11/3/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 11/3/2021 Conditional Approval HAMIK HARTOUNIAN
HVAC-Rough 11/3/2021 Corrections Issued HAMIK HARTOUNIAN
MERV13>=Rough 11/3/2021 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 11/3/2021 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/29/2021 Approved HAMIK HARTOUNIAN
Green Building Rough 11/29/2021 Approved HAMIK HARTOUNIAN
HVAC-Rough 11/29/2021 Approved HAMIK HARTOUNIAN
Insulation 11/29/2021 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 11/29/2021 Approved HAMIK HARTOUNIAN
Drywall Nailing 1/4/2022 Approved HAMIK HARTOUNIAN
Gas Test 1/4/2022 Approved HAMIK HARTOUNIAN
Shower Pan 1/4/2022 Approved HAMIK HARTOUNIAN
Sewer 4/7/2022 Approved HAMIK HARTOUNIAN
Underground Mechanical 4/7/2022 Approved HAMIK HARTOUNIAN
Underground Mechanical 4/26/2022 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Final 2/21/2023 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Final 2/21/2023 Corrections Issued HAMIK HARTOUNIAN
Final 6/30/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/30/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 6/30/2023 Not Ready for Inspection HAMIK HARTOUNIAN
MERV13>=Final 6/30/2023 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 6/30/2023 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 6/30/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Final 7/5/2023 OK to Issue CofO HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/5/2023 Approved HAMIK HARTOUNIAN
Green Building Final 7/5/2023 Approved HAMIK HARTOUNIAN
MERV13>=Final 7/5/2023 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 7/5/2023 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 7/5/2023 Approved HAMIK HARTOUNIAN