3062 W AVENUE 35 90065
Certificate Information: 3062 W AVENUE 35 90065
- Application / Permit
- 18010-10000-03398
- Plan Check / Job No.
- B18LA13541
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 29'X45' 2-STORY SINGLE FAMILY DWELLING. NFPA 13D SPRINKLERS THROUGHOUT (H2)
- Permit Issued
- Issued on 12/18/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/3/2018 | APPLICANT |
| Green Plans Picked Up | 8/6/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2018 | GEORGE ALVAREZ |
| Corrections Issued | 9/13/2018 | GEORGE ALVAREZ |
| Quality Review Completed | 9/18/2018 | MICHAEL PEREZ |
| Building Plans Picked Up | 9/18/2018 | APPLICANT |
| Plan Check Approved | 8/12/2019 | GEORGE ALVAREZ |
| Plan Check Approved | 8/12/2019 | GEORGE ALVAREZ |
| Plan Check Approved | 8/12/2019 | GEORGE ALVAREZ |
| Issued | 12/18/2019 | LADBS |
| CofO in Progress | 7/5/2023 | HAMIK HARTOUNIAN |
| Permit Finaled | 7/16/2023 | DEROLD HAUFF |
| CofO Issued | 7/16/2023 | DEROLD HAUFF |
| Permit Finaled | 7/16/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Street width determination | Cleared | 11/2/2018 | ADRIAN SANCHEZ |
| Address approval | Cleared | 11/6/2018 | NAZILA NOORIFAR |
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2018 | NAZILA NOORIFAR |
| Hydrant and Access approval | Cleared | 11/6/2018 | GEORGE SUCHAND |
| Sewer availability | Cleared | 11/6/2018 | NAZILA NOORIFAR |
| Green Code | Cleared | 12/7/2018 | GEORGE ALVAREZ |
| Low Impact Development | Cleared | 2/6/2019 | RYAN HUDSON |
| Address approval | Cleared | 2/27/2019 | NAZILA NOORIFAR |
| Grading Pre-Inspection | Cleared | 2/27/2019 | GEORGE ALVAREZ |
| Roof/Waste drainage to street | Cleared | 3/13/2019 | JEANETTE VONG |
| CPC | Cleared | 3/18/2019 | SOPHIE GABEL-SCHEINBAU |
| ZI | Cleared | 7/8/2019 | SOPHIE GABEL-SCHEINBAU |
| Waste Hauler Permit | Cleared | 12/17/2019 | RYAN HUDSON |
Contact Information
| Contractor | Lightning Construction Company; Lic. No.: 900084-B | 16804 CALIFORNIA AVE BELLFLOWER, CA 90706 |
| Contractor | Owner-Builder | , |
| Engineer | Barakat, Fouad Chafic; Lic. No.: C67449 | 5211 GOLDEN WEST AVE TEMPLE CITY, CA 91780 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/12/2020 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 4/30/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 5/11/2020 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2020 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 12/9/2020 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/26/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Rough-Elec/Plmb/HVAC | 7/26/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 11/3/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 11/3/2021 | Approved | HAMIK HARTOUNIAN |
| Gas Test | 11/3/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 11/3/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 11/3/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| MERV13>=Rough | 11/3/2021 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 11/3/2021 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 11/3/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 11/29/2021 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 11/29/2021 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 11/29/2021 | Approved | HAMIK HARTOUNIAN |
| Insulation | 11/29/2021 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 11/29/2021 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 1/4/2022 | Approved | HAMIK HARTOUNIAN |
| Gas Test | 1/4/2022 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 1/4/2022 | Approved | HAMIK HARTOUNIAN |
| Sewer | 4/7/2022 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 4/7/2022 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 4/20/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 2/21/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 2/21/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Final | 2/21/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 6/30/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 6/30/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 6/30/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| MERV13>=Final | 6/30/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 6/30/2023 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Service/Power Release | 6/30/2023 | Not Required | HAMIK HARTOUNIAN |
| Smoke Detectors | 6/30/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 7/5/2023 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/5/2023 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 7/5/2023 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Final | 7/5/2023 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 7/5/2023 | SGSOV Approved | HAMIK HARTOUNIAN |