9779 N ORCAS AVE 91040
Certificate Information: 9779 N ORCAS AVE 91040
- Application / Permit
- 18010-10000-03331
- Plan Check / Job No.
- B18LA13144
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- New 1-story 1-car garage and storage. All works per Wood Frame Prescriptive Provisions.
- Permit Issued
- Issued on 2/24/2020
- Issuing Office
- Metro
- Current Status
- Issued on 2/24/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/28/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/26/2018 | HELEN NGUYEN |
| Corrections Issued | 7/30/2018 | HELEN NGUYEN |
| Quality Review Completed | 8/7/2018 | BILL STUTSMAN |
| Building Plans Picked Up | 8/14/2018 | APPLICANT |
| Applicant returned to address corrections | 9/10/2018 | HELEN NGUYEN |
| Green Plans Picked Up | 9/10/2018 | APPLICANT |
| Applicant returned to address corrections | 9/25/2018 | HELEN NGUYEN |
| Applicant returned to address corrections | 11/8/2018 | HELEN NGUYEN |
| Plan Check Approved | 2/24/2020 | HELEN NGUYEN |
| Issued | 2/24/2020 | LADBS |
Permit Application Clearance Information
| Green Code | Cleared | 10/17/2018 | SARAH ABOULHOSN |
| Grading Pre-Inspection | Cleared | 10/18/2018 | PATRICK MISCHLICH |
| Low Impact Development | Cleared | 11/2/2018 | JORGE MEJIA LEMUS |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2018 | JAMES MORALEZ |
| Permit | Cleared | 11/9/2018 | JAMES MORALEZ |
| Roof/Waste drainage to street | Cleared | 11/9/2018 | JAMES MORALEZ |
| Specific Plan | Cleared | 1/31/2020 | DENZEL HENDERSON |
| Trees in Parkway | Cleared | 2/14/2020 | JOHN KIM |
Contact Information
| Contractor | Owner-Builder | , |
| Geologist | Kaligi,, Azad Adam; Lic. No.: GEO9287 | 26905 ROLLING HILLS AVE SANTA CLARITA, CA 91387 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/2/2020 | Approved | DAVID MATSON |
| METHANE-Barrier | 11/2/2020 | Approved | DAVID MATSON |
| METHANE-Subgrade | 11/2/2020 | Approved | DAVID MATSON |
| BUILDING-Rough-Frame | 5/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 5/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| METHANE-Rough | 5/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 6/29/2022 | Approved | DAVID ANDERSON |
| Final | 12/2/2024 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 12/2/2024 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 12/2/2024 | SGSOV Not Required | DAVID ANDERSON |
| Service/Power Release | 12/2/2024 | Not Required | DAVID ANDERSON |
| Smoke Detectors | 12/2/2024 | Approved | DAVID ANDERSON |