10675 W BELLAGIO ROAD 90077

Certificate Information: 10675 W BELLAGIO ROAD 90077

Application / Permit
18010-10000-03324
Plan Check / Job No.
B18LA13114
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SINGLE FAMILY HOUSE 3 STORY WITH BASEMENT
Permit Issued
Issued on 11/5/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2018 APPLICANT
Green Plans Picked Up 7/12/2018 APPLICANT
Assigned to Plan Check Engineer 7/26/2018 JOE VO
Corrections Issued 8/13/2018 JOE VO
Quality Review Completed 8/13/2018 GARO TELMI
Building Plans Picked Up 8/14/2018 APPLICANT
Applicant returned to address corrections 9/10/2018 JOE VO
Plan Check Approved 10/30/2018 JOE VO
Issued 11/5/2018 LADBS
CofO in Progress 2/26/2024 CHRISTOPHER WILSON
Permit Finaled 3/11/2024 DANIEL ORRANTE
CofO Issued 3/11/2024 DANIEL ORRANTE
Permit Finaled 3/11/2024 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 8/14/2018 MAHELET GEBEYHU
BHO/Hillside ordinance Cleared 8/14/2018 MAHELET GEBEYHU
BHO/Hillside ordinance Cleared 8/14/2018 MAHELET GEBEYHU
Eng Process Fee Ord 176,300 Cleared 8/14/2018 MAHELET GEBEYHU
Hydrant and Access approval Cleared 8/27/2018 JOHN DALLAS
Miscellaneous Cleared 8/27/2018 JOHN DALLAS
Green Code Cleared 9/14/2018 DONALD CRICHLOW
Low Impact Development Cleared 10/9/2018 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 10/10/2018 STEVE MELGAR
Permit Cleared 10/12/2018 BRIAN KELLY
Excavation more than 5-ft deep Cleared 10/30/2018 CALOSHA APPROVED

Contact Information

Contractor Arya Group Inc; Lic. No.: 694649-B 10490 SANTA MONICA BLVD      LOS ANGELES, CA 90025
Engineer , ; Lic. No.: C75121       ,
Engineer , ; Lic. No.: S4549       ,
Engineer Hollingsworth, Robert Alan; Lic. No.: GE2022 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/18/2020 Approved CHRISTOPHER WILSON
Piling/Pier/Caisson 5/1/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 6/15/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 9/2/2020 Corrections Issued CHRISTOPHER WILSON
Piling/Pier/Caisson 9/3/2020 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 9/17/2020 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 9/18/2020 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 9/28/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 10/19/2020 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 10/20/2020 Conditional Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 10/20/2020 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 10/22/2020 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 10/22/2020 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 10/28/2020 Conditional Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 10/28/2020 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 10/30/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 11/2/2020 Conditional Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 11/2/2020 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 11/5/2020 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 11/5/2020 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 11/6/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 11/6/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 11/12/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 11/13/2020 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 11/13/2020 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 11/13/2020 Partial Approval CHRISTOPHER WILSON
Deputy Grading 11/18/2020 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 11/18/2020 Partial Approval CHRISTOPHER WILSON
Deputy Grading 11/19/2020 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 11/19/2020 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 11/19/2020 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 11/20/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 11/23/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 11/24/2020 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 11/25/2020 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 11/30/2020 Partial Approval JUAN VALENZUELA
Piling/Pier/Caisson 12/7/2020 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 12/8/2020 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 12/10/2020 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 12/10/2020 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 12/11/2020 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 12/18/2020 Partial Inspection THOMAS FINNILA
Footing/Foundation/Slab 12/23/2020 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 12/24/2020 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 12/30/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 12/31/2020 Approved MATT KELLERMAN
Reinforced Concrete Frame 1/6/2021 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 1/7/2021 Conditional Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 1/7/2021 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 1/7/2021 Partial Approval CHRISTOPHER WILSON
Deputy Other (see comments) 1/12/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 1/14/2021 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 1/14/2021 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 1/15/2021 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 1/15/2021 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 1/20/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 1/21/2021 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 1/21/2021 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 2/3/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Other (see comments) 2/4/2021 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 2/4/2021 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 2/9/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 2/9/2021 Conditional Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 2/9/2021 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 2/10/2021 Conditional Approval CHRISTOPHER WILSON
Structural Steel Frame 2/10/2021 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 2/17/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 2/17/2021 Conditional Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 2/18/2021 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 2/19/2021 Not Ready for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 2/19/2021 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 2/19/2021 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 2/25/2021 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 2/26/2021 Conditional Approval CHRISTOPHER WILSON
Structural Steel Frame 3/2/2021 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 3/5/2021 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 3/8/2021 Conditional Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 3/12/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Reinforced Concrete Frame 3/18/2021 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 3/19/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 3/25/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 3/26/2021 Approved MATT KELLERMAN
Reinforced Concrete Frame 3/30/2021 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 3/30/2021 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 3/31/2021 Approved MATT KELLERMAN
Deputy Steel/Welding 4/5/2021 Conditional Approval CHRISTOPHER WILSON
Structural Steel Frame 4/5/2021 Not Ready for Inspection MATT KELLERMAN
Underground Mechanical 4/5/2021 No Access for Inspection MATT KELLERMAN
Deputy Steel/Welding 4/6/2021 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 4/6/2021 Partial Inspection CHRISTOPHER WILSON
Deputy Reinf. Concrete 4/7/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 4/7/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 4/8/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 4/12/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 4/13/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 4/14/2021 Conditional Approval ANTHONY MCDOWALL
Deputy Steel/Welding 4/15/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 4/16/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 4/16/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 4/26/2021 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 4/26/2021 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 4/27/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 4/27/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 4/28/2021 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 4/28/2021 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 4/29/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 4/29/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Wood Construction 4/29/2021 Conditional Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 4/30/2021 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 4/30/2021 Partial Approval CHRISTOPHER WILSON
Deputy Wood Construction 5/4/2021 Conditional Approval CHRISTOPHER WILSON
Drywall Nailing 5/4/2021 Partial Approval CHRISTOPHER WILSON
Wood Frame 5/4/2021 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 5/13/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Wood Construction 5/13/2021 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 5/14/2021 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 5/14/2021 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 5/24/2021 Conditional Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 5/24/2021 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 5/25/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/4/2021 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 6/8/2021 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 6/9/2021 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 6/17/2021 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 6/24/2021 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 7/9/2021 Partial Approval CHRISTOPHER WILSON
Deputy Wood Construction 7/12/2021 Conditional Approval CHRISTOPHER WILSON
Wood Frame 7/13/2021 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 7/15/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 7/16/2021 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 7/20/2021 Corrections Issued CHRISTOPHER WILSON
HVAC-Rough 7/22/2021 Corrections Issued CHRISTOPHER WILSON
Wood Frame 8/2/2021 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 8/3/2021 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 8/4/2021 Conditional Approval KRISTEN CAUSEY
PLUMBING-Rough 8/5/2021 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 8/6/2021 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 8/25/2021 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 9/9/2021 Conditional Approval JAVIER RAMOS JR
Reinforced Concrete Frame 9/16/2021 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 9/20/2021 Conditional Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 10/7/2021 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 10/8/2021 Conditional Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 10/18/2021 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 10/18/2021 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 10/19/2021 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 10/21/2021 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 10/22/2021 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 11/2/2021 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 11/9/2021 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 11/10/2021 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 11/12/2021 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 11/18/2021 Corrections Issued CHRISTOPHER WILSON
Reinforced Concrete Frame 11/18/2021 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 11/22/2021 Partial Approval BRENDAN LOONEY
Wood Frame 11/29/2021 Corrections Issued CHRISTOPHER WILSON
Deputy Drilled-In Anchors 11/30/2021 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 11/30/2021 Not Ready for Inspection CHRISTOPHER WILSON
Underground Mechanical 11/30/2021 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 12/1/2021 Partial Approval CHRISTOPHER WILSON
Sewer 12/17/2021 Partial Approval CHRISTOPHER WILSON
Sewer 12/21/2021 Approved STEPHANIE SWANSON
Insulation 12/27/2021 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 12/27/2021 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Rough 1/11/2022 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 1/25/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 1/27/2022 Corrections Issued CHRISTOPHER WILSON
HVAC-Rough 2/14/2022 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 2/17/2022 Partial Approval CHRISTOPHER WILSON
Green Building Rough 2/17/2022 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 2/17/2022 Approved CHRISTOPHER WILSON
Shower Pan 3/25/2022 Corrections Issued CHRISTOPHER WILSON
Shower Pan 3/29/2022 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 4/7/2022 Partial Approval CHRISTOPHER WILSON
Insulation 4/22/2022 Partial Approval CHRISTOPHER WILSON
Pre-Inspection 4/28/2022 Partial Approval CHRISTOPHER WILSON
Pre-Inspection 4/29/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 5/4/2022 Partial Approval RYAN SALAZAR
HVAC-Rough 5/6/2022 Not Ready for Inspection CHRISTOPHER WILSON
Insulation 5/6/2022 Partial Approval CHRISTOPHER WILSON
Pre-Inspection 5/6/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 5/27/2022 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 6/2/2022 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 6/2/2022 Corrections Issued CHRISTOPHER WILSON
Wood Frame 6/2/2022 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 6/3/2022 Partial Approval CHRISTOPHER WILSON
Service/Power Release 6/3/2022 Corrections Issued CHRISTOPHER WILSON
Deputy Drilled-In Anchors 6/6/2022 Conditional Approval CHRISTOPHER WILSON
Service/Power Release 6/7/2022 Approved CHRISTOPHER WILSON
Reinforced Concrete Frame 6/10/2022 Conditional Approval CHRISTOPHER WILSON
Deputy Shotcrete 6/13/2022 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Rough 7/13/2022 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 7/13/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 7/13/2022 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 7/22/2022 Partial Approval CHRISTOPHER WILSON
Insulation 7/22/2022 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 8/9/2022 Conditional Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 8/10/2022 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 8/11/2022 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 8/11/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 8/12/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 8/12/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 8/16/2022 Partial Approval CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 8/16/2022 SGSOV Not Ready CHRISTOPHER WILSON
Wood Frame 8/18/2022 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 8/19/2022 Partial Approval JUAN VALENZUELA
Green Building Rough 8/19/2022 Not Ready for Inspection JUAN VALENZUELA
Deputy Shotcrete 9/15/2022 Conditional Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 10/6/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 10/6/2022 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 10/7/2022 Corrections Issued CHRISTOPHER WILSON
HVAC-Rough 10/12/2022 Partial Approval CHRISTOPHER WILSON
Light Gage Steel Frame 10/12/2022 Partial Approval CHRISTOPHER WILSON
Insulation 10/18/2022 Corrections Issued STEPHANIE SWANSON
Insulation 10/26/2022 Approved STEPHANIE SWANSON
Drywall Nailing 10/31/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 11/2/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 11/28/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 11/28/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 11/28/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Wood Frame 11/28/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 11/29/2022 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 11/29/2022 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 11/29/2022 Not Ready for Inspection CARLOS MATAMOROS
Shower Pan 1/13/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Wood Frame 1/17/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Pre-Inspection 1/19/2023 Approved CARLOS MATAMOROS
HVAC-Rough 1/20/2023 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 1/20/2023 Approved CARLOS MATAMOROS
Shower Pan 1/20/2023 Approved CARLOS MATAMOROS
Wood Frame 1/20/2023 Approved CARLOS MATAMOROS
Insulation 1/23/2023 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 1/31/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 2/22/2023 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 2/22/2023 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 3/28/2023 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 5/22/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 5/22/2023 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 5/22/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 5/22/2023 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 5/22/2023 Partial Approval CHRISTOPHER WILSON
Insulation 5/23/2023 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 5/26/2023 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 5/26/2023 Corrections Issued CHRISTOPHER WILSON
Insulation 5/26/2023 Partial Approval CHRISTOPHER WILSON
Structural Steel Frame 5/31/2023 Corrections Issued CHRISTOPHER WILSON
Drywall Nailing 6/1/2023 Partial Approval CHRISTOPHER WILSON
Structural Steel Frame 6/1/2023 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 6/7/2023 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 6/7/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 6/7/2023 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 6/9/2023 Corrections Issued CHRISTOPHER WILSON
Wood Frame 6/9/2023 Partial Approval CHRISTOPHER WILSON
Insulation 6/12/2023 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 6/16/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 7/13/2023 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 7/13/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 7/13/2023 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 7/19/2023 Partial Approval CHRISTOPHER WILSON
Wood Frame 7/19/2023 Approved CHRISTOPHER WILSON
Drywall Nailing 7/31/2023 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 8/15/2023 Not Ready for Inspection CHRISTOPHER WILSON
Structural Steel Frame 8/15/2023 Corrections Issued CHRISTOPHER WILSON
Interior/Exterior Lathing 8/17/2023 Partial Approval CHRISTOPHER WILSON
Gas Test 8/21/2023 Not Ready for Inspection CHRISTOPHER WILSON
Gas Test 8/29/2023 Corrections Issued CHRISTOPHER WILSON
Special/Order Compliance 8/29/2023 Not Ready for Inspection BRANDON IVES
Deck 9/14/2023 Not Ready for Inspection CHRISTOPHER WILSON
Structural Steel Frame 9/14/2023 Corrections Issued CHRISTOPHER WILSON
Structural Steel Frame 9/20/2023 Approved CHRISTOPHER WILSON
PLUMBING-Final 9/21/2023 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Final 9/25/2023 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Final 9/26/2023 Corrections Issued CHRISTOPHER WILSON
HVAC-Final 9/27/2023 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 10/2/2023 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Final 10/2/2023 Corrections Issued CHRISTOPHER WILSON
HVAC-Final 10/3/2023 Approved CHRISTOPHER WILSON
PLUMBING-Final 10/3/2023 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 10/5/2023 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 10/10/2023 Corrections Issued CHRISTOPHER WILSON
Special/Order Compliance 10/10/2023 Partial Inspection BRANDON IVES
ELECTRICAL-Final 10/11/2023 Approved CHRISTOPHER WILSON
Gas Test 10/11/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 10/11/2023 Corrections Issued CHRISTOPHER WILSON
Gas Test 10/16/2023 Partial Inspection CHRISTOPHER WILSON
Gas Test 10/17/2023 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 10/17/2023 SGSOV Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 11/16/2023 Approved CHRISTOPHER WILSON
Final 11/16/2023 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 11/16/2023 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Final 11/16/2023 Approved CHRISTOPHER WILSON
Green Building Rough 11/16/2023 Approved CHRISTOPHER WILSON
Smoke Detectors 11/16/2023 Approved CHRISTOPHER WILSON
Verify Sprinkler Sign Off 11/16/2023 Approved CHRISTOPHER WILSON
Final 12/4/2023 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 12/4/2023 Approved CHRISTOPHER WILSON
Special/Order Compliance 12/4/2023 Corrections Issued MICHAEL PELHAM
Final 2/14/2024 Not Ready for Inspection CHRISTOPHER WILSON
Final 2/20/2024 Not Ready for Inspection CHRISTOPHER WILSON
Final 2/22/2024 OK to Issue CofO CHRISTOPHER WILSON
Shower Pan 2/22/2024 Approved CHRISTOPHER WILSON
Special/Order Compliance 2/22/2024 Partial Inspection MICHAEL PELHAM