3225 1/2 W MADERA AVE 90039

Certificate Information: 3225 1/2 W MADERA AVE 90039

Application / Permit
18010-10000-03233
Plan Check / Job No.
B18LA12584
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 42'-6" X 30'' (2) STORY 1195 (sq ft) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 WITH ATTACHED GARAGE
Permit Issued
Issued on 7/31/2020
Issuing Office
Current Status
CofO Issued on 10/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2018 APPLICANT
Green Plans Picked Up 7/12/2018 APPLICANT
Assigned to Plan Check Engineer 7/26/2018 MICHAEL PEREZ
Corrections Issued 7/31/2018 MICHAEL PEREZ
Quality Review Completed 8/7/2018 KESETE HAREGOT
Building Plans Picked Up 8/10/2018 APPLICANT
Plan Check Approved 12/6/2019 MICHAEL PEREZ
Issued 7/31/2020 APPLICANT
CofO in Progress 9/19/2022 HAMIK HARTOUNIAN
No Progress 9/19/2022 RUBEN SALAS
CofO in Progress 9/19/2022 HAMIK HARTOUNIAN
Permit Finaled 10/1/2022 DEROLD HAUFF
Permit Finaled 10/1/2022 DEROLD HAUFF
CofO Issued 10/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/24/2019 CELINA MORENO
CPC Cleared 6/25/2019 SOPHIE GABEL-SCHEINBAU
CPC Cleared 6/25/2019 SOPHIE GABEL-SCHEINBAU
Hydrant and Access approval Cleared 6/25/2019 GEORGE SUCHAND
Specific Plan Cleared 6/25/2019 SOPHIE GABEL-SCHEINBAU
Eng Process Fee Ord 176,300 Cleared 7/29/2019 ERIK BEASLEY
Sewer availability Cleared 7/29/2019 ERIK BEASLEY
Low Impact Development Cleared 9/18/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 9/18/2019 CELINA MORENO
Green Code Cleared 12/3/2019 NEGAR NEJAD
Construction near power lines Cleared 7/29/2020 RIDWAN HARDY

Contact Information

Contractor Lord'S Construction; Lic. No.: 854236-B 15364 NARANJA AVERNUE      PARAMOUNT, CA 90723
Engineer Hazrati,, Kayvan Naghib; Lic. No.: C60556 465 PUERTO DEL MAR      PACIFIC PALISADES, CA 90272

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/4/2020 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/5/2020 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 8/7/2020 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/7/2020 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/14/2020 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/1/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 12/1/2020 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 12/1/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Rough-Elec/Plmb/HVAC 12/1/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 12/1/2020 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/7/2020 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 12/7/2020 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 12/7/2020 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 12/7/2020 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 12/7/2020 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 12/7/2020 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/13/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 1/13/2021 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 1/13/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 1/13/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 3/5/2021 Conditional Approval JOSEPH MCGARRY
HVAC-Rough 3/31/2021 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 4/7/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 4/12/2021 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 4/12/2021 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 4/12/2021 Approved HAMIK HARTOUNIAN
Insulation 4/21/2021 Corrections Issued JOSEPH MCGARRY
Drywall Nailing 5/11/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 5/11/2021 Approved STUART CHAPMAN
ELECTRICAL-Rough 12/16/2021 Approved HAMIK HARTOUNIAN
Underground Mechanical 12/16/2021 Approved HAMIK HARTOUNIAN
Sewer 1/5/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 1/24/2022 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 6/7/2022 Approved HAMIK HARTOUNIAN
Final 6/7/2022 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/7/2022 Approved HAMIK HARTOUNIAN
Green Building Final 6/7/2022 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 6/7/2022 SGSOV Not Ready HAMIK HARTOUNIAN
Service/Power Release 6/7/2022 Not Required HAMIK HARTOUNIAN
Smoke Detectors 6/7/2022 Approved HAMIK HARTOUNIAN
Final 8/22/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 8/22/2022 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 8/22/2022 SGSOV Approved HAMIK HARTOUNIAN
Final 9/16/2022 OK to Issue CofO HAMIK HARTOUNIAN
Green Building Final 9/16/2022 Approved HAMIK HARTOUNIAN