15350 W OXNARD ST 91411
Certificate Information: 15350 W OXNARD ST 91411
- Application / Permit
- 18010-10000-03162
- Plan Check / Job No.
- B18LA09645
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- NEW TRASH ENCLOSURE FOR SITE
- Permit Issued
- Issued on 3/9/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/15/2018 | APPLICANT |
| Green Plans Picked Up | 5/31/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 6/7/2018 | RICARDO SUPAN |
| Corrections Issued | 6/18/2018 | RICARDO SUPAN |
| Quality Review Completed | 7/5/2018 | MINYE PAK |
| Disabled Access Plans Picked Up | 7/9/2018 | APPLICANT |
| Building Plans Picked Up | 7/12/2018 | APPLICANT |
| Applicant returned to address corrections | 8/27/2018 | RICARDO SUPAN |
| Applicant returned to address corrections | 1/31/2019 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 4/11/2019 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 4/18/2019 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 4/24/2019 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 4/25/2019 | CAROLYNN NEPOMUCENO |
| Plan Check Approved | 3/9/2020 | SERGIO GUTIERREZ |
| Issued | 3/9/2020 | LADBS |
| CofO in Progress | 8/25/2021 | JEFFREY DURAN |
| CofO Issued | 9/15/2021 | RICKEY JACKSON |
| Permit Finaled | 9/15/2021 | RICKEY JACKSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/7/2018 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 8/7/2018 | JOHN DALLAS |
| Highway dedication | Cleared | 8/31/2018 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 8/31/2018 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/31/2018 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 2/7/2019 | ORVAL HERNANDEZ-MARCI |
| Prkng lot landscape/Water mgmt | Cleared | 4/25/2019 | SARAHI ORTEGA |
| Site Plan review | Cleared | 4/25/2019 | SARAHI ORTEGA |
| Tract Map conditions | Cleared | 4/25/2019 | SARAHI ORTEGA |
| Tract Map conditions | Cleared | 4/25/2019 | SARAHI ORTEGA |
| ZA Case | Cleared | 4/25/2019 | SARAHI ORTEGA |
| ZI | Cleared | 4/25/2019 | SARAHI ORTEGA |
| DAS Clearance | Cleared | 2/21/2020 | RICARDO SUPAN |
| Green Code | Cleared | 2/21/2020 | RICARDO SUPAN |
Contact Information
| Architect | Vakili, Shabnam; Lic. No.: C26298 | 25341 COMMERCENTRE DRIVE SUITE 100 KSP STUDIO LAKE FOREST, CA 92630 |
| Contractor | Alston Construction Company Inc; Lic. No.: 759899-B | 8775 FOLSOM BLVD STE 201 SACRAMENTO, CA 95826 |
| Engineer | Shakerin, Kayvon; Lic. No.: C46202 | 25341 COMMERCENTRE DR STE 100 LAKE FOREST, CA 92630 |
Inspector Information
| ROBERT DAVIS, (818) 374-1125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/1/2020 | Approved | JEFFREY DURAN |
| Masonry Wall/Backfill | 4/3/2020 | Partial Approval | ROBERT COLE |
| Reinforced Concrete Frame | 4/3/2020 | Not Ready for Inspection | ROBERT COLE |
| Final | 6/9/2020 | Not Ready for Inspection | HAMID PISHEHVAR |
| Green Building Final | 6/9/2020 | Approved | HAMID PISHEHVAR |
| Green Building Rough | 6/9/2020 | Approved | HAMID PISHEHVAR |
| Reinforced Masonry Frame | 6/9/2020 | Not Ready for Inspection | HAMID PISHEHVAR |
| SGSOV-Seismic Gas S/O Valve | 6/9/2020 | SGSOV No Gas | HAMID PISHEHVAR |
| Smoke Detectors | 6/9/2020 | Approved | HAMID PISHEHVAR |
| Verify Sprinkler Sign Off | 6/9/2020 | Approved | HAMID PISHEHVAR |
| Wood Frame | 6/9/2020 | Approved | HAMID PISHEHVAR |
| Final | 1/19/2021 | Partial Inspection | HAMID PISHEHVAR |
| Reinforced Masonry Frame | 1/19/2021 | Partial Approval | HAMID PISHEHVAR |
| Final | 8/25/2021 | OK to Issue CofO | JEFFREY DURAN |
| Reinforced Masonry Frame | 8/25/2021 | Approved | JEFFREY DURAN |