5815 S NORMANDIE AVE 90044

Certificate Information: 5815 S NORMANDIE AVE 90044

Application / Permit
18010-10000-02878
Plan Check / Job No.
B18LA11800
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(9) Car Wash
Work Description
NEW 2-STORY CAR WASH DEVELOPMENT WITH INCIDENTAL OUTDOOR USES (SEE PERMITS 18010-10000-02879, 02880, 02881 & 18020-10000-01736, 19010-10000-05171)
Permit Issued
Issued on 1/3/2020
Issuing Office
Metro
Current Status
CofO Issued on 10/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/12/2018 APPLICANT
Green Plans Picked Up 6/21/2018 APPLICANT
Disabled Access Plans Picked Up 6/26/2018 APPLICANT
Assigned to Plan Check Engineer 7/5/2018 JOE VO
Corrections Issued 7/9/2018 JOE VO
Quality Review Completed 7/10/2018 GARO TELMI
Building Plans Picked Up 7/17/2018 APPLICANT
Applicant returned to address corrections 12/3/2019 JOE VO
Plan Check Approved 12/30/2019 JOE VO
Issued 1/3/2020 LADBS
CofO in Progress 10/27/2022 JAMES POWERS
CofO Issued 10/27/2022 TED RIES
Permit Finaled 10/27/2022 TED RIES

Permit Application Clearance Information

Metro Rail approval Cleared 9/21/2018 JOE VO
Eng Process Fee Ord 176,300 Cleared 9/23/2019 CELINA MORENO
Green Code Cleared 9/23/2019 KHEDER ALRAZAA
Highway dedication Cleared 10/31/2019 CELINA MORENO
Project located in CRA area Cleared 10/31/2019 JIM URQUHART
Sewer availability Cleared 10/31/2019 CELINA MORENO
Hydrant and Access approval Cleared 11/8/2019 JEREMY CARTER
Driveway location Cleared 11/14/2019 MOHAMMAD HASAN
Permit Cleared 11/14/2019 CELINA MORENO
Work Adjacent to Public Way Cleared 11/14/2019 ROSA SILVA
Cleaning solvents Cleared 11/18/2019 SCAQMD APPROVED
"Q" conditions Cleared 11/27/2019 KIT AWAKUNI
Comm Cor/Mini-Mall Cleared 11/27/2019 KIT AWAKUNI
Comm Cor/Mini-Mall Cleared 11/27/2019 KIT AWAKUNI
Comm Cor/Mini-Mall Cleared 11/27/2019 KIT AWAKUNI
Miscellaneous Cleared 11/27/2019 KIT AWAKUNI
ZA Case Cleared 11/27/2019 KIT AWAKUNI
Low Impact Development Cleared 12/2/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 12/2/2019 EMIL KYUPELYAN
DAS Clearance Cleared 12/12/2019 JOE VO

Contact Information

Contractor Ubcon Inc; Lic. No.: 1058343-B 3055 WILSHIRE BLVD #810      LOS ANGELES, CA 90010
Engineer Lee,, Chong Dennis; Lic. No.: C26282 3870 BALDWIN AVENUE      EL MONTE, CA 91731
Engineer Lee,, Chong Dennis; Lic. No.: S2543 3870 BALDWIN AVENUE      EL MONTE, CA 91731

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 3/31/2020 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 4/21/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/21/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 4/24/2020 Partial Approval RONALD PACHECO
Footing/Foundation/Slab 4/24/2020 Partial Approval RONALD PACHECO
Deputy Reinf. Concrete 4/27/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/29/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/4/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/5/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/6/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/13/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/15/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/20/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 5/29/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/1/2020 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 7/6/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/8/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/13/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/14/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/20/2020 Partial Approval JAMES POWERS
Green Building Rough 7/24/2020 Approved JAMES POWERS
Structural Steel Frame 7/24/2020 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 7/24/2020 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 8/3/2020 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/7/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/14/2020 Partial Approval JAMES POWERS
Drywall Nailing 9/8/2020 Partial Approval JAMES POWERS
Light Gage Steel Frame 9/15/2020 Approved JAMES POWERS
Drywall Nailing 9/28/2020 Approved JAMES POWERS
Interior/Exterior Lathing 10/20/2020 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 10/23/2020 Approved JAMES POWERS
Excavation/Setback/Form/Re-Bar 12/14/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 12/31/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/5/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 2/8/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 3/9/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 4/5/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 5/13/2021 Partial Approval JAMES POWERS
Final 9/27/2022 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 9/27/2022 Approved JAMES POWERS
Green Building Final 9/27/2022 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 9/27/2022 SGSOV No Gas JAMES POWERS
Smoke Detectors 9/27/2022 Approved JAMES POWERS
Structural Steel Frame 9/27/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 9/27/2022 Approved JAMES POWERS
Wood Frame 9/27/2022 Not Ready for Inspection JAMES POWERS
Final 10/27/2022 OK to Issue CofO JAMES POWERS
Structural Steel Frame 10/27/2022 Approved JAMES POWERS
Wood Frame 10/27/2022 Approved JAMES POWERS