5815 S NORMANDIE AVE 90044
Certificate Information: 5815 S NORMANDIE AVE 90044
- Application / Permit
- 18010-10000-02878
- Plan Check / Job No.
- B18LA11800
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (9) Car Wash
- Work Description
- NEW 2-STORY CAR WASH DEVELOPMENT WITH INCIDENTAL OUTDOOR USES (SEE PERMITS 18010-10000-02879, 02880, 02881 & 18020-10000-01736, 19010-10000-05171)
- Permit Issued
- Issued on 1/3/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/12/2018 | APPLICANT |
| Green Plans Picked Up | 6/21/2018 | APPLICANT |
| Disabled Access Plans Picked Up | 6/26/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/5/2018 | JOE VO |
| Corrections Issued | 7/9/2018 | JOE VO |
| Quality Review Completed | 7/10/2018 | GARO TELMI |
| Building Plans Picked Up | 7/17/2018 | APPLICANT |
| Applicant returned to address corrections | 12/3/2019 | JOE VO |
| Plan Check Approved | 12/30/2019 | JOE VO |
| Issued | 1/3/2020 | LADBS |
| CofO in Progress | 10/27/2022 | JAMES POWERS |
| CofO Issued | 10/27/2022 | TED RIES |
| Permit Finaled | 10/27/2022 | TED RIES |
Permit Application Clearance Information
| Metro Rail approval | Cleared | 9/21/2018 | JOE VO |
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2019 | CELINA MORENO |
| Green Code | Cleared | 9/23/2019 | KHEDER ALRAZAA |
| Highway dedication | Cleared | 10/31/2019 | CELINA MORENO |
| Project located in CRA area | Cleared | 10/31/2019 | JIM URQUHART |
| Sewer availability | Cleared | 10/31/2019 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 11/8/2019 | JEREMY CARTER |
| Driveway location | Cleared | 11/14/2019 | MOHAMMAD HASAN |
| Permit | Cleared | 11/14/2019 | CELINA MORENO |
| Work Adjacent to Public Way | Cleared | 11/14/2019 | ROSA SILVA |
| Cleaning solvents | Cleared | 11/18/2019 | SCAQMD APPROVED |
| "Q" conditions | Cleared | 11/27/2019 | KIT AWAKUNI |
| Comm Cor/Mini-Mall | Cleared | 11/27/2019 | KIT AWAKUNI |
| Comm Cor/Mini-Mall | Cleared | 11/27/2019 | KIT AWAKUNI |
| Comm Cor/Mini-Mall | Cleared | 11/27/2019 | KIT AWAKUNI |
| Miscellaneous | Cleared | 11/27/2019 | KIT AWAKUNI |
| ZA Case | Cleared | 11/27/2019 | KIT AWAKUNI |
| Low Impact Development | Cleared | 12/2/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 12/2/2019 | EMIL KYUPELYAN |
| DAS Clearance | Cleared | 12/12/2019 | JOE VO |
Contact Information
| Contractor | Ubcon Inc; Lic. No.: 1058343-B | 3055 WILSHIRE BLVD #810 LOS ANGELES, CA 90010 |
| Engineer | Lee,, Chong Dennis; Lic. No.: C26282 | 3870 BALDWIN AVENUE EL MONTE, CA 91731 |
| Engineer | Lee,, Chong Dennis; Lic. No.: S2543 | 3870 BALDWIN AVENUE EL MONTE, CA 91731 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 3/31/2020 | Not Ready for Inspection | JAMES POWERS |
| Deputy Reinf. Concrete | 4/21/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 4/21/2020 | Partial Approval | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 4/24/2020 | Partial Approval | RONALD PACHECO |
| Footing/Foundation/Slab | 4/24/2020 | Partial Approval | RONALD PACHECO |
| Deputy Reinf. Concrete | 4/27/2020 | Conditional Approval | LESLIE TRUJILLO |
| Deputy Reinf. Masonry | 4/29/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 5/4/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 5/5/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 5/6/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 5/13/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 5/15/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 5/20/2020 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 5/29/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Masonry | 6/1/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Steel/Welding | 7/6/2020 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 7/8/2020 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 7/13/2020 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 7/14/2020 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 7/20/2020 | Partial Approval | JAMES POWERS |
| Green Building Rough | 7/24/2020 | Approved | JAMES POWERS |
| Structural Steel Frame | 7/24/2020 | Partial Approval | JAMES POWERS |
| Verify Sprinkler Sign Off | 7/24/2020 | Not Ready for Inspection | JAMES POWERS |
| Deputy Steel/Welding | 8/3/2020 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 8/7/2020 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2020 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 9/8/2020 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 9/15/2020 | Approved | JAMES POWERS |
| Drywall Nailing | 9/28/2020 | Approved | JAMES POWERS |
| Interior/Exterior Lathing | 10/20/2020 | Not Ready for Inspection | JAMES POWERS |
| Interior/Exterior Lathing | 10/23/2020 | Approved | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 12/14/2020 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 12/31/2020 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 1/5/2021 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 2/8/2021 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 3/9/2021 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 4/5/2021 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 5/13/2021 | Partial Approval | JAMES POWERS |
| Final | 9/27/2022 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 9/27/2022 | Approved | JAMES POWERS |
| Green Building Final | 9/27/2022 | Approved | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 9/27/2022 | SGSOV No Gas | JAMES POWERS |
| Smoke Detectors | 9/27/2022 | Approved | JAMES POWERS |
| Structural Steel Frame | 9/27/2022 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 9/27/2022 | Approved | JAMES POWERS |
| Wood Frame | 9/27/2022 | Not Ready for Inspection | JAMES POWERS |
| Final | 10/27/2022 | OK to Issue CofO | JAMES POWERS |
| Structural Steel Frame | 10/27/2022 | Approved | JAMES POWERS |
| Wood Frame | 10/27/2022 | Approved | JAMES POWERS |