2110 S BARRY AVE 90025
Certificate Information: 2110 S BARRY AVE 90025
- Application / Permit
- 18010-10000-02761
- Plan Check / Job No.
- B18LA11417
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AT REAR.
- Permit Issued
- Issued on 5/10/2022
- Issuing Office
- Current Status
- CofO Issued on 11/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/7/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/5/2018 | KEVIN MORALES |
| Corrections Issued | 7/17/2018 | ANA AVELAR |
| Quality Review Completed | 7/18/2018 | SIAVOSH POURSABAHIAN |
| Green Plans Picked Up | 7/27/2018 | APPLICANT |
| Applicant returned to address corrections | 9/4/2019 | RAHEL BEYENE |
| Applicant returned to address corrections | 1/6/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 12/8/2021 | KEVIN MORALES |
| Plan Check Approved | 3/25/2022 | KEVIN MORALES |
| Issued | 5/10/2022 | APPLICANT |
| Building Plans Picked Up | 5/19/2022 | APPLICANT |
| CofO in Progress | 11/20/2025 | DAVID FEILER |
| Permit Finaled | 11/21/2025 | RICHARD STEINBACH |
| CofO Issued | 11/21/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/21/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Green Code | Cleared | 12/4/2018 | ANA AVELAR |
| Address approval | Cleared | 7/18/2019 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2019 | JOHN LIN |
| Miscellaneous | Cleared | 7/18/2019 | JOHN LIN |
| Permit | Cleared | 7/18/2019 | JOHN LIN |
| Sewer availability | Cleared | 7/18/2019 | JOHN LIN |
| Hydrant and Access approval | Cleared | 8/14/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 9/3/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 9/3/2019 | ELAINE LEI |
| ZA Case | Cleared | 6/30/2021 | LAUREN PADICK |
| Specific Plan | Cleared | 11/15/2021 | KEVIN ARUCAN |
| Tract Map conditions | Cleared | 2/9/2022 | LAUREN PADICK |
Contact Information
| Contractor | Ornelas Construction Inc; Lic. No.: 925494-C21 | P O BOX 922735 SYLMAR, CA 91342 |
| Engineer | Kim, Taewon; Lic. No.: C80632 | 23105 MADISON ST 114 TORRANCE, CA 90505 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/22/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 7/21/2022 | Corrections Issued | JOHN KIDWELL |
| Footing/Foundation/Slab | 2/16/2023 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| PLUMBING-Rough | 3/2/2023 | Approved | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2023 | Corrections Issued | CLAYTON GRAHAM |
| Wood Frame | 3/9/2023 | Corrections Issued | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2023 | Partial Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2023 | Approved | JESUS PINEDA |
| Green Building Rough | 5/18/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 5/18/2023 | Partial Approval | JESUS PINEDA |
| Verify Sprinkler Sign Off | 5/18/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 5/19/2023 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Rough | 5/19/2023 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 5/30/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 5/30/2023 | Conditional Approval | JESUS PINEDA |
| Insulation | 6/5/2023 | Approved | RICHARD STEINBACH |
| Shower Pan | 6/5/2023 | Approved | RICHARD STEINBACH |
| Interior/Exterior Lathing | 6/9/2023 | Approved | JESUS PINEDA |
| Sewer | 6/9/2023 | Partial Approval | JESUS PINEDA |
| Drywall Nailing | 7/13/2023 | Approved | JEREMY TODD |
| Sewer | 10/26/2023 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 11/3/2023 | Partial Approval | CARLOS MATAMOROS |
| Gas Test | 11/3/2023 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 11/3/2023 | SGSOV Not Ready | CARLOS MATAMOROS |
| Sewer | 11/3/2023 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 3/27/2024 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Final | 3/27/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 4/10/2024 | Approved | KENNETH NAGLE |
| HVAC-Final | 4/10/2024 | Approved | KENNETH NAGLE |
| Service/Power Release | 5/1/2024 | Approved | KENNETH NAGLE |
| Gas Test | 5/22/2024 | Approved | KIRK SANDERS |
| PLUMBING-Final | 5/22/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 5/24/2024 | Approved | KIRK SANDERS |
| Final | 1/31/2025 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 1/31/2025 | Approved | KIRK SANDERS |
| Green Building Final | 1/31/2025 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 1/31/2025 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 1/31/2025 | Approved | KIRK SANDERS |
| Final | 2/4/2025 | Partial Approval | KIRK SANDERS |
| Final | 11/20/2025 | OK to Issue CofO | DAVID FEILER |