1010 N SEWARD ST 90038

Certificate Information: 1010 N SEWARD ST 90038

Application / Permit
18010-10000-02705
Plan Check / Job No.
B18LA11224
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(8) Parking Building
Work Description
NEW 6 STORY ( 7 TIERS) PARKING STRUCTURE.
Permit Issued
Issued on 10/18/2018
Issuing Office
Metro
Current Status
CofO Issued on 10/15/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/6/2018 APPLICANT
Disabled Access Plans Picked Up 6/20/2018 APPLICANT
Green Plans Picked Up 6/22/2018 APPLICANT
Assigned to Plan Check Engineer 6/28/2018 GARO TELMI
Corrections Issued 7/9/2018 GARO TELMI
Quality Review Completed 7/9/2018 JOHN FRANCIA
Building Plans Picked Up 7/12/2018 APPLICANT
Applicant returned to address corrections 7/31/2018 GARO TELMI
Applicant returned to address corrections 8/9/2018 GARO TELMI
Applicant returned to address corrections 8/22/2018 GARO TELMI
Applicant returned to address corrections 9/6/2018 GARO TELMI
Plan Check Approved 10/12/2018 GARO TELMI
Issued 10/18/2018 LADBS
CofO in Progress 10/15/2020 LARRY ARNICK
CofO Issued 10/15/2020 TERRY HERR
Permit Finaled 10/15/2020 TERRY HERR

Permit Application Clearance Information

Address approval Cleared 7/23/2018 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 7/23/2018 ADRIAN SANCHEZ
Sewer availability Cleared 7/23/2018 ADRIAN SANCHEZ
Highway dedication Cleared 7/30/2018 MICHAEL CASTILLO
Hydrant and Access approval Cleared 8/31/2018 JOHN CONNEALLY
Construction near power lines Cleared 9/5/2018 WALTER RAMIREZ
Encroachment in public way Cleared 9/7/2018 KAREN LE
Green Code Cleared 9/10/2018 GARO TELMI
Low Impact Development Cleared 9/25/2018 ORVAL HERNANDEZ-MARCI
Internal circulation Cleared 9/26/2018 MOHAMMAD HASAN
Roof/Waste drainage to street Cleared 9/27/2018 SOPHEA EK
Permit Cleared 9/28/2018 LINDA MARGARET
City Hist. Cultural Monument Cleared 10/4/2018 LAMBERT GIESSINGER
DAS Clearance Cleared 10/4/2018 ELIZABETH TOMS
ZI Cleared 10/4/2018 EDBER MACEDO
Frnt yard landscape/Water mgmt Cleared 10/9/2018 EDBER MACEDO
Miscellaneous Cleared 10/9/2018 EDBER MACEDO
Site Plan review Cleared 10/9/2018 EDBER MACEDO
ZA Case Cleared 10/9/2018 EDBER MACEDO
Work Adjacent to Public Way Cleared 10/10/2018 BOK GOH
Building over 3-story or 36-ft Cleared 10/12/2018 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 10/12/2018 CALOSHA APPROVED

Contact Information

Architect Choate, John Richard; Lic. No.: C20781 16969 VON KARMAN SUITE 230      IRVINE, CA 92606
Contractor Parkco Building Company; Lic. No.: 982113-B 3190-F AIRPORT LOOP DR      COSTA MESA, CA 92626
Engineer , ; Lic. No.: C43969 15790 RANCHO VIEJO DR.      REVERSIDE, CA 92506
Engineer , ; Lic. No.: C56178 439 WESTERN AVE.      GLENDALE, CA 91201
Engineer , ; Lic. No.: C75902 700 S. FLOWER ST   2100    LA, CA 90017
Engineer , ; Lic. No.: L8912 2603 MAIN ST   400    IRVINE, CA 92614
Engineer Waggoner, Michael Alan; Lic. No.: S3738 10641 BENT TREE RD      SANTA ANA, CA 92705

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 12/20/2018 Approved TED RIES
Deputy Reinf. Concrete 1/3/2019 Approved TED RIES
Footing/Foundation/Slab 1/3/2019 Partial Approval TED RIES
METHANE-Barrier 1/3/2019 Approved TED RIES
METHANE-Subgrade 1/3/2019 Approved TED RIES
Pre-Inspection 1/3/2019 Approved TED RIES
Deputy Reinf. Concrete 1/4/2019 Approved TED RIES
Deputy Reinf. Concrete 1/7/2019 No Access for Inspection TED RIES
Deputy Reinf. Concrete 1/24/2019 Approved TED RIES
Piling/Pier/Caisson 1/24/2019 Conditional Approval TED RIES
Footing/Foundation/Slab 1/28/2019 Partial Approval TED RIES
Deputy Reinf. Concrete 1/29/2019 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 2/11/2019 Partial Approval TED RIES
Footing/Foundation/Slab 2/25/2019 Partial Approval GREGORY POMISH
Reinforced Concrete Frame 2/25/2019 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 2/26/2019 Approved TED RIES
Reinforced Concrete Frame 2/27/2019 Partial Approval TED RIES
Deputy Reinf. Concrete 3/1/2019 Approved TED RIES
Footing/Foundation/Slab 3/5/2019 Partial Approval TED RIES
Excavation/Setback/Form/Re-Bar 3/11/2019 Partial Approval TED RIES
Reinforced Concrete Frame 3/12/2019 Partial Approval TED RIES
Deputy Reinf. Concrete 3/13/2019 No Access for Inspection TED RIES
Footing/Foundation/Slab 3/15/2019 Partial Approval TED RIES
Green Building Rough 3/18/2019 Not Ready for Inspection TED RIES
METHANE-Rough 3/18/2019 Not Ready for Inspection TED RIES
Reinforced Masonry Frame 3/18/2019 Partial Approval TED RIES
Verify Sprinkler Sign Off 3/18/2019 Not Ready for Inspection TED RIES
Reinforced Concrete Frame 3/19/2019 Partial Approval TED RIES
Footing/Foundation/Slab 3/26/2019 Partial Approval TED RIES
Reinforced Concrete Frame 3/29/2019 Not Ready for Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 4/1/2019 Partial Approval JEFF BYTHEWAY
Footing/Foundation/Slab 4/4/2019 Partial Approval TED RIES
Deputy Reinf. Concrete 4/5/2019 Approved TED RIES
Footing/Foundation/Slab 4/22/2019 Partial Approval TED RIES
Footing/Foundation/Slab 4/29/2019 Conditional Approval TED RIES
Deputy Reinf. Concrete 4/30/2019 Approved TED RIES
Reinforced Concrete Frame 4/30/2019 Partial Approval TED RIES
Reinforced Concrete Frame 5/2/2019 Partial Approval TED RIES
Piling/Pier/Caisson 5/7/2019 Partial Approval TED RIES
Reinforced Concrete Frame 5/7/2019 Partial Approval TED RIES
Reinforced Concrete Frame 5/15/2019 Not Ready for Inspection TED RIES
Footing/Foundation/Slab 5/16/2019 Partial Approval TED RIES
Deputy Reinf. Concrete 5/17/2019 Approved TED RIES
Reinforced Concrete Frame 5/29/2019 Partial Approval TED RIES
Footing/Foundation/Slab 5/30/2019 Not Ready for Inspection TED RIES
Deputy Reinf. Concrete 6/4/2019 Approved TED RIES
Footing/Foundation/Slab 6/4/2019 Partial Approval TED RIES
Reinforced Concrete Frame 6/12/2019 Partial Approval TED RIES
Footing/Foundation/Slab 6/13/2019 Partial Approval TED RIES
Deputy Reinf. Concrete 6/14/2019 Approved TED RIES
Green Building Rough 6/21/2019 Not Ready for Inspection JAMES POWERS
METHANE-Rough 6/21/2019 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 6/21/2019 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 6/21/2019 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 6/25/2019 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 6/26/2019 Conditional Approval DANIEL MC AULIFFE
Green Building Rough 6/26/2019 Approved DANIEL MC AULIFFE
METHANE-Rough 6/26/2019 Approved DANIEL MC AULIFFE
Reinforced Masonry Frame 6/26/2019 Partial Approval DANIEL MC AULIFFE
Verify Sprinkler Sign Off 6/26/2019 Approved DANIEL MC AULIFFE
Reinforced Masonry Frame 7/3/2019 Partial Approval LARRY ARNICK
Reinforced Concrete Frame 7/8/2019 Partial Approval LARRY ARNICK
Footing/Foundation/Slab 7/9/2019 Partial Approval LARRY ARNICK
Reinforced Masonry Frame 7/11/2019 Partial Approval LARRY ARNICK
Reinforced Concrete Frame 7/18/2019 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 7/22/2019 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 7/22/2019 Partial Approval LARRY ARNICK
Reinforced Masonry Frame 8/6/2019 Partial Inspection LARRY ARNICK
Reinforced Concrete Frame 8/12/2019 Partial Approval LARRY ARNICK
Reinforced Masonry Frame 8/12/2019 Partial Approval LARRY ARNICK
Footing/Foundation/Slab 8/14/2019 Partial Approval LARRY ARNICK
Reinforced Masonry Frame 8/15/2019 Partial Approval LARRY ARNICK
Reinforced Masonry Frame 8/20/2019 Partial Approval LARRY ARNICK
Reinforced Masonry Frame 8/26/2019 Partial Approval JEFF BYTHEWAY
Reinforced Concrete Frame 8/27/2019 Corrections Issued LARRY ARNICK
Reinforced Masonry Frame 8/28/2019 Partial Approval LARRY ARNICK
Footing/Foundation/Slab 8/29/2019 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 9/3/2019 Conditional Approval LARRY ARNICK
Reinforced Masonry Frame 9/9/2019 Not Ready for Inspection LARRY ARNICK
Masonry Wall/Backfill 9/10/2019 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 9/11/2019 Partial Approval DANIEL MC AULIFFE
Reinforced Concrete Frame 9/11/2019 Partial Approval DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 9/12/2019 Off-Hour Fees Due
Reinforced Concrete Frame 9/12/2019 Partial Approval DANIEL MC AULIFFE
Reinforced Masonry Frame 9/16/2019 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 9/23/2019 Partial Approval LARRY ARNICK
Reinforced Masonry Frame 9/23/2019 Partial Approval LARRY ARNICK
Footing/Foundation/Slab 9/24/2019 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 9/25/2019 Partial Approval DANIEL MC AULIFFE
Deputy Pre-Stress Concrete 10/7/2019 Conditional Approval LARRY ARNICK
Footing/Foundation/Slab 10/7/2019 Partial Approval LARRY ARNICK
Footing/Foundation/Slab 10/11/2019 Partial Approval LARRY ARNICK
Reinforced Masonry Frame 10/17/2019 Partial Approval LARRY ARNICK
Reinforced Masonry Frame 10/21/2019 Partial Approval LARRY ARNICK
Reinforced Concrete Frame 10/24/2019 Partial Approval DANIEL MC AULIFFE
Reinforced Masonry Frame 10/29/2019 Partial Approval LARRY ARNICK
Footing/Foundation/Slab 11/19/2019 Partial Approval LARRY ARNICK
Reinforced Masonry Frame 11/22/2019 Approved LARRY ARNICK
Structural Steel Frame 12/6/2019 Not Ready for Inspection LARRY ARNICK
Structural Steel Frame 12/13/2019 Partial Approval LARRY ARNICK
Structural Steel Frame 12/18/2019 Approved LARRY ARNICK
Verify Rec and Parks Fee Memo 2/20/2020 Approved LARRY ARNICK
Final 9/17/2020 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 9/17/2020 Approved LARRY ARNICK
Green Building Final 9/17/2020 Not Ready for Inspection LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 9/17/2020 SGSOV No Gas LARRY ARNICK
Smoke Detectors 9/17/2020 Approved LARRY ARNICK
Special/Order Compliance 9/18/2020 Approved LARRY ARNICK
Final 9/21/2020 Conditional Approval LARRY ARNICK
Green Building Final 9/21/2020 Approved LARRY ARNICK