2133-2133 1/2 S CARMONA AVE 90016

Certificate Information: 2133-2133 1/2 S CARMONA AVE 90016

Application / Permit
18010-10000-02652
Plan Check / Job No.
B18LA09160
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3 STORY DUPLEX REAR BUILDING
Permit Issued
Issued on 1/7/2019
Issuing Office
South Los Angeles
Current Status
CofO Corrected on 2/9/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/9/2018 APPLICANT
Green Plans Picked Up 5/17/2018 APPLICANT
Assigned to Plan Check Engineer 5/31/2018 MOHAMMAD FIROUZBAKHT
Corrections Issued 6/5/2018 MOHAMMAD FIROUZBAKHT
Quality Review Completed 6/5/2018 DAVID CHANG
Building Plans Picked Up 6/6/2018 APPLICANT
Plan Check Approved 10/19/2018 MOHAMMAD FIROUZBAKHT
Issued 1/7/2019 LADBS
CofO in Progress 7/1/2020 MATTHEW NUCKOLLS
CofO Issued-Status Void 7/1/2020 DEROLD HAUFF
Permit Finaled-Status Void 7/1/2020 DEROLD HAUFF
Re-Activate Permit 1/28/2021 DEROLD HAUFF
Permit Finaled 2/9/2021 DEROLD HAUFF
CofO Corrected 2/9/2021 DEROLD HAUFF
Permit Finaled 2/9/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/7/2018 NAZILA NOORIFAR
Permit Cleared 6/7/2018 NAZILA NOORIFAR
Eng Process Fee Ord 176,300 Cleared 6/8/2018 CARLA VALLADARES
Sewer availability Cleared 6/8/2018 CARLA VALLADARES
Green Code Cleared 6/25/2018 COLIN LOREDO
Low Impact Development Cleared 7/2/2018 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 7/13/2018 CELINA MORENO
Hydrant and Access approval Cleared 8/29/2018 GILBERT URREA

Contact Information

Contractor Baksh Construction Inc; Lic. No.: 910533-B 4 HILCREST MANOR      ROLLING HILLS ESTATES, CA 90274
Engineer , ; Lic. No.: GE773 60 HACKAMORE LN      BELL CANYON, CA 91307
Engineer , ; Lic. No.: S5682 1201 N YECINO LN      PLACENTIA, CA 92870

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/28/2019 Partial Approval KATHRYN BUTTERWORTH
Footing/Foundation/Slab 3/19/2019 Corrections Issued KATHRYN BUTTERWORTH
Footing/Foundation/Slab 3/21/2019 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 5/7/2019 Partial Approval MATTHEW NUCKOLLS
Floor/Roof Diaphrgm/Shear Wall 5/13/2019 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 8/12/2019 Corrections Issued ELMER BLAND
ELECTRICAL-Rough 8/12/2019 Not Ready for Inspection ELMER BLAND
Floor/Roof Diaphrgm/Shear Wall 8/12/2019 Corrections Issued ELMER BLAND
Green Building Rough 8/12/2019 Approved ELMER BLAND
Verify Sprinkler Sign Off 8/12/2019 Not Ready for Inspection ELMER BLAND
HVAC-Rough 8/13/2019 Partial Inspection RUBEN SALAS
PLUMBING-Rough 8/13/2019 Corrections Issued RUBEN SALAS
ELECTRICAL-Rough 8/14/2019 Corrections Issued ELMER BLAND
PLUMBING-Rough 8/16/2019 Approved KATHRYN BUTTERWORTH
HVAC-Rough 8/19/2019 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Rough 8/23/2019 Corrections Issued KATHRYN BUTTERWORTH
Wood Frame 8/23/2019 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 9/12/2019 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 9/12/2019 Approved KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 9/12/2019 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 9/23/2019 Approved PAUL BECKER
Insulation 9/26/2019 Not Ready for Inspection KATHRYN BUTTERWORTH
Special/Order Compliance 9/26/2019 Approved ELMER BLAND
Insulation 9/30/2019 Approved ELMER BLAND
Special/Order Compliance 9/30/2019 Approved HENRY KIM
Drywall Nailing 10/15/2019 Approved HENRY KIM
Interior/Exterior Lathing 10/15/2019 Approved HENRY KIM
ELECTRICAL-Final 4/7/2020 Corrections Issued DAVID CHAN
Gas Test 4/7/2020 Approved DAVID CHAN
Service/Power Release 4/7/2020 Corrections Issued DAVID CHAN
Final 4/24/2020 Not Ready for Inspection DAVID CHAN
SGSOV-Seismic Gas S/O Valve 4/24/2020 SGSOV Not Ready DAVID CHAN
ELECTRICAL-Final 5/11/2020 Approved MATTHEW NUCKOLLS
Final 5/11/2020 Conditional Approval MATTHEW NUCKOLLS
Green Building Final 5/11/2020 Approved MATTHEW NUCKOLLS
HVAC-Final 5/11/2020 Approved MATTHEW NUCKOLLS
PLUMBING-Final 5/11/2020 Approved MATTHEW NUCKOLLS
SGSOV-Seismic Gas S/O Valve 5/11/2020 SGSOV Approved MATTHEW NUCKOLLS
Service/Power Release 5/11/2020 Approved MATTHEW NUCKOLLS
Smoke Detectors 5/11/2020 Approved MATTHEW NUCKOLLS
Service/Power Release 5/28/2020 Approved MATTHEW NUCKOLLS