1409 N BATES AVE 90027

Certificate Information: 1409 N BATES AVE 90027

Application / Permit
18010-10000-02625
Plan Check / Job No.
B18LA10869
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 3-story single family dwelling w/ attached 2-car garage in small-lot subdivision pursuant to Tentative Tract Map No./Preliminary Map No. VTT-map- 78234-SL. A Certificate of Occupancy (temporary or final ) shall not be issued until after the final map has been recorded.
Permit Issued
Issued on 2/15/2019
Issuing Office
Metro
Current Status
Issued on 2/15/2019
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/1/2018 APPLICANT
Assigned to Plan Check Engineer 6/28/2018 ZAW HAN
Corrections Issued 7/5/2018 ZAW HAN
Quality Review Completed 7/11/2018 HERNAN ARREOLA
Building Plans Picked Up 7/31/2018 APPLICANT
Green Plans Picked Up 7/31/2018 APPLICANT
Applicant returned to address corrections 9/11/2018 ZAW HAN
Applicant returned to address corrections 9/27/2018 ZAW HAN
Applicant returned to address corrections 10/12/2018 ZAW HAN
Applicant returned to address corrections 11/6/2018 ZAW HAN
Applicant returned to address corrections 12/11/2018 ZAW HAN
Applicant returned to address corrections 12/14/2018 ZAW HAN
Plan Check Approved 1/4/2019 ZAW HAN
Plan Check Approved 2/15/2019 ZAW HAN
Issued 2/15/2019 LADBS

Permit Application Clearance Information

Miscellaneous Cleared 8/9/2018 DIANA JIMENEZ
ZA Case Cleared 8/9/2018 DIANA JIMENEZ
Eng Process Fee Ord 176,300 Cleared 8/17/2018 KARAN PATEL
Address approval Cleared 8/23/2018 STEVE MELGAR
Address approval Cleared 8/23/2018 STEVE MELGAR
Green Code Cleared 8/24/2018 Zaw Han
Hydrant and Access approval Cleared 8/27/2018 ROBERT DUFF
Building over 3-story or 36-ft Cleared 9/11/2018 CALOSHA APPROVED
Sewer availability Cleared 10/12/2018 MICHAEL CASTILLO
Low Impact Development Cleared 11/1/2018 MITESH PATEL
Miscellaneous Cleared 12/5/2018 SOPHEA EK
Permit Cleared 12/5/2018 SOPHEA EK
Frnt yard landscape/Water mgmt Cleared 12/7/2018 LATANYA ROUX
Highway dedication Cleared 12/7/2018 NAZILA NOORIFAR
Miscellaneous Cleared 12/7/2018 LATANYA ROUX
Roof/Waste drainage to street Cleared 12/7/2018 TERRY PHAN
GPI Written Notices Cleared 12/11/2018 ROBERT HUGHES
Grading Pre-Inspection Cleared 12/11/2018 ROBERT HUGHES

Contact Information

Architect , ; Lic. No.: C9147 5931 OAKDALE AVENUE      WOODLAND HILLS, CA 91367
Contractor Ayala Development Inc; Lic. No.: 1006608-B 13300 VICTORY BLVD SUITE 507      VALLEY GLEN, CA 91401
Engineer Jiang, Clarence Tzu-Wei; Lic. No.: GE2477 PO BOX 1891      WEST COVINA, CA 91793
Engineer Salem, Rifaat Sammy; Lic. No.: GE2549 4195 W SAMPLE AVE      FRESNO, CA 93722
Engineer Truong, Phong Lap; Lic. No.: C70784 20754 TIMBERLINE LN      WALNUT, CA 91789
Engineer Tsalyuk, Yefim; Lic. No.: L7421 11278 LOS ALAMITOS BLVD 354      LOS ALAMITOS, CA 90720

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/12/2021 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 5/12/2021 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 5/27/2021 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 5/27/2021 Partial Approval SCOTT FINNILA
PLUMBING-Rough 5/27/2021 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 6/4/2021 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 6/8/2021 Partial Approval SCOTT FINNILA
Special/Order Compliance 7/20/2022 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/16/2022 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/20/2022 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/7/2022 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/27/2022 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/30/2022 Corrections Issued ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 2/22/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Sewer 4/18/2023 Corrections Issued ALIZAH MAYAGOITIA
Underground Mechanical 5/8/2023 Partial Approval ALIZAH MAYAGOITIA
Underground Mechanical 5/11/2023 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 5/18/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 7/20/2023 Corrections Issued ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 9/20/2023 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 9/21/2023 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 10/27/2023 Partial Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 10/27/2023 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 11/3/2023 Partial Approval ALIZAH MAYAGOITIA
HVAC-Rough 12/5/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Rough 12/8/2023 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 12/12/2023 Approved ALIZAH MAYAGOITIA
Green Building Rough 12/12/2023 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 12/12/2023 Approved ALIZAH MAYAGOITIA
Insulation 12/22/2023 Approved ALIZAH MAYAGOITIA
Shower Pan 12/27/2023 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 12/29/2023 Approved ALIZAH MAYAGOITIA
Drywall Nailing 1/10/2024 Approved ALIZAH MAYAGOITIA
Pre-Inspection 4/19/2024 Corrections Issued JOSEPH MCGARRY
Underground Mechanical 6/28/2024 Partial Approval BRENDAN MORELLI
ELECTRICAL-Final 8/12/2024 Corrections Issued BRENDAN MORELLI
Special/Order Compliance 2/6/2025 Corrections Issued BRENDAN MORELLI
Special/Order Compliance 4/3/2025 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Final 12/9/2025 Corrections Issued NICHOLAS LOPEZ
ELECTRICAL-Final 1/5/2026 Approved NICHOLAS LOPEZ
Special/Order Compliance 1/5/2026 Corrections Issued NICHOLAS LOPEZ
ELECTRICAL-Final 2/25/2026 Approved NICHOLAS LOPEZ
HVAC-Final 5/20/2026 Approved BRENDAN MORELLI
PLUMBING-Final 5/20/2026 Approved BRENDAN MORELLI