9703-9703 1/2 S COMPTON AVE 90002
Certificate Information: 9703-9703 1/2 S COMPTON AVE 90002
- Application / Permit
- 18010-10000-02610
- Plan Check / Job No.
- B18LA10841
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW DETACHED 2-CAR GARAGE **2 OF 2**
- Permit Issued
- Issued on 1/22/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 7/5/2018 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 7/16/2018 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 7/17/2018 | SIAVOSH POURSABAHIAN |
| Building Plans Picked Up | 7/30/2018 | APPLICANT |
| Green Plans Picked Up | 7/30/2018 | APPLICANT |
| Plan Check Approved | 1/22/2020 | FARSHAD ALIMOHAMADI |
| Issued | 1/22/2020 | LADBS |
| CofO in Progress | 12/31/2020 | ANSON MAGLASANG |
| Permit Finaled | 1/2/2021 | DEROLD HAUFF |
| CofO Issued | 1/2/2021 | DEROLD HAUFF |
| Permit Finaled | 1/2/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 9/19/2018 | KHEDER ALRAZAA |
| Eng Process Fee Ord 176,300 | Cleared | 1/18/2019 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 1/18/2019 | ADRIAN SANCHEZ |
Contact Information
| Contractor | F S Z Bros General Contractors Inc; Lic. No.: 794097-B | 7320 FIRESTONE BLVD #208 DOWNEY, CA 90241 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 26851 GRAYSLAKE ROAD RANCHO PALOS VERDES, CA 90275 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/13/2020 | Approved | WILLIAM ROSE |
| Footing/Foundation/Slab | 2/20/2020 | Approved | WILLIAM ROSE |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2020 | No Access for Inspection | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2020 | Partial Approval | BRIAN CHRISTIAN |
| BUILDING-Rough-Frame | 5/11/2020 | Approved | EUGENE CASSIDY |
| Green Building Rough | 5/11/2020 | Approved | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 5/11/2020 | Approved | EUGENE CASSIDY |
| Verify Rec and Parks Fee Memo | 5/11/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Insulation | 5/15/2020 | Approved | BRIAN CHRISTIAN |
| Drywall Nailing | 5/28/2020 | Approved | BRIAN CHRISTIAN |
| Interior/Exterior Lathing | 5/28/2020 | Approved | BRIAN CHRISTIAN |
| Final | 11/18/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 11/18/2020 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 11/18/2020 | SGSOV Not Required | EUGENE CASSIDY |
| Service/Power Release | 11/18/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 11/18/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 12/14/2020 | Approved | EUGENE CASSIDY |
| Final | 12/14/2020 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 12/14/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 12/14/2020 | Approved | EUGENE CASSIDY |
| Service/Power Release | 12/14/2020 | Approved | EUGENE CASSIDY |