9631 S COMPTON AVE 90002

Certificate Information: 9631 S COMPTON AVE 90002

Application / Permit
18010-10000-02604
Plan Check / Job No.
B18LA10839
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 2-STORY SFD. WITH ATTACHED GARAGE.
Permit Issued
Issued on 9/11/2020
Issuing Office
Current Status
CofO Issued on 6/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2018 APPLICANT
Assigned to Plan Check Engineer 6/28/2018 FARSHAD ALIMOHAMADI
Corrections Issued 7/13/2018 FARSHAD ALIMOHAMADI
Quality Review Completed 7/17/2018 SIAVOSH POURSABAHIAN
Green Plans Picked Up 7/23/2020 APPLICANT
Applicant returned to address corrections 9/3/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 9/10/2020 FARSHAD ALIMOHAMADI
Plan Check Approved 9/11/2020 FARSHAD ALIMOHAMADI
Issued 9/11/2020 APPLICANT
Building Plans Picked Up 9/21/2020 APPLICANT
CofO in Progress 4/26/2021 EUGENE CASSIDY
Permit Finaled 6/4/2021 DEROLD HAUFF
CofO Issued 6/4/2021 DEROLD HAUFF
Permit Finaled 6/4/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/19/2018 MICHAEL CASTILLO
Eng Process Fee Ord 176,300 Cleared 9/19/2018 ADRIAN SANCHEZ
Green Code Cleared 9/19/2018 SARAH ABOULHOSN
Permit Cleared 9/19/2018 ADRIAN SANCHEZ
Sewer availability Cleared 9/19/2018 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 1/18/2019 ADRIAN SANCHEZ
Grading in hillside Cleared 1/18/2019 MOTOUMI SASAKI
Historic monument Cleared 1/18/2019 MOTOUMI SASAKI
Low Impact Development Cleared 1/18/2019 MARTIN FRAGOSO
Low Impact Development Cleared 1/18/2019 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 1/18/2019 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 1/18/2019 ADRIAN SANCHEZ
ZA Case Cleared 1/18/2019 MOTOUMI SASAKI
Hydrant and Access approval Cleared 6/15/2020 MATTHEW CRAIG
ZI Cleared 6/16/2020 SARAHI ORTEGA

Contact Information

Contractor F S Z Bros General Contractors Inc; Lic. No.: 794097-B 7320 FIRESTONE BLVD #208      DOWNEY, CA 90241
Engineer Dorta, Michael Rohrs; Lic. No.: C72538 26851 GRAYSLAKE ROAD      RANCHO PALOS VERDES, CA 90275

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/29/2020 Conditional Approval EUGENE CASSIDY
Footing/Foundation/Slab 10/5/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/27/2020 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 11/9/2020 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 11/9/2020 Partial Approval EUGENE CASSIDY
Green Building Rough 11/9/2020 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 11/9/2020 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 11/9/2020 Corrections Issued EUGENE CASSIDY
Verify Sprinkler Sign Off 11/9/2020 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 11/16/2020 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 11/16/2020 Approved EUGENE CASSIDY
HVAC-Rough 11/16/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 11/16/2020 Approved EUGENE CASSIDY
Insulation 11/24/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 11/24/2020 Approved EUGENE CASSIDY
Drywall Nailing 12/4/2020 Approved EUGENE CASSIDY
Green Building Rough 12/4/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 12/4/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 3/5/2021 Not Ready for Inspection EUGENE CASSIDY
Final 3/5/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 3/5/2021 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 3/5/2021 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 3/5/2021 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 3/5/2021 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 3/5/2021 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 4/21/2021 Approved EUGENE CASSIDY
Final 4/21/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 4/21/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 4/21/2021 SGSOV Approved EUGENE CASSIDY
Service/Power Release 4/21/2021 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 4/21/2021 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 4/21/2021 Approved EUGENE CASSIDY
ELECTRICAL-Final 4/23/2021 Approved EUGENE CASSIDY
Final 4/23/2021 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 4/23/2021 Approved EUGENE CASSIDY
PLUMBING-Final 4/23/2021 Approved EUGENE CASSIDY
Service/Power Release 4/23/2021 Approved EUGENE CASSIDY