689 S CATALINA ST 90005

Certificate Information: 689 S CATALINA ST 90005

Application / Permit
18010-10000-02473
Plan Check / Job No.
B18LA10431
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
PROPOSED 8 STORY OVER 2 BASEMENT LEVELS MIXED USE BLDG. APARTMENT, RETAIL AND PARKING PER ZA 2017-4204 ZAA SPR GLASS GUARDRAILS ARE DEFERRED
Permit Issued
Issued on 12/31/2019
Issuing Office
Metro
Current Status
CofO Issued on 3/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2018 APPLICANT
Assigned to Plan Check Engineer 6/28/2018 JOHN VASQUEZ
Corrections Issued 7/2/2018 JOHN VASQUEZ
Quality Review Completed 7/5/2018 CHARLES CHANG
Applicant returned to address corrections 11/7/2018 JOHN VASQUEZ
Applicant returned to address corrections 11/16/2018 JOHN VASQUEZ
Applicant returned to address corrections 11/28/2018 JOHN VASQUEZ
Applicant returned to address corrections 12/14/2018 JOHN VASQUEZ
Plan Check Approved 3/8/2019 JOHN VASQUEZ
Issued 12/31/2019 LADBS
TCO Issued (Expire Date: 04-14-2024) 10/17/2023 ERNESTO CORRAL
CofO Issued 3/18/2024 ERNESTO CORRAL
Permit Finaled 3/18/2024 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 10/15/2018 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 10/15/2018 STEVE MELGAR
Highway dedication Cleared 10/15/2018 STEVE MELGAR
Permit Cleared 10/15/2018 STEVE MELGAR
Project located in CRA area Cleared 11/2/2018 JIM URQUHART
Driveway location Cleared 11/8/2018 EDUARDO HERMOSO
Internal circulation Cleared 11/8/2018 EDUARDO HERMOSO
Bicycle Parking Cleared 11/13/2018 KAREN LE
Green Code Cleared 11/27/2018 DONALD CRICHLOW
Sewer availability Cleared 12/13/2018 ZIXUAN CHEN
Low Impact Development Cleared 1/31/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 1/31/2019 CELINA MORENO
Stormwater Pollution Mitigatn Cleared 1/31/2019 RYAN HUDSON
Work Adjacent to Public Way Cleared 2/11/2019 CHIU TAM
DAS Clearance Cleared 2/12/2019 JOHN VASQUEZ
Hydrant and Access approval Cleared 2/15/2019 GEORGE SUCHAND
Certificate of Compliance Cleared 2/19/2019 ANNA VAN
Frnt yard landscape/Water mgmt Cleared 2/19/2019 ANNA VAN
Opn space landscape/Water mgmt Cleared 2/19/2019 ANNA VAN
Site Plan review Cleared 2/19/2019 ANNA VAN
ZA Case Cleared 2/19/2019 ANNA VAN
Fire Marshall Fire Life Safety Cleared 2/21/2019 WILLIAM JOHNS
Building over 3-story or 36-ft Cleared 3/8/2019 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 3/8/2019 CALOSHA APPROVED

Contact Information

Architect Fischer,, James Robert; Lic. No.: C32908 17904 HARTLAND STREET      RESEDA, CA 91335
Contractor Wilshire Construction L P; Lic. No.: 1048091-B 3470 WILSHIRE STE 1010      LOS ANGELES, CA 90010
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245
Engineer Larocca,, Francis Joseph; Lic. No.: C75121 1821 PACIFIC COAST HWY 38      HERMOSA BEACH, CA 90254

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/22/2021 Approved RAFAEL ESPINOZA
Deputy Reinf. Concrete 2/24/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 2/25/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 2/26/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/2/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/3/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 3/4/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/12/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 4/12/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/13/2021 Conditional Approval DAVID BURKHEAD
Deputy Steel/Welding 4/14/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/16/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/20/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 4/21/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/28/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/29/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 4/30/2021 Conditional Approval RAFAEL ESPINOZA
Light Gage Steel Frame 4/30/2021 Partial Inspection RAFAEL ESPINOZA
Deputy Steel/Welding 5/10/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 5/11/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 5/13/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/18/2021 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 6/21/2021 Partial Approval JAMES POWERS
METHANE-Barrier 6/21/2021 No Access for Inspection JAMES POWERS
METHANE-Subgrade 6/21/2021 Approved JAMES POWERS
Deputy Reinf. Concrete 6/22/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 7/1/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 7/2/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 7/2/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/2/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 7/6/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/8/2021 Conditional Approval JONATHAN QUACH
Deputy Shotcrete 7/8/2021 Conditional Approval JONATHAN QUACH
Deputy Shotcrete 7/9/2021 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 7/9/2021 Partial Approval RAFAEL ESPINOZA
Deputy Shotcrete 7/12/2021 Conditional Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 7/12/2021 Partial Approval RAFAEL ESPINOZA
Deputy Shotcrete 7/13/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 7/14/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/4/2021 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 8/4/2021 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 8/4/2021 Approved EDWIN GREGORYONA
Deputy Drilled-In Anchors 8/27/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/30/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 8/30/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 9/1/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 9/9/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 9/9/2021 Not Ready for Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 9/10/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 9/13/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 9/14/2021 Partial Approval EDWIN GREGORYONA
Green Building Rough 9/14/2021 Not Ready for Inspection EDWIN GREGORYONA
METHANE-Rough 9/14/2021 Approved EDWIN GREGORYONA
Reinforced Concrete Frame 9/14/2021 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 9/14/2021 Not Ready for Inspection EDWIN GREGORYONA
Deputy Shotcrete 9/15/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 9/16/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 10/5/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 10/6/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 10/6/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 10/7/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 10/8/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 10/14/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 10/18/2021 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 10/18/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 10/19/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 10/19/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 10/20/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 10/20/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 10/21/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 10/21/2021 Not Ready for Inspection EDWIN GREGORYONA
Deputy Shotcrete 10/22/2021 Conditional Approval ERNESTO CORRAL
Excavation/Setback/Form/Re-Bar 10/22/2021 Partial Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 10/25/2021 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Masonry 10/28/2021 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 10/29/2021 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 11/12/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 11/19/2021 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 11/19/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 11/22/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 11/23/2021 Conditional Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 12/1/2021 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 12/1/2021 Partial Approval NICK DANERI
Deputy Reinf. Concrete 12/9/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 12/10/2021 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 12/10/2021 Partial Approval NICK DANERI
Deputy Shotcrete 12/13/2021 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 12/14/2021 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 12/15/2021 Conditional Approval NICK DANERI
Green Building Rough 12/15/2021 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 12/15/2021 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 12/15/2021 Not Ready for Inspection NICK DANERI
Deputy Shotcrete 12/16/2021 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 12/22/2021 Conditional Approval NICK DANERI
Masonry Wall/Backfill 1/7/2022 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 1/19/2022 Partial Approval JAMES POWERS
Footing/Foundation/Slab 1/25/2022 Partial Approval NICK DANERI
Deputy Reinf. Concrete 1/26/2022 Conditional Approval NICK DANERI
Footing/Foundation/Slab 1/26/2022 Partial Approval NICK DANERI
Deputy Reinf. Concrete 2/3/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 2/4/2022 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 2/4/2022 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 2/7/2022 Conditional Approval NICK DANERI
Deputy Drilled-In Anchors 2/25/2022 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 3/1/2022 Not Ready for Inspection NICK DANERI
Deputy Reinf. Concrete 3/2/2022 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 3/2/2022 Partial Approval NICK DANERI
Deputy Reinf. Concrete 3/3/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/4/2022 Conditional Approval NICK DANERI
Deputy Wood Construction 3/29/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 3/29/2022 Partial Approval EDWIN GREGORYONA
Deputy Wood Construction 4/14/2022 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/14/2022 Not Ready for Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/15/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 5/4/2022 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 5/5/2022 Partial Approval NICK DANERI
Deputy Wood Construction 5/18/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 5/18/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 5/24/2022 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Wood Construction 5/25/2022 Conditional Approval TERRY HERR
Deputy Wood Construction 5/25/2022 Conditional Approval WINSTON DUNNING
Floor/Roof Diaphrgm/Shear Wall 5/26/2022 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 6/1/2022 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/3/2022 Partial Approval NICK DANERI
Deputy Wood Construction 6/7/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 6/7/2022 Partial Approval NICK DANERI
Insulation 6/9/2022 Partial Approval NICK DANERI
Deputy Wood Construction 6/15/2022 Conditional Approval NICK DANERI
Deputy Wood Construction 6/16/2022 Conditional Approval NICK DANERI
Insulation 6/16/2022 Partial Approval NICK DANERI
Deputy Wood Construction 6/22/2022 Conditional Approval NICK DANERI
Insulation 6/22/2022 Partial Approval NICK DANERI
Deputy Wood Construction 6/24/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Partial Approval NICK DANERI
Deputy Wood Construction 6/28/2022 Conditional Approval ERNESTO CORRAL
Deputy Wood Construction 7/6/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 7/7/2022 Partial Approval RAFAEL ESPINOZA
Insulation 7/7/2022 Partial Inspection RAFAEL ESPINOZA
Deputy Wood Construction 7/14/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 7/14/2022 Partial Approval NICK DANERI
Insulation 7/25/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Wood Construction 7/29/2022 Conditional Approval WINSTON DUNNING
Deputy Wood Construction 8/1/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 8/4/2022 Partial Approval NICK DANERI
Grading Pre-Inspection 8/11/2022 Not Ready for Inspection NICK DANERI
Insulation 8/11/2022 Partial Approval NICK DANERI
Light Gage Steel Frame 8/25/2022 Partial Approval NICK DANERI
Masonry Wall/Backfill 8/25/2022 Conditional Approval NICK DANERI
Wood Frame 8/29/2022 Partial Approval NICK DANERI
Drywall Nailing 8/31/2022 Partial Approval NICK DANERI
Drywall Nailing 9/19/2022 Partial Approval NICK DANERI
Drywall Nailing 9/22/2022 Conditional Approval BRUCE CAMPBELL
Drywall Nailing 9/28/2022 Not Ready for Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 9/30/2022 Partial Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 10/14/2022 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 10/19/2022 Not Ready for Inspection GREGORY POMISH
Insulation 10/19/2022 Partial Inspection GREGORY POMISH
Interior/Exterior Lathing 10/20/2022 Partial Approval GREGORY POMISH
Insulation 10/26/2022 Partial Approval GREGORY POMISH
Drywall Nailing 10/28/2022 Partial Approval GREGORY POMISH
Drywall Nailing 12/7/2022 Not Ready for Inspection NICK DANERI
Special/Order Compliance 12/7/2022 Partial Inspection NICK DANERI
Drywall Nailing 3/3/2023 Partial Approval NICK DANERI
Special/Order Compliance 3/22/2023 Partial Inspection NICK DANERI
Special/Order Compliance 3/28/2023 Partial Inspection NICK DANERI
Final 5/31/2023 Partial Inspection NICK DANERI
Footing/Foundation/Slab 5/31/2023 Not Ready for Inspection NICK DANERI
Green Building Final 5/31/2023 Not Ready for Inspection NICK DANERI
Green Building Rough 5/31/2023 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 5/31/2023 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 5/31/2023 Not Ready for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 5/31/2023 SGSOV Not Ready NICK DANERI
SUSMP-Std. Urban Storm Water 5/31/2023 Not Ready for Inspection NICK DANERI
Smoke Detectors 5/31/2023 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 5/31/2023 Conditional Approval NICK DANERI
Final 6/13/2023 Partial Inspection GREGORY POMISH
Footing/Foundation/Slab 6/13/2023 Partial Inspection GREGORY POMISH
Green Building Final 6/13/2023 Partial Inspection GREGORY POMISH
Green Building Rough 6/13/2023 Partial Inspection GREGORY POMISH
Reinforced Concrete Frame 6/13/2023 Partial Inspection GREGORY POMISH
Reinforced Masonry Frame 6/13/2023 Partial Inspection GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 6/13/2023 SGSOV Not Ready GREGORY POMISH
SUSMP-Std. Urban Storm Water 6/13/2023 Not Ready for Inspection GREGORY POMISH
Smoke Detectors 6/13/2023 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 6/13/2023 Partial Inspection GREGORY POMISH
Special/Order Compliance 6/22/2023 Partial Inspection NICK DANERI
Final 7/12/2023 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 7/12/2023 Approved GREGORY POMISH
Green Building Final 7/12/2023 Not Ready for Inspection GREGORY POMISH
Green Building Rough 7/12/2023 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 7/12/2023 Not Ready for Inspection GREGORY POMISH
Reinforced Masonry Frame 7/12/2023 Partial Approval GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 7/12/2023 SGSOV Approved GREGORY POMISH
SUSMP-Std. Urban Storm Water 7/12/2023 Not Ready for Inspection GREGORY POMISH
Smoke Detectors 7/12/2023 Not Ready for Inspection GREGORY POMISH
Verify Sprinkler Sign Off 7/12/2023 Partial Inspection GREGORY POMISH
Final 7/14/2023 Not Ready for Inspection NICK DANERI
Green Building Final 7/14/2023 Not Ready for Inspection NICK DANERI
Green Building Rough 7/14/2023 Approved NICK DANERI
Reinforced Concrete Frame 7/14/2023 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 7/14/2023 Not Ready for Inspection NICK DANERI
SUSMP-Std. Urban Storm Water 7/14/2023 Not Ready for Inspection NICK DANERI
Smoke Detectors 7/14/2023 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 7/14/2023 Not Ready for Inspection NICK DANERI
Special/Order Compliance 7/18/2023 Partial Approval NICK DANERI
Final 7/26/2023 Not Ready for Inspection NICK DANERI
Green Building Final 7/26/2023 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 7/26/2023 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 7/26/2023 Not Ready for Inspection NICK DANERI
SUSMP-Std. Urban Storm Water 7/26/2023 Not Ready for Inspection NICK DANERI
Smoke Detectors 7/26/2023 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 7/26/2023 Not Ready for Inspection NICK DANERI
Final 8/1/2023 Not Ready for Inspection NICK DANERI
Green Building Final 8/1/2023 Not Ready for Inspection NICK DANERI
Reinforced Concrete Frame 8/1/2023 Not Ready for Inspection NICK DANERI
Reinforced Masonry Frame 8/1/2023 Not Ready for Inspection NICK DANERI
SUSMP-Std. Urban Storm Water 8/1/2023 Not Ready for Inspection NICK DANERI
Smoke Detectors 8/1/2023 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 8/1/2023 Partial Inspection NICK DANERI
Final 9/27/2023 Not Ready for Inspection NICK DANERI
Green Building Final 9/27/2023 Approved NICK DANERI
Reinforced Concrete Frame 9/27/2023 Approved NICK DANERI
Reinforced Masonry Frame 9/27/2023 Approved NICK DANERI
SUSMP-Std. Urban Storm Water 9/27/2023 Approved NICK DANERI
Smoke Detectors 9/27/2023 Approved NICK DANERI
Verify Sprinkler Sign Off 9/27/2023 Approved NICK DANERI
Final 9/29/2023 Partial Approval NICK DANERI
Final 10/6/2023 Not Ready for Inspection NICK DANERI
Final 10/23/2023 Partial Inspection NICK DANERI
Special/Order Compliance 2/6/2024 Conditional Approval NICK DANERI
Final 3/14/2024 Conditional Approval NICK DANERI